Machine Protection System Commissioning Plans - PowerPoint PPT Presentation

About This Presentation
Title:

Machine Protection System Commissioning Plans

Description:

Many thanks to the Members of the MPS Commissioning Working ... External Properties (LDB) Property Values (test variables) Parameters (historical tracking) ... – PowerPoint PPT presentation

Number of Views:25
Avg rating:3.0/5.0
Slides: 25
Provided by: uyth
Category:

less

Transcript and Presenter's Notes

Title: Machine Protection System Commissioning Plans


1
Machine Protection System Commissioning Plans
  • Jan UythovenMany thanks to the Members of the
    MPS Commissioning Working group, The MP Working
    Group and the LHC Commissioning Working Group.
    Special thanks to R. Schmidt and J. Wenninger

2
Outline
  • Introduction
  • The Commissioning of the MPS has started!
  • Plans for further Commissioning and follow-up
  • Conclusions

3
Introduction
  • Core elements of the LHC Machine Protection
    System
  • Beam Interlock System
  • Beam Dumping System
  • Beam Loss Monitoring System
  • Collimation System
  • Quench Protection System Powering Interlocks
  • Injection System
  • Together with other elements they will need to
    guarantee the safety of the LHC equipment
    protection
  • Detect any equipment state or beam state that is
    potentially dangerous
  • Dump the beam before damage to equipment can
    occur
  • This safety of the system needs to be guaranteed
    (SIL 3) by
  • Good system design
  • Redundancy between subsystems
  • Redundancy within critical subsystems
  • Reliable system components
  • Careful follow-up during production and
    installation
  • Thorough commissioning of the system
  • Individual System Tests
  • System commissioning with and without beam

4
The LHC Machine Protection System Interfaces
Movable Detectors
Beam Loss Monitors BCM
Experimental Magnets
Environmental parameters
LHC Devices
Collimator Positions
LHC Devices
Safe Beam Parameter Distribution
LHC Devices
SpecialBLMs
LHC Experiments
Collimation System
Transverse Feedback
Beam Aperture Kickers
Operator Buttons CCC
Safe LHC Parameter
Software Interlocks
Sequencer
Beam Dumping System
Beam Interlock System
Safe Beam Flag
Injection Interlock
Powering Interlocks sc magnets
Powering Interlocks nc magnets
Magnet Current Monitor
Beam LifetimeFBCM
Screens / Mirrors BTV
Access System
Vacuum System
Beam loss monitors BLM
RF System
Timing System (Post Mortem Trigger)
Monitors aperture limits (some 100)
Monitors in arcs (several 1000)
Power Converters
Magnets
QPS (several 1000)
Power Converters 1500
AUG
UPS
Cryo OK
Doors
EIS
Vacuum valves
Access Safety Blocks
RF Stoppers
5
Commissioning has Started!
  • LHC Hardware Commissioning
  • Individual System Tests of LHC on the way
  • Experience of MPS equipment with the powering of
    the first LHC sector
  • SPS operation 2006 and 2007
  • Fast Magnet Current Change Monitoring in 2006 and
    later in 2007
  • Beam Interlock Systems following same design as
    LHC BIS being used for
  • CNGS and TT40/TT60 (towards LHC!) extraction
    interlocking
  • SPS ring interlock in 2007
  • LHC-like beam permit loop with clients connected
    to the dump through one of the 6 BICs connected
    to the loop
  • Safe Beam Flag for CNGS operation
  • Proof of the hardware and the design choices
    that have been made
  • Experience concerning commissioning and
    operations of systems similar to those that will
    be used in the LHC

6
SPS Extraction towards to LHC Using SPS
Extraction BIS
J.Wenninger
7
SPS extraction BIS information
Signals as seen on an oscilloscope for testing
the interlock system
Beam Energy Tracking System considers dipole DCCT
and HV of extraction kicker Same hardware as for
the LHC Beam Dumping System (but reverse logic)
8
SPS extraction BIS information
Bar graph summarising the status of the interlock
system
9
Fast Magnet Current Change Monitor MBG 4101M
Interlock Triggers at 10-4 change of I nominal
FMCM triggers _at_ 3984.4 10E-4
3 FMCMs were operational last year and tested
following well defined procedures. Modified CERN
types (better adapted for pulsed magnets and
additional controls interface) will be installed
later this year
M. Zerlauth,Adapted DESY design
10
LHC Hardware CommissioningD2.L8 presently under
test
Quench event at 17018 ms
  • Presently being commissioned
  • Quench Protection System PIC system
  • Obtain experience with
  • Tools for Post Mortem and Logging
  • Sequencer

Current ramp
Current starts to change 17.027 ms
Quench heaters efficient 17.026 ms
Quench loop reading PIC 17021 ms
Signal to BIC
Quench detected 17018 ms
11
Plans for (further) Commissioning and follow-up
  • Thorough commissioning of the Machine Protection
    System
  • Individual System Tests
  • Part of the LHC Hardware Commissioning
  • LHC Cold Check-Out period (machine closed, ready
    for beam)
  • System commissioning with beam
  • Different phases depending on beam intensity and
    beam energy
  • Special attention to the links between the
    different systems

Most hours of MPS testing before first beam, Some
systems completely tested before beam ?
12
100 Tested before First Beam
Movable Detectors
Beam Loss Monitors BCM
Experimental Magnets
Environmental parameters
LHC Devices
Collimator Positions
LHC Devices
Safe Beam Parameter Distribution
LHC Devices
SpecialBLMs
LHC Experiments
Collimation System
Transverse Feedback
Beam Aperture Kickers
Operator Buttons CCC
Safe LHC Parameter
Software Interlocks
Sequencer
Beam Dumping System
Beam Interlock System
Safe Beam Flag
Injection Interlock
Powering Interlocks sc magnets
Powering Interlocks nc magnets
Magnet Current Monitor
Beam LifetimeFBCM
Screens / Mirrors BTV
Access System
Vacuum System
Beam loss monitors BLM
RF System
Timing System (Post Mortem Trigger)
Monitors aperture limits (some 100)
Monitors in arcs (several 1000)
Power Converters
Magnets
QPS (several 1000)
Power Converters 1500
AUG
UPS
Cryo OK
Doors
EIS
Vacuum valves
Access Safety Blocks
RF Stoppers
13
MPS Commissioning Working Group
  • Sub working group of the LHC Commissioning
    Working Group
  • Six meetings since November 2006,
  • 20 Members
  • Two people per main system
  • Engineers in charge
  • a few others
  • Webpage http//lhccwg.web.cern.ch/lhccwg/MPS/mps.
    htm

Mandate of Sub-Working Group on the Commissioning
of the Machine Protection System   " Produce the
detailed (step by step) description of the
commissioning of the LHC Machine Protection
System and record the test results. " The aim is
to have a first version available by June / July
2007. 
...but was defined with circulating beam in mind
for November 2007
That is going to be tight.
14
Detailed Procedure for Each System
  • Follow standard format for tests to be performed
    at the different phases
  • Identical to LHC HC strategy
  • To be published and approved by MPS comm. wg
    members
  • Specific tests are listed and tabulated

15
Format of the Procedures
16
Manufacturing and Test Folder (MTF)
  • Each Described Test is to be found back in the
    MTF system
  • The Status of the Test (passed, not passed,
    pending) and possible test reports are kept in
    this system
  • Identical system to what is being used for the
    LHC Hardware Commissioning
  • Many of the MPS tests will be done during the LHC
    Hardware Commissioning
  • Need to have compatible systems
  • MPS commissioning procedures can refer to LHC HC
    procedures

17
The Hardware Commissioning Manufacturing Test
Folder
B. Perea Solano
Organization of the stored information within
arborescence
18
Validation of the tests performed to the equipment
External Properties (LDB) Property Values
(test variables) Parameters (historical
tracking)
Report documents, journals, EDMS, etc.
19
Within MTF specific reports (views) can be
created to show the progress of the commissioning
as an example by region for all the systems
20
Status of Written Procedures
  • Some of the procedures exist and are well
    advanced, (almost) ready for distribution within
    edms
  • PIC, FMCM, Vacuum System
  • Advanced (already presented)
  • BIS system, BLM system
  • Next presentations
  • Injection System, WIC System
  • Outstanding main systems (but already worked
    upon)
  • Beam Dumping System, Collimation System
  • Other systems need to be assigned to people to
    write procedures
  • Experiments, RF Feedback, Aperture Kickers AC
    dipole, Safe Beam Flag etc.
  • After comments and approval to be described in
    MTF
  • Results of tests to be entered in MTF
  • Custom reports to be created to follow progress

21
Different Procedures Work in other Groups
  • LHC Hardware Commissioning WG
  • Procedures per System create for MPS if it does
    not exist
  • LHC Commissioning Working Group
  • Procedures are given per phase of LHC
    Commissioning
  • First Injection (pilot), energy ramp, increasing
    the intensity etc.
  • MPS commissioning
  • Procedures are per System, over all phases

22
Besides Procedures
  • MPS Commissioning Working Group is a forum to
    discuss different items related to the MPS
    commissioning and operation
  • Establishes a team of experts who can be called
    in during LHC operation when required
  • Training for Engineers In Charge

23
Topics concerning the MPS under discussion in the
different working groups
  • BLM operation
  • Which thresholds to set?
  • Proposed 30 of quench level, for the arcs, this
    concerns operational efficiency and not machine
    protection
  • When and How to change BLM settings?
  • Are remote changes via Management of Critical
    Settings more risky than a local change?
  • Procedure for disabling single BLMs when required
  • Protection settings (collimators) during the
    different phases of LHC commissioning
  • Relation with limits on beam parameters (beta
    beta, orbit etc.) during the different
    commissioning phases
  • Interlocking Strategy of the Aperture kicker and
    Ac Dipole
  • Based on keys and LHC Safe Beam Flag

24
Conclusions
  • The Commissioning of the LHC Machine Protection
    System has already started
  • LHC Hardware Commissioning
  • SPS extraction and ring Beam Interlock System,
    FMCM
  • Proof of the hardware design choices that have
    been made
  • Experience concerning commissioning and
    operations of systems similar to those that will
    be used in the LHC
  • To guarantee a Safe LHC operation, the
    commissioning procedures of the different MPS
    components
  • Are being described in detail following a fixed
    format, distributed and agreed upon
  • Will be followed up in the Manufacturing and Test
    Folder
  • A lot of work still to be done
  • On paper (procedures, MTF, reports)
  • In reality, following the paper work
  • The fruits of the work should be
  • Limited confusion during LHC commissioning, with
    and without beam
  • Never see the destructive potential of the LHC
    being confirmed
Write a Comment
User Comments (0)
About PowerShow.com