Title: Status of Hydrogen System Development
1Status of Hydrogen System Development
Yury Ivanyushenkov, Tom Bradshaw, Elwyn Baynham,
Mike Courthold, Matthew Hills, Tony
Jones Applied Science Division, Engineering and
Instrumentation Department RAL
MICE Collaboration Meeting, Frascati, June 26-29,
2005
2Scope
- Hydrogen system
- - principal points
- - process and instrumentation diagram (PID)
- - layout
- Hydrogen RD
- - motivation and scope
- - work packages
- - components
- - layout
- Plans
3Conceptual points
- Individual hydrogen system for each of 3
absorbers. - Use of a metal hydride bed for hydrogen storage.
- Compact location of the components under
hydrogen extraction hood - close to the absorber.
4MICE hydrogen system layout Principle
- Argon jacketing of pipework is proposed in
outside the hood. Basic philosophy is shown below
H2sensor
Hood
Argon Jacketing
1m3
Cabinet for hydride bed and pipework
MICE
Safety area
5MICE hydrogen system (familiar sketch)
High level vent
High level vent
Vent outside flame arrester
Non return valve
Vent manifold
Vent manifold
0.1 bar
Hydrogen zone 2
Extract hood
VP2
PV8
P1
P
Metal Hydride storage unit (20m3 capacity)
P
PV7
P
PV2
PV1
Chiller/Heater Unit
1 bar
Tbed
Buffer vessel
Hydrogen supply
PV3
1 m3
PV4
P
Fill valve
P
HV1
Pre-cooling Out In
P2
P
0.5 bar
0.9 bar
Liquid level gauge
P3
HV2
Internal Window
P
P
Purge valve
P
P
P
LH2 absorber
Safety windows
Vacuum
Purge valve
HV3
Vacuum vessel
0.9 bar
Nitrogen supply
PV6
Helium supply
0.5 bar
VP1
Pressure gauge
Non-return valve
Pressure relief valve
Pressure regulator
Bursting disk
Valve
P
P
VP
Vacuum pump
6MICE hydrogen system PID
7MICE hydrogen system layout
8MICE hydrogen system layout (2)
9Hydrogen system development Scope
- To construct a prototype hydrogen handling system
at RAL which will become the first full system of
MICE - This will consist of 2 main parts
- The external system which will be in the final
form - to deliver H2 to the absorber and store the H2 in
the hydride beds - The safety system to vent H2 in failure modes- to
include relief valves and buffer volume - The dummy absorber
- The absorber will be simulated by a simple
cryostat with a containment vessel to contain 20
litres of H2 operated from a condensing pot
with a cryocooler
10Hydrogen system development Scope (2)
- The development programme will address the
following issues - Confirm the working parameters of a hydride bed
in the regimes of storage, absorption and
desorption of hydrogen ? - Purity of hydrogen and effects of impurities.
- Hydride bed heating/ cooling power requirements.
- Instrumentation and control required for the
operation of the system - Safety aspects including - safety relief valves,
sensors and interlocks and safety documentation - The RD programme will enable the final design
for the MICE hydrogen system to be confirmed and
the HAZOP to be completed.
11Hydrogen system RD Work packages
- WP1 Initial design -gt Internal safety review
- WP2 Detailed design and procurement
- WP3 Installation and commissioning
- WP4 Test Programme
12Hydrogen system RD WP1
- Initial Design
- H2 handling system
- Confirmation of
- components on H2 circuit diagram
- pipe sizes, mass flows, pressure drops, relief
valve specifications, venting, manifolding - vacuum and purging systems
- layouts in hall
- H2 zones
- basic specifications for purchased items
13Hydrogen system RD WP1 (2)
- Initial Design
- Dummy absorber
- Cryostat design
- H2 containment vessel, condensing pot, internal
pipework components - Pre - cooling heat exchanger etc
- Heater for load simulation and H2 boil off
- Instrumentation
- Data acquisition
- Outline definition of test programme and
proposals for fault condition simulation
14Hydrogen system RD WP1
- Conclusion of WP1
- Update cost estimates for main components
- Internal Engineering and Safety Review
- - Aim will be confirm the scope of the RD
programme and release the stage of WP2 detailed
design and procurement
15Tchill
16Hydrogen test cryostat Concept
- Instrumentation mimics what we will need on the
absorber for the control system and interlocks - Heater will regulate temperature of cryocooler
need redundancy and interlock with compressor - Dia.Reservoir height290mm
T
H
T
H
17Hydrogen Test Cryostat Outline
18Hydrogen test cryostat
19Hydrogen test cryostat (2)
20Instrumentation
- Capacitance-based level sensors (2 or even 3)
- (communicating with a supplier concerning choice
of a sensor) - Temperature sensors (PRTs)
- (standard components of any cryogenic system)
- Cartridge heaters
- (standard components)
21Control system
- Initial control sequence diagrams have been
developed - (example)
- Will be revised and completed
- Talking to ISIS and DL experts on hardware
implementation
22Provisional Hydrogen System Control
Sequence Control logic Fill Sequence
23 Metal hydride tank
Table 1 The specification of the MH tank for
RAL Â Hydrogen Storage Capacity
20 Nm3 Tank
Description Heat Transfer Medium
Water MH Weight
155kg Tank Total Weight
220 Kg Operating Condition Charging Gas
Component
Hydrogen of 99.99 purity Charging Gas
Pressure
1.2 barA Hydrogen Charging
Rate
70NL/min (up to 90 of Storage
Capacity) Discharging Gas Pressure
1.2
barA Hydrogen Discharging Rate
70NL/min (up
to 90 of Storage Capacity) Utility
Requirements Cooling Medium
Water Below -10? (At 20L/min) Heating Medium
Above 20? (At 20L/min)
- Status
- Waiting for a new quotation from the supplier
24Hydrogen RD Layout
25Hydrogen RD Phase I initial
26Hydrogen RD Phase I initial (2)
27Hydrogen RD Phase I final
28Hydrogen RD Phase I final (2)
29Hydrogen system RD Schedule
- Outline Schedule
- WP1 Initial design May August 05
- with Review in September 05
- WP2 Detailed design and procurement Aug 05 Feb
06 - WP3 Installation and commissioning Jan April
06 - WP4 Test Programme June Oct 06