Title: Status of the Powering Interlock system
1Status of the Powering Interlock system
- Markus Zerlauth Bruno Puccio
- AB-CO-IN
2Architecture
LHC Ref DB
PVSS Operator Console (in the Field Control Room
or CCC )
Ethernet Technical Network
PLC in non-radiation area
PIC
Profibus
Power Converter
Power Converter
QPS
PC_PERMIT
Power Converter
QPS
Power Converter
QPS
QPS
CIRCUIT_QUENCH
PC_FAST_ABORT
Remote I/O (close to clients)
POWERING_FAILURE
DISCHARGE_ REQUEST
PC_DISCHARGE_ REQUEST
ABORT
UPS
Beam Permit
Beam Interlock sys.
AUG
336 PICs for 28 Powering Subsectors, managing
1600 electrical circuits, using more than 1000
cables, handling 2400 interlock signals
4PIC Racks in UA83
for A.L8
for X.L8
for M.L8
5Hardware Commissioning planning for the PIC
Interlock team composed of only 3 people (Markus,
Robert Pierre)
Validation of commissioning performed via
automated procedures tools
Individual test of the PIC
PIC involved in short-circuits tests
Powering Tests
Additional resources still expected (time needed
for training of personnel)
6Status of the different levels of the project
(1/3)
- Despite initial delay the activity is progressing
well - (thanks
to Frederic Hervé) - Lab tests are going to start soon
- ALARMS and PM have to be included
-
(discussions started, tbc)
PVSS layer
Ethernet Technical Network
7Status of the different levels of the project
(2/3)
PVSS layer
Ethernet Technical Network
- PLC program is working and functionality tested
- Together with PVSS tests, communication tests to
be started - Worry about CPU module performance
- bug in the last version available on the market
- acknowledged from Siemens but no change before
next generation (in 2006?)
Equipment layer CPU part
PIC
Profibus
8Status of the different levels of the project
(3/3)
PVSS layer
Ethernet Technical Network
Equipment layer CPU part
PIC
Profibus
I/O part
- For the different boards, patch-panels,
sub-units - Prototypes validated
- Entering now in the pre-series phase
- all hardware foreseen for end of July
- Wiring and assembly will be made at CERN
-
(workshop and/or Interlock
Team)
9Summing-up
- Preparation in progress no show-stopper for the
3 layers (PVSS side, Siemens CPU I/O parts) - 2 PICs are going to commissioned in Sep.05
- 2 others PICs for the Arc 7-8 in Dec.05
- One more in UA83
- One in UJ76. Radiation issues gt system moved in
TZ gallery? - The units will be fully tested in the lab in
August gt dismounted and re-mounted in the
undergrounded area by the interlock Team. -
- Dependencies issues?
- All copper cables (TS/EL) are already there
-
(check performed for LSS8L, and partially done in
large part of LHC) - UPS should be present in the racks (gttbc)
- Ethernet should be OK (gttbc)
- Remote Reset connection should be OK (gtGuy)
In conclusion (for the time being) we are
optimistic to be on time!