Title: SELBY%20STORM%20DRAIN%20IMPROVEMENT%20DESIGN
1SELBY STORM DRAIN IMPROVEMENT DESIGN
- Anne Arundel County
- Department of Public Works
- Presented by
- Shannon Lucas, P.E.
- Brightwater, Inc.
2OBJECTIVE
- MINIMIZE OR ELIMIINATE FLOODING FROM FREQUENT
SMALL STORMS - Storms of 1- to 2-year frequency are causing
flooding in the community - 1-year storm 2.7 inches in 24 hours
- 2-year storm 3.2 inches in 24 hours
- IMPROVE WATER QUALITY OF STORMWATER RUNOFF
- Use Low Impact Development SWMgt approaches
- MINIMIZE PRIVATE PROPERTY and UTILITY
ENCROACHMENTS
3Responsibility
- Residents of Chesapeake Bay Watershed
- Residents of the South River Watershed
- Impairments
- Nutrients (Phosphorous and Nitrogen)
- Total Suspended Sediment
- Fecal Bacteria
- Fish and Benthic Bio-assessment
- Doing our part taking the opportunity
-
Photo from southriverfederation.net
4CHALLENGES
- Selby Community has no adequate storm drain
system - Low vertical relief (flat slopes) make it
difficult to move stormwater runoff - High water table further impedes the management
of stormwater runoff - Jurisdictional wetlands limit management options
- Annual cleanout of existing stream channels and
wetlands is prohibited by regulations - Sanitary Sewer System constrains area for
retrofits
5PREVIOUS EFFORTS BY COUNTY
- Earlier Effort by County resulted in design with
very large multiple pipes that required raising
roads. - Interference with existing Sanitary Sewer System
became prohibitive. - There was no water quality improvement with the
earlier design. - Large pipes required substantial encroachment on
private property
6Old School Approach
- Get the water off the roads and into pipes as
quickly as possible - Size pipes to carry large storm events
- Concentrates runoff and moves it quickly to
downstream - Exacerbates problems downstream
- more water all at once
- erosive velocities
7CURRENT APPROACH
- Design for the frequent flooding events (2-year
storm) - Use Low Impact Development (LID) or Environmental
Site Design approach to reduce runoff volume to
downstream areas - Improve water quality of runoff using LID
techniques - Light touch
- Minimize conflicts with private property and
utilities
8LID APPROACHUsing bioswales
- Use Bioswales in upstream areas
- Infiltrate first few inches of runoff where soils
will allow - Use Swales with underdrains where soils wont
infiltrate - The swales will drain within 24 hours
- Swales support an attractive, functional
landscape plan
9LID APPROACH (continued)
- Swales slow the runoff enough to reduce
downstream flows in two ways - Storing runoff temporarily in swales and
underground in the soils actually reduces total
volume of runoff - Increasing the time for runoff to concentrate
reduces the magnitude of peak flows - Bioswales treat runoff and improve water quality
10Examples of BioSwales
11(No Transcript)
12(No Transcript)
13PROPOSED LAYOUT OF STORM DRAIN SYSTEM
14Location Existing Proposed
Fontron to Severn Segments of 15 and 18 CMP swales Bioswales, 15 RCP
Severn to 2nd Swales, 12x15 and 18 CMP, sump at I-6 18 RCP
2nd None 2-18 RCPs
2nd to Beach 2-12x18 CMP, swale (sump at I-1) 2-21 RCPs, enhance swale (deeper)
Beach 2-15x18 CMPs Extend swale and eliminate portion of pipe, headwalls and 3-18 RCP
First 15x20 CMP Headwalls and 3-18 RCPs
15QUESTIONS??