Title: Hydrologic%20Design%20and%20Design%20Storms
1Hydrologic Design and Design Storms
04/18/2005
- Readings Applied Hydrology Sections 13.1-13.2
2Hydrologic extremes
- Extreme events
- Floods
- Droughts
- Magnitude of extreme events is related to their
frequency of occurrence - The objective of frequency analysis is to relate
the magnitude of events to their frequency of
occurrence through probability distribution - It is assumed the events (data) are independent
and come from identical distribution
3Hydrologic design
- Water control
- Peak flows, erosion, pollution, etc.
- Water management
- Domestic and industrial use, irrigation, instream
flows, etc - Tasks
- Determine design inflow
- Route the design inflow
- Find the output
- check if it is sufficient to meet the demands
(for management) - Check if the outflow is at safe level (for
control)
4Hydrologic design scale
- Hydrologic design scale range in magnitude of
the design variable within which a value must be
selected - Design considerations
- Safety
- Cost
- Do not design small structures for large peak
values (not cost effective) - Do not design large structures for small peak
values (unsafe) - Balance between safety and cost.
5Estimated Limiting Value (ELV)
- Lower limit on design value 0
- Upper limit on design value ELV
- ELV largest magnitude possible for a hydrologic
event at a given location, based on the best
available hydrologic information. - Length of record
- Reliability of information
- Accuracy of analysis
- Probable Maximum Precipitation (PMP) / Probable
Maximum Flood (PMF)
6(No Transcript)
7TxDOT Recommendations
8Hydrologic design level
- Hydrologic design level magnitude of the
hydrologic event to be considered for the design
or a structure or project. - Three approaches for determining design level
- Empirical/probabilistic
- Risk analysis
- Hydroeconomic analysis
9Empirical/Probabilitic
- P(most extreme event of last N years will be
exceeded once in next n years) - P(largest flood of last N years will be exceeded
in nN years) 0.5 - Drought lasting m years is worst in N year
record. What is the probability that a worse
drought will occur in next n years? - sequences of length m in N years N-m1
- sequences of length m in n years n-m1
10Example 13.2.1
- If the critical drought of the record, as
determined from 40 yrs of data, lasted 5 yrs,
what is the chance that a more severe drought
will occur during the next 20 yrs? - Solution
- N 40, m 5 and n 20
11Risk Analysis
- Uncertainty in hydrology
- Inherent - stochastic nature of hydrologic
phenomena - Model approximations in equations
- Parameter estimation of coefficients in
equations - Consideration of Risk
- Structure may fail if event exceeds Tyear design
magnitude - R P(event occurs at least once in n years)
- Natural inherent risk of failure
12Example 13.2.2
- Expected life of culvert 10 yrs
- Acceptable risk of 10 for the culvert capacity
- Find the design return period
- What is the chance that the culvert designed for
an event of 95 yr return period will not have its
capacity exceeded for 50 yrs?
The risk associated with failure of culvert when
the flow exceed 95 yr flood in the next 95 years
is
The chance that the capacity will not be exceeded
during the next 50 yrs is 1-0.41 0.59
13Hydroeconomic Analysis
- Probability distribution of hydrologic event and
damage associated with its occurrence are known - As the design period increases, capital cost
increases, but the cost associated with expected
damages decreases. - In hydroeconomic analysis, find return period
that has minimum total (capital damage) cost.
14(No Transcript)
15Beargrass Creek Case Study
- Description of the Study Area
- Hydrology Hydraulics
- Economic Analysis
- Project Planning
- Assessment of the Risk Based Analysis Methodology
From Risk Analysis and Uncertainty in Flood
Damage Reduction Studies, NRC Report
http//www.nap.edu/catalog.php?record_id9971
16Beargrass Creek Study Area
Ohio River
North Fork
Middle Fork
South Fork
61 mi2 Drainage Area
Buechel Br
17Levee on the Ohio River
18Pump Station at the Levee(Capacity 7800 cfs!)
19Concrete-Lined Channel
20Detention Pond
Inlet Weir
21Beargrass Creek at the Detention Pond
Pond Outlet Pipe
22Damage Reaches
South Fork Beargrass Creek (12 miles)
1
15
14
13
Example Reach SF-9
12
11
2
10
Buechel Branch (2.2 miles)
5
9
3
4
7
6
4
8
3
2
5
1
23Beargrass Creek Case Study
- Description of the Study Area
- Hydrology Hydraulics
- Economic Analysis
- Project Planning
- Assessment of the Risk Based Analysis Methodology
24Flood Frequency Curve (SF-9)Separate curve for
each reach and each plan
25Uncertainty in Frequency CurveReach SF-9,
Without Plan Conditions
Prob Mean (cfs) Mean 2 SD Mean -2 SD Log10 (SD)
0.01 4310 3008 6176 0.0781
0.5 1220 1098 1356 0.0229
26Water Surface Profiles
South Fork Beargrass Creek (202 cross-sects)
1
15
14
13
12
11
2
Buechel Branch (61 cross-sects)
10
5
9
3
4
7
6
4
8
3
2
5
1
27Water Surface Profiles
28Uncertainty in Stage-Discharge
Constant
Reduces prop. to depth
SD 0.5 ft at 100 yr flow
29Beargrass Creek Case Study
- Description of the Study Area
- Hydrology Hydraulics
- Economic Analysis
- Project Planning
- Assessment of the Risk Based Analysis Methodology
30Computation of Expected Annual Damage (EAD)
Discharge (Q)
Discharge (Q)
Exceedance Probability (p)
Stage (H)
Damage (D)
Damage (D)
Stage (H)
Exceedance Probability (p)
31Damage Categories
- Single-family residential
- Multi-family residential
- Commercial buildings
- Public buildings
- Automobiles
- Cemeteries
- Traffic disruption
- Utilities
32Structures
p0.002
p0.01
p0.1
p0.999
33Index Location
- Each damage reach has an index location
- All structures are assumed to exist there
- First floor elevation adjusted to reflect the
change in location within the reach
p0.01
Index for SF-9
p0.1
p0.5
Invert
Rm 10.363
Rm 10.124
Rm 9.960
34Building Damage
- Value of the structure, V
- Value of the contents, C kV
- kV/C, contents to value ratio (40)
- Damage is a function of depth of flooding,
expressed as ratio,r(h), of value
Depth, h r1(h) r2(h)
3ft 27 35
6ft 40 45
35Uncertainty in Building Damage
- Value of structure,
- SD10 of V for residential
- Commercial distribution described by
- Value of contents (SD of k in CkV)
- Uncertainty in first floor elevation, SD0.2ft
- Uncertainty in damage ratios, r(h)
36Stage-Damage Curve
Multi-family Residential, Reach SF-9
37Stage-Damage Curves
- Each structure is treated individually
- Stage-damage curve with uncertainty is produced
for each damage category for each reach - Added together to give the total stage-damage
curve for the reach(?)
38Beargrass Creek Case Study
- Description of the Study Area
- Hydrology Hydraulics
- Economic Analysis
- Project Planning
- Assessment of the Risk Based Analysis Methodology
39Planning Team
- Three key people
- Planner formulates project alternatives, works
with local sponsor - Hydraulic Engineer determines discharge and
stage data - Economist estimates damage, costs, benefits and
does the risk analysis
40Planning Methodology
- Identify potential project components (detention
ponds, levees, ) - 22 initially proposed, 11 on Beargrass Creek, and
11 on Buechel Branch - Evaluate them all individually to see if net
benefits are positive - 8 components on Buechel Branch eliminated
- Combine components into plans, incrementally
- 10 components in NED plan 8 detention ponds,
1 floodwall, 1 channel improvement
41Three Plan Development Reaches
1
1
15
14
13
2
12
11
2
10
3
5
9
3
Buechel Branch
4
7
6
4
8
3
2
5
1
42Risk of Flooding
- Establish a target stage at each damage reach
index point - Find annual probability of exceeding that stage
- Find reliability of passing design floods
Target Stage
43Assessment of Engineering Risk
F(h)
- Conditional probability
- Assumes a particular flood severity
- Annual probability
- Integrates over all flood severities
- Risk measures actually used
- Annual exceedance probability
- Conditional nonexceedance probability
1
Exceedance probability
Nonexceedance probability
0
H
Target Stage
44 Computation of Engineering Risk Measuresfrom
the Stage-Frequency Curve
Q
H
H
Q
Target Stage
H
f1(Qp)
H
f2(HQ)
f3(Hp)
p
p
Q
pe
p
p
Q
- Annual exceedance probability
- Find pe for target stage at each Monte Carlo
replicate - Get expected value and median of pe values over
all simulations - Get long term risk as 1-(1-pe)n
- Conditional nonexceedance probability
- Find H for given p at each replicate
- Find of replicates for which H lt Target stage
45(No Transcript)
46Beargrass Creek Case Study
- Description of the Study Area
- Hydrology Hydraulics
- Economic Analysis
- Project Planning
- Assessment of the Risk Based Analysis Methodology
47Overall Assessment
- The core methodology is solid and is an advance
in engineering practice of flood risk assessment - Focus is completely on damage reaches considered
as statistically independent entities - Whole project risk and 25,50,75 damage values
cannot be built up this way - Can specification of standard deviations of
analysis variables be improved?
48Beargrass Creek 100 year Flood Plain Map
Middle Fork
South Fork
49Spatial Subdivision of the Region
Spatial Unit Used for
Whole River Expected Annual Damage (EAD), Benefit-Cost analysis
3 Main River Reaches Incremental analysis to get NED plan
22 Damage Reaches Basic unit for analysis using HEC-FDA
263 Hydraulic Cross-sections Water surface elevation profile computation
2150 Structures Structure inventory
50Whole Project Risk Assessment
- Take a flood of severity, p, and integrate the
damage along the reach - Without any plan (o)
- With a plan (w)
- Benefit of plan is B Do - Dw
- Randomize the flood discharge and stage for the
whole project rather than for each reach - Compute project-based damage values for each
randomization and use them to get B25, B75 values