Coppin State University - PowerPoint PPT Presentation

About This Presentation
Title:

Coppin State University

Description:

Biobehavioral Health Building The Pennsylvania State University Daniel Bodde Structural Option Advisor Heather Sustersic Building Introduction Existing Structure ... – PowerPoint PPT presentation

Number of Views:77
Avg rating:3.0/5.0
Slides: 46
Provided by: Cori69
Learn more at: https://www.engr.psu.edu
Category:

less

Transcript and Presenter's Notes

Title: Coppin State University


1
Biobehavioral Health Building The Pennsylvania
State University
Daniel Bodde Structural Option Advisor Heather
Sustersic
2
Presentation Outline
Building Introduction
Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
  • Location
  • The Pennsylvania State University University
    Park, PA
  • Project Size
  • 5 Stories above grade
  • Full basement (100 below ground)
  • Approximately 93,500 sqft
  • Cost
  • 40 Million

3
Presentation Outline
Existing Structure
Typical Section
  • Foundation System
  • Spread footing
  • Sits on bedrock (15 ksi)

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
4
Presentation Outline
Existing Structure
Typical Section
  • Foundation System
  • Spread footing
  • Sits on bedrock (15 ksi)
  • Superstructure
  • Concrete and composite metal deck

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
5
Presentation Outline
Existing Structure
Lateral Layout
  • Foundation System
  • Spread footing
  • Sits on bedrock (15 ksi)
  • Superstructure
  • Concrete and composite metal deck
  • Lateral System
  • Steel Moment Frames
  • Eccentric Braced Frame (Column Line 10)

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
6
Presentation Outline
Existing Structure
Eccentric Braced Frame
  • Foundation System
  • Spread footing
  • Sits on bedrock (15 ksi)
  • Superstructure
  • Concrete and composite metal deck
  • Lateral System
  • Steel Moment Frames
  • Eccentric Braced Frame (Column Line 10)

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
7
Presentation Outline
Problem Statement
  • Statement
  • Steel has become an unviable option as main
    structural material
  • Solution
  • Structural Depth - Redesign the structure using
    reinforced concrete with minimal impact on
    existing interior architecture and spaces
  • One-way slab with interior beam
  • Concrete moment frame

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
8
Presentation Outline
Problem Statement
  • Statement
  • Steel has become an unviable option as main
    structural material
  • Solution
  • Structural Depth - Redesign the structure using
    reinforced concrete with minimal impact on
    existing interior architecture and spaces
  • One-way slab with interior beam
  • Concrete moment frame
  • Façade Study Breadth Change façade to precast

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
9
Presentation Outline
Problem Statement
  • Statement
  • Steel has become an unviable option as main
    structural material
  • Solution
  • Structural Depth - Redesign the structure using
    reinforced concrete with minimal impact on
    existing interior architecture and spaces
  • One-way slab with interior beam
  • Concrete moment frame
  • Façade Study Breadth Change façade to precast
  • Schedule Impact Breadth Determine what impact
    the concrete redesign and precast façade have on
    the construction schedule

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
10
Presentation Outline
Structural Depth - Loads
  • Gravity Loads
  • Dead
  • Structure Self weight
  • Superimposed (5 psf)
  • Slate Floor (20 psf)
  • Live
  • Lobbies/Assembly (100 psf)

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
Typical floor layout
11
Presentation Outline
Structural Depth - Loads
  • Gravity Loads
  • Dead
  • Structure Self weight
  • Superimposed (5 psf)
  • Slate Floor (20 psf)
  • Live
  • Lobbies/Assembly (100 psf)
  • Lateral Loads
  • Wind (Controls)
  • Seismic

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
12
Structural Depth - Gravity
Presentation Outline
Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
13
Structural Depth - Gravity
Presentation Outline
  • One-way Concrete Slab
  • 5 Slab (Table 9.5a)
  • 5 _at_ 12oc (flexure)
  • 5 _at_ 10 (crack control)

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
14
Structural Depth - Gravity
Presentation Outline
  • One-way Concrete Slab
  • 5 Slab (Table 9.5a)
  • 5 _at_ 12oc (flexure)
  • 5 _at_ 10 (crack control)
  • Beams
  • Support slab
  • Run N-S
  • Supported by girders, edge beams, Columns
  • Flexure shear controlled design
  • 5 in corners for cage construction
  • Consistent concrete cross section

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
15
Structural Depth - Gravity
Presentation Outline
  • One-way Concrete Slab
  • 5 Slab (Table 9.5a)
  • 5 _at_ 12oc (flexure)
  • 5 _at_ 10 (crack control)
  • Beams
  • Support slab
  • Run N-S
  • Supported by girders, edge beams, Columns
  • 5 in corners for cage construction
  • Consistent concrete cross section

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
16
Structural Depth - Gravity
Presentation Outline
  • Girders
  • Run E-W
  • Supported by columns at both ends
  • Concentrated loads produce large moments
  • 2 shallower than existing steel structure
  • Assumed 50 sustained live load for deflections

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
17
Structural Depth - Gravity
Presentation Outline
  • Girders
  • Run E-W
  • Supported by columns at both ends
  • Concentrated loads produce large moments
  • 2 shallower than existing steel structure
  • Assumed 50 sustained live load for deflections

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
18
Structural Depth - Gravity
Presentation Outline
  • Girders
  • Run E-W
  • Supported by columns at both ends
  • Concentrated loads produce large moments
  • 2 shallower than existing steel structure
  • Assumed 50 sustained live load for deflections

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
19
Structural Depth - Gravity
Presentation Outline
  • Girders
  • Run E-W
  • Supported by columns at both ends
  • Concentrated loads produce large moments
  • 2 shallower than existing steel structure
  • Assumed 50 sustained live load for deflections
  • Edge Beam
  • Run perimeter of BBH Building
  • Concentrated load produces torsion
  • Added longitudinal transverse reinforcement
  • Supports masonry

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
20
Structural Depth - Gravity
Presentation Outline
  • Girders
  • Run E-W
  • Supported by columns at both ends
  • Concentrated loads produce large moments
  • 2 shallower than existing steel structure
  • Assumed 50 sustained live load for deflections
  • Edge Beam
  • Run perimeter of BBH Building
  • Concentrated load produces torsion
  • Added longitudinal transverse reinforcement
  • Supports masonry

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
21
Structural Depth - Gravity
Presentation Outline
  • Girders
  • Run E-W
  • Supported by columns at both ends
  • Concentrated loads produce large moments
  • 2 shallower than existing steel structure
  • Assumed 50 sustained live load for deflections
  • Edge Beam
  • Run perimeter of BBH Building
  • Concentrated load produces torsion
  • Added longitudinal transverse reinforcement
  • Supports masonry

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
22
Structural Depth - Lateral
Presentation Outline
  • Concrete Moment Frame
  • Does not affect interior architecture.
  • Stiff beam to column connection

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
23
Structural Depth - Lateral
Presentation Outline
  • Concrete Moment Frame
  • Does not affect interior architecture.
  • Stiff beam to column connection
  • Wind Loads
  • Case 1 Case 2 Controlled

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
24
Structural Depth - Lateral
Presentation Outline
  • Concrete Moment Frame
  • Does not affect interior architecture.
  • Stiff beam to column connection
  • Wind Loads
  • Case 1 Case 2 Controlled
  • Relative Stiffness
  • 1 kip load applied to each frame
  • Calculated relative stiffness based on
    deflection.
  • Distribution of wind loads

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
25
Structural Depth - Lateral
Presentation Outline
  • Concrete Moment Frame
  • Does not affect interior architecture.
  • Stiff beam to column connection
  • Wind Loads
  • Case 1 Case 2 Controlled
  • Relative Stiffness
  • 1 kip load applied to each frame
  • Calculated relative stiffness based on
    deflection.
  • Distribution of wind loads
  • ETABS
  • Line elements with proper material section
    properties
  • Columns 0.70Ig
  • Beams 0.35Ig
  • Verified output with hand calculations

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
26
Structural Depth - Lateral
Presentation Outline
  • Column Design
  • Corner, Interior, Exterior
  • Resists axial flexural loads

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
27
Structural Depth - Lateral
Presentation Outline
  • Column Design
  • Corner, Interior, Exterior
  • Resists axial flexural loads
  • Design Checks
  • Lateral Displacement lt H/400
  • 0.9DLW

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
28
Structural Depth Cost Impact
Presentation Outline

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
29
Façade Study Breadth
Presentation Outline
  • Existing Façade
  • Traditional hand placed brick limestone
  • Held back by 8 fully grouted CMU
  • Flashing, weep holes, air barrier
  • Heavy Expensive

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
30
Façade Study Breadth
Presentation Outline
  • Existing Façade
  • Traditional hand placed brick limestone
  • Held back by 8 fully grouted CMU
  • Flashing, weep holes, air barrier
  • Heavy Expensive
  • Alternative Façade
  • Thin brick precast panels
  • Made in controlled conditions
  • Faster Construction

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
31
Façade Study Breadth
Presentation Outline
  • Thin Brick Precast
  • Typical Layout
  • Hung from edge beams
  • Kickback provide lateral support

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
32
Façade Study Breadth
Presentation Outline
  • Thin Brick Precast
  • Typical Layout
  • Hung from edge beams
  • Kickback provide lateral support
  • Thermal Moisture Resistance
  • Sandwich Wall
  • Provides rain barrier thermal resistance

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
33
Façade Study Breadth
Presentation Outline
Cost Impact
Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
34
Schedule Impact Breadth
Presentation Outline
  • Construction Sequencing
  • Sequence 1 Col Line 1-5
  • Sequence 2 Col Line 5-10

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
35
Schedule Impact Breadth
Presentation Outline
  • Construction Sequencing
  • Sequence 1 Col Line 1-5
  • Sequence 2 Col Line 5-10
  • Assumptions
  • Reinforcement starts 1-3 days after forming
    starts
  • Wait 7 days for concrete cure before construction
    on next floor

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
36
Schedule Impact Breadth
Presentation Outline
  • Construction Sequencing
  • Sequence 1 Col Line 1-5
  • Sequence 2 Col Line 5-10
  • Assumptions
  • Reinforcement starts 1-3 days after forming
    starts
  • Wait 7 days for concrete cure before construction
    on next floor
  • Key Completion Dates
  • Concrete redesign Feb 3, 2012 (3 months)
  • Alternative precast façade Mar. 15, 2012 (-6
    months)

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
37
Conclusion
Presentation Outline
  • Structural Depth
  • Successful concrete redesign
  • Met all serviceability requirements
  • Minimal impact interior architecture layout

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
38
Conclusion
Presentation Outline
  • Structural Depth
  • Successful concrete redesign
  • Met all serviceability requirements
  • Minimal impact interior architecture layout
  • Façade Study Breadth
  • Matched existing thermal moisture protection
  • Cheaper
  • Fast Construction

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
39
Conclusion
Presentation Outline
  • Structural Depth
  • Successful concrete redesign
  • Met all serviceability requirements
  • Minimal impact interior architecture layout
  • Façade Study Breadth
  • Matched existing thermal moisture protection
  • Cheaper
  • Fast Construction
  • Schedule Impact Breadth
  • Develop an adjusted schedule
  • Structure 3 months
  • Façade -6 months

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
40
Acknowledgments
Presentation Outline
  • Massaro CM Services
  • Tim Jones
  • Jim Kephart
  • Keith Smith
  • Robert Silman Associates
  • Dipa Makim
  • The Entire Penn State Faculty
  • Family Friends

Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
41
Presentation Outline
Building Introduction Existing Structure Problem
Statement Structural Depth Façade Study Breadth
Schedule Impact Breadth Conclusion Questions
Comments
Questions Comments
42
Appendix
Weight Comparison
43
Appendix
44
Appendix
45
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com