Title: AGENDA ITEM NO 13
1AGENDA ITEM NO 13 CLUSTER BOARD Date 14 July 2011
REPORT OF Director of Finance
DATE OF PAPER 28 June 2011
SUBJECT Finance Report for the two months ended 31 May 2011
IN CASE OF QUERY, PLEASE CONTACT Mrs Claire Yarwood 0161 212 4835
PURPOSE OF PAPER This paper provides an update to the Cluster Board on the financial position for Greater Manchester for the first two months of 2011-12. PURPOSE OF PAPER This paper provides an update to the Cluster Board on the financial position for Greater Manchester for the first two months of 2011-12.
2Contents
- 1. Key Financial Performance Dashboard
- 2. Summary Financial Position
- 3. Risks
- 4. Cost Improvement Programme Performance
- PCT Performance Exception Report
- 6. Capital Investment Programme
- 7. Recommendations
31 Key Financial Performance Dashboard
Review Commentary Year to Date Rating Year End Rating
Revenue The current revenue position after two months is a cumulative surplus of 2,167k, which is slightly behind the planned year to date surplus of 2,604k. PCTs are forecasting achievement of the planned surplus of 14,717k for 2011-12 although this is based on limited information from providers at this early stage in the financial year, and dependent on the achievement of significant levels of QIPP savings.
Capital To date there has been minimal spend of 382k against a total net capital resource limit of 14,716k.
Cash PCTs are largely drawing down cash in accordance with their plans, with the exception of NHS Bury (1.3 ahead of plan) and NHS Trafford (0.56 ahead of plan). No PCTs are currently indicating a requirement for cash in excess of their allocation.
Provider Breakeven NHS Stockport and NHS Bolton are the only PCTs with provider arms. NHS Stockport has reported a year to date surplus of 122k due to lower than planned pay costs and NHS Bolton is reporting a break even position. Both PCTs are forecasting that their provider arms will break even in 2011-12. Both PCTs are planning to transfer their provider services to Acute Trusts during 2011/12
42 Summary Financial Position
Surplus / (Deficit) YTD Surplus / (Deficit) YTD Surplus / (Deficit) YTD
Resource Limit Opening in-year allocation Budget Actual Variance Forecast Surplus
000's 000's 000's 000's 000's
NHS Ashton Leigh and Wigan 573,073 602 486 (116) 2,726
NHS Bolton 488,691 96 79 (17) 1,000
NHS Bury 316,152 5 0 (5) 250
NHS Heywood Middleton and Rochdale 396,762 270 270 0 2,000
NHS Manchester 1,032,509 56 135 79 1,000
NHS Oldham 422,179 335 0 (335) 2,015
NHS Salford 476,052 691 691 0 2,260
NHS Stockport 482,475 111 233 122 667
NHS Tameside and Glossop 429,940 166 166 0 1,000
NHS Trafford 379,322 272 107 (165) 1,799
Total Greater Manchester 4,997,155 2,604 2,167 (437) 14,717
53 Risks
63 Risks
- There are a number of financial risks that are
included in the PCTs forecast financial position
however the magnitude and certainty of these
risks is variable. The table on the previous
page lists the major risks and the potential best
and worst cases. Currently the most likely
positions are included in the forecast outturns
and are mitigated by contingencies, under spends
on developments and strategic initiatives. - Each PCT has assessed the risks applicable to
their financial position and commissioned
services. Whilst some risks are specific to
particular PCTs, the risks relating to secondary
care contracts, QIPP delivery and prescribing
spend are common to most PCTs. - This format of presenting financial risks is new
to some PCTs, and therefore the information
contained within this schedule at month two
should be treated with caution. However, this
will continue to be developed with Organisations.
6
74 Cost Improvement Programme (CIP) Performance
Resource Limit Opening in-year allocation CIP Plan CIP Plan as of Resource Limit CIP Forecast
000's 000's 000's
NHS Ashton Leigh and Wigan 573,073 12,700 2.2 12,700
NHS Bolton 488,691 9,300 1.9 5,944
NHS Bury 316,152 26,903 8.5 26,903
NHS Heywood Middleton and Rochdale 396,762 10,478 2.6 10,938
NHS Manchester 1,032,509 20,243 2.0 23,238
NHS Oldham 422,179 0.0
NHS Salford 476,052 2,258 0.5 3,379
NHS Stockport 482,475 8,180 1.7 8,180
NHS Tameside and Glossop 429,940 10,200 2.4 10,200
NHS Trafford 379,322 15,300 4.0 15,300
Total Greater Manchester 4,997,155 115,562 2.3 116,782
84 Cost Improvement Programme (CIP) Performance
- NHS Bury has the highest CIP target as a
percentage of revenue resource limit, at 26.9m.
Of this amount, 21.7m or 81 of the schemes are
rated as high risk at month two, but this is a
slight improvement over the plan position.
However, achievement of CIP at month two is only
1.4m , which is 2.6m behind plan, but further
analysis will be undertaken over the course of
the next two months to evidence the savings. - NHS Manchester set an initial CIP target of
20.2m and then added a further 50 to allow for
slippage on schemes, optimism bias, and to
provide a potential contingency for any
deterioration in the underlying financial
position. Detailed plans have been drawn up by
consortia leads and other budget holders to
address 23m of the revised 30m target and are
currently working on proposals to achieve the
balance. However significant savings are
anticipated from service agreements, with over
50 of the original target covered by block
contract arrangements and therefore these have
been achieved. The highest risk areas are in
schemes to save costs in relation to secure
mental health and running costs. - NHS Stockport is reporting achievement of 6.8m
of the 8.2m CIP savings at month two, and 4.6m
of this relates to a 2 reduction in elective and
unscheduled care contracts. If these contracts
over perform later in the year, the PCT will
report this as a cost pressure rather than an
underachievement of CIP.
- NHS Bolton are currently forecasting an under
achievement against their CIP plans of 3.4m, of
which 2m is related to prescribing schemes and
based on holding spend to 2010-11 levels, and
1.4m is for demand management schemes.
However this is expected to improve as the
programme takes effect but will be closely
monitored.
95 PCT Performance Exception Report
- PCTs are currently forecasting achievement of
the planned surpluses totalling 14,717k. This
is the surplus control total agreed with the
Strategic Health Authority. Therefore achieving
the planned 2 recurrent headroom target. - The year to date position is a surplus achieved
of 2,167k against a budgeted position of
2,604k, with the majority of the
underachievement contributed by NHS Ashton Leigh
and Wigan, NHS Oldham and NHS Trafford.
However, as expected at this stage of the
financial year, many of the sources of
information used to generate forecasts are not
available, most notably prescribing,
collaborative commissioning and other provider
activity monitoring reports. Most PCTs have
incorporated month one activity from their main
provider into their forecasts. - NHS Bury has a number of financial recovery
schemes in place, and those related to secondary
care, prescribing and continuing care in
particular have had a slower impact than
anticipated. NHS Bury is forecasting achievement
of the target surplus on the basis that in year
savings on financial recovery schemes will be
made to mitigate any recurrent shortfall. To
date, there have also been non recurrent savings
in other areas and work will be undertaken to
secure these savings recurrently. - NHS Manchester has identified forecast overspends
of 6.3m, mainly within prescribing (2m), mental
health non secure contracts (2m) and
specialist/collaboratively commissioned services
(1m). There are ongoing negotiations between
NHS Manchester and Manchester City Council
regarding the settlement of mental health non
secure over performance for 2009-10, the 2010-11
mental health pool contribution and pooling
resources for 2011-12. - Currently all PCTs are assuming that the full
amount of the 2 non recurrent top slice will be
returned in 2011-12 and be available for planned
non recurrent expenditure.
105 PCT Performance Exception Report
- NHS Oldham are in the process of developing
dashboards to provide evidence based reporting
on CIP achievements including financial benefits
realised, and therefore whilst banked savings
at month two are low, it is anticipated these are
understated. The financial position is being
closely monitored by Cluster and Locality
Director of Finance.
10
116 Capital Investment Programme
PCT CAPITAL PROGRAMME PCT CAPITAL PROGRAMME PCT CAPITAL PROGRAMME PCT CAPITAL PROGRAMME PCT CAPITAL PROGRAMME PCT CAPITAL PROGRAMME PCT CAPITAL PROGRAMME
Plan Plan Plan Forecast Forecast Forecast
Expenditure Disposals /Grants /IFRIC-12 Charge against CRL Expenditure Disposals /Grants /IFRIC-12 Charge against CRL
NHS Ashton Leigh and Wigan 2,068 (1,633) 435 2,068 (1,633) 435
NHS Bolton 16,130 (11,925) 4,205 15,930 (11,725) 4,205
NHS Bury 1,558 (592) 966 966 966
NHS Heywood Middleton and Rochdale 925 (340) 585 925 (340) 585
NHS Manchester 3,718 0 3,718 3,718 0 3,718
NHS Oldham 15,346 (16,942) (1,596) 15,981 (18,212) (2,231)
NHS Salford 3,954 (831) 3,123 3,954 (831) 3,123
NHS Stockport 2,092 (427) 1,665 2,092 (427) 1,665
NHS Tameside and Glossop 1,105 (340) 765 1,105 (340) 765
NHS Trafford 1,900 (1,050) 850 1,900 (1,050) 850
48,796 (34,080) 14,716 48,639 (34,558) 14,081
126 Capital Investment Programme
- Although there has been very little expenditure
to date on the capital programmes, all PCTs are
forecasting to remain within the net Capital
Resource Limit for 2011-12. - Approximately 6.3m of capital expenditure is
dependent on the disposal of assets, all to non
NHS bodies, and PCTs have programmed capital
schemes to commence only when disposals are
certain. However, there is a risk that if
disposals are delayed until later in the year,
that there will be insufficient time to complete
planned schemes and there may be capital resource
limit under spends which cannot be carried
forward to 2012-13. - IT schemes total 4.4m and work is currently
being undertaken to review the nature of planned
expenditure and determine whether efficiencies in
procurement and/or implementation are possible
across the Greater Manchester footprint.
12
137 Future Performance Management Information
- In future reports information will be presented
on the following areas of financial performance - Performance against main provider contracts
- Delivery of running cost targets/paybill
- Non recurrent 2 expenditure plans
148 Recommendations
- 8.1 The Cluster Board is asked to note the
contents of the report. - 8.2 The Cluster Board is asked if the
information contained within or proposed is
sufficient to meet the needs of Board members,
given full detailed financial reports will be
prepared for Locality Boards. Any comments can
be sent directly to Mrs C Yarwood.