Title: Layer0 Status Andrei Nomerotski 2/3/2005
1Layer0 Status Andrei Nomerotski 2/3/2005
- Outline
- Introduction
- Module Production
- Assembly of Layer0
- Electronics
- System tests
- Schedule
- Mechanical and Installation issues will be
covered in Bill Coopers talk -
2Overview
- Layer0 will improve impact parameter resolution
and mitigate degradation of performance caused by
radiation damage to the SMT inner layers after
3-4 fb-1 - Important for tracking b-tagging at high
luminosity and for Bs mixing measurement - Layer0 uses RD and experience of the DZero Run2B
Silicon Upgrade - Many components prototyped in advance
- Contributing institutions Brown,
CINVESTAV,Fermilab, Fresno, UIC, U.Indiana,
U.Kansas, Kansas State, Louisiana Tech,
U.Mississippi, MSU, Moscow State, NorthWestern,
Rice, Stony Brook, U.Washington, Zurich
3Layout of Layer0
- 6-fold symmetry, total 48 modules, 96 SVX4
readout chips - 8 module types different in sensor and analog
cable length
Inside SMT
4Run2B Silicon Closeout
- Run2B closeout is complete
- Results on L2-5 stave and grounding RD on Layer0
have been presented at several instrumentation
conferences and published in proceedings. - NIM paper on the grounding RD submitted
- Though present Layer0 has a different design, the
original Run2B Layer 0 allowed to prototype many
aspects of the new design - CF support structure
- Grounding/noise issues
- Assembly issues
-
Original Run2B support structure
5Layer 0 Module Concept
- Sensor connected to hybrid with double-deck
analog cable
analog cable
sensor
hybrid
6Module Production
- We are in production since mid January 2005
- Had PRR in Nov 2004 very useful, implemented
many recommendations of the committee - 8 types of modules, 6 of each type
- Total 48 needed
- Have parts for 100 modules, plan to build 64
modules to select best 48 - During Sept-Dec 2004 built 14 preproduction
modules - Most of them used for system tests
- Will discuss below
- Production components
- Module assembly
- Status and Production rate
- Module QC
-
7Sensors
- Pitch 71/81 micron, intermediate strip, 70/120 mm
long four types - Ordered from HM 120 sensors (4 x 30) in March
2004 - Received 112 in July and 8 in November 2004
- All IV, CV tested at Fermilab
- 3 out of spec due to large DI/DV - used for
prototypes - Only one(!) bad strip pinhole on one of last 8
sensors - Out of 120 x 256 30720 strips
- spec 1
- Four sensors fully probed at Stony Brook
- Results consistent with HM
- Four sensors and test structures irradiated at
KSU - Measured at Stony Brook
- Built two modules, see later
8Pitch Adapter
- Two types of Pitch Adapter
- Ordered in June 2004, received in Oct 2004
(Seigert) - Satisfactory bond strength (6.8/- 0.8 g) and
etching quality - Before unsuccessfully tried two other vendors
- As backup ordered pitch adapters also from
Advanced Thin Film Products - Provided samples with very good pull strengths
- Received and evaluating first batches
- Building a module with this PA
9Analog Cable
- 8 types of cables required (4 pairs different in
length) - 128 signal lines per cable
- Max length 34 cm
- Ordered in March 2004, delivered in July 2004
(Dyconex) - Total 200 cables
- Testing visual inspection no bad channels
-
10Hybrid
- 48 hybrids required
- Had 267 tested SVX4.2B chips
- Received 119 hybrids in Sept 2004 (Amitron)
- 70 good, 49 out of spec
- out of spec cutoff edge off by 200 micron,
can be used with modified fixtures - Mechanical tests at Fermilab and KU
- Flatness lt 80 micron, thickness lt 800 micron
(both better than spec)
- Assembled 101 hybrids at NXGen and 10 at
Fermilab - Yield (before burn-in) 90
- 7 hybrids left unstuffed, 1 broken
- gt50 of hybrids are burnt-in (KU)
11Module Assembly Overview
- Sensor and spacer are glued to kapton wrap-around
circuit Spacers are glued to top cable - Bottom cable is glued to hybrid and pitch adapter
- SVX chip is wire bonded to the bottom cable
- Top cable is glued to bottom cable. Wrapping of
sensor is completed - Pitch adapter is glued to the sensor
- Cables are wire bonded to the pitch adapter and
SVX chip - Sensor is bonded to pitch adapter
Day 1
Day 2
Day 3
Day 4
12Module Assembly Fixtures
Stage 4
- A number of fixtures is required for all steps
- Typically have double quantity of fixtures
- Example below Gluing of analog cable
pitch adapter
hybrid
Stage 4
analog cable
Bond profiles for analog cable
13Assembled Layer0 Module
sensor
pitch adapter
SVX4
analog cable
hybrid
14Production Rate and Module QC
- Current status 10 production modules assembled
since Jan 13 - Current rate 4 modules per week
- Have all fixtures to boost production to 8
modules per week - Module QC
- Mechanical inspections
- I-V curve
- Burn-in 72 hours with 200V bias
- Encapsulation of HV and GND bonds
- Another short burn-in before storage
- Results analyzed and put into the module database
- So far three modules with 0 defects, two with 1
defect, one with many, others still need to be
tested - Additional module testing (done for a few
modules) - Several modules underwent long-term tests in
April-July 2004 - Built and tested two modules with irradiated
sensors (10 fb-1 equivalent) - Thermocycling
- Laser tests
15V-I plots
- Range 0-300V, typically current 50-150 nA,
correlates well with sensor current
16Examples of plots from hybrid burn-ins pedestals
L0 - 202
17Tests of Irradiated Modules Shot Noise
- Good opportunity to check that we understand
irradiated modules - Normally stored in the freezer - warmed up to
increase current - Current vs. Temperature dependence is in
agreement with expectations - Minimal increase of noise wrt non-irradiated
module at operational T - Observed rising contribution from shot noise with
rising T - Shot noise scales as sqrt(Integration time x
Current) - 1400 e for 396 ns integration time at T10oC
agrees with calculations
18Support Structure Assembly Fixture
Collar North
North Modules Holders
CF Support Structure
South Modules Holders
Collar South
Support Mount North
Base Plate 90x20
Middle Support
CF Support Structure
Support Mount South
Rotation Control
The fixture will be mounted on CMM Table Lab C
at SiDET
19Sensor Hybrid Holders
- Each module after mounting is tested electrically
20Layer0 Electronics
- Layer0 will use 48 readout channels now used by
Outer H-disks - Readout chain needs to be interfaced to Run2A SMT
electronics - New wrt Run2A Hybrid-Jumper Cable-Junction
Card-Twisted Pair Cable-Adapter Card - Adapter Card isolates Layer0 ground and detector
ground - Needed because South is shorted to North by the
support structure - SVX4 needs to coexist with SVX2
- Status of Cables
- Digital Jumper Cables (KSU KU)
- Production cables ordered from Compunetics in Jan
2005 - Have reduced thickness to 0.15 mm
- Twisted Pair Cable (KU) ready
21Junction Card
- Two channels per card
- Cable routing and dressing prototyped with mockup
- Design finalized, will be ordered in Feb
22Adapter Card
- Four channel per card
- Ground isolation tests done in Sept-Oct 2004
- Had good results with and without isolation
- Plan to reproduce them with the prototype support
structure - Design finalized, will be ordered in Feb
23System Tests
- Effects of possible interference with support
structure and between modules addressed with
setups at Sidet - Readout of modules installed on the support
structure - Readout of large number of channels, in the limit
full Layer0 - Testing at conditions similar to operations
addressed with setups at DZero - Use real DAQ with Trigger Framework
- Preparation and exercising of online software
- Cooling system / Thermocycling
-
24Prototype Support Structure
- CF support structure for Layer0 implements new
grounding approach laminated ground mesh
covering all surface crucial design feature
ensuring low inductance path for GND and hence
low noise - Prototype is electrically and mechanically the
same as final structure - Have 8 L0 modules mounted on the prototype
support structure since Nov 2004 - Simultaneous readout through simplified chain
modules installed on the support structure
25Results with Prototype Structure
- Low total and random noise (no Faraday cage)
- the grounding scheme works well
- Observe pedestal shapes at fast SVX4 settings
- Caused by digital-to-analog couplings between
hybrid and analog cable below the hybrid
Noise 1500 e S(MIP) / N 151 Coherent
noise very small
Noise for 4 modules
hybrid
cable
sensor
26Pedestal Shapes
- Pedestal peak-to-peak difference
- At fast preamp settings 6-7 ADC counts
- At slow settings 2 ADC counts - acceptable
- Other remedies
- It looks that most of pickup comes from clock
signals will have provisions to regulate clock
amplitude at AC - Have a spacer between hybrid and analog cable
- 0.2 mm spacer significantly reduces effect
- More testing in progress
Pedestals for 4 modules
fast preamp settings
10 ADC counts
slow preamp settings
10 ADC counts
27Plans for system tests at Sidet
- Feb 2005 Read out 10 modules on the support
structure through Junction Card-Twisted Pair
Cable-Adapter Card - Use prototype JumperCable-JC-TPC-AC
- Mar 2005 Read out the 10 modules though full
chain (above Sequencer VRB) - May 2005 Expand full readout to 48 channels
- June 2005 Read out full Layer0
- Use production JC-JC-TPC-AC
- Also thermocycle prototype support structure
with 10 modules (Feb 2005)
28System tests at DZero
- Installed two L0 modules, two hybrids, WIENER LV
PS and power distribution during the 2004
shutdown - Successfully read out in special runs
- Data is being analyzed, noise looks reasonable
- However these SVX4 strings are not yet in
operations, waiting for acceptable SEQC firmware - Have a stand at DZero with IB, SEQ and VRB crates
connected to Trigger Framework to debug firmware
- These SVX4 strings will be used
- To develop all slow control and monitoring online
software - Exercise offline software
- Measure S/N from real particles in the modules
4 ch. Adapter Card at HorseShoe
29Other Integration Issues
- Some remapping choreography of Layer0/Inner
H-disks/Outer H-disk readout and HV channels will
be required during 2005 shutdown - Isolated LV Supply (WIENER)
- Provides SVX4 power
- PS and heavy power cabling installed during 2004
shutdown - Power distribution to Adapter Cards will be
installed during 2005 shutdown - High Voltage Supplies
- Located outside of Collision Hall (in MCH2)
- Install more channels of Bira supplies
- Install new fanout box rated to 700 V
- Integrate new components to
- Slow Controls
- Interlock
- Online GUIs
30Schedule
- Hybrid production essentially done (1/25/2005)
- Junction/Adapter Cards production ends on
3/18/2005 - Module production ends on 4/22/2005
- Start module installation 4/1/2005
- Layer0 ready for system tests at Sidet on
5/11/2005 - Layer0 ready to go to DZero on 7/19/2005
- Main schedule risks are in
- Design and preparation of assembly fixturing
- Full system tests
31Summary
- Good progress on all fronts
- All parts in hand - started module production in
January 2005 - Layer0 assembly to start in April 2005
- Detector should be ready to go to DZero in July
2005 - Paying attention to system tests so far all
looks under control