Title: FNAL
1- FNAL
- Hugh Montgomery
- Fermilab
- October, 2007
2Organisation Issues
- Fermi Research Alliance was awarded the contract
to operate Fermilab for 5 years with possibility
of up to 20 years, if performance is good. - FRA is partnership between U. Chicago and URA.
- FRA Board of directors, Chair is Bob Zimmer,
President of U. Chicago. - Board has 7 URA regional representatives
- Physics Sub-committee still exists and they
organize a Physics Visiting Committee review.
3Organisation Issues
- FY2008 Budget As last year there is a Continuing
Resolution, so the year starts as a continuation
of last year, No new starts, no increases for
projects on the rise. - Divisions and Sections had a preview in July but
we have not distributed a strawman budget, nor
heard responses. - In DOE OHEP, Robin Staffin has moved on to be an
advisor to Ray Orbach, OHEP has Acting Head,
Dennis Kovar, who was Head of Nuclear Physics for
many years. - We are developing a budget briefing for Dennis
for Wednesday, October 31.
4Long Range Planning
- Steering Group
- Chair Deputy Director -Young Kee Kim
- Committee 50/50 Fermilab-Non Fermilab
- Plan US Accelerator Based Future supporting ILC
- Report in September 2007
- If ILC decision is delayed
- Build 6 GeV ILC Linac
- 2 GeV LINAC front end
- Feed 8 GeV to Accelerator complex and physics
- Eg gt 2 MW for 120 GeV protons for LBL Neutrino
Program - 8 GeV protons for muon and kaon program
- Recommendations are under discussion by everyone
- Accelerator and Physics Workshops in November
5Tevatron Performance
Tevatron peak and integrated luminosities
62007 Accelerator Shutdown
- Accelerator work appears to have gone well
- Significant work on several of the machines
- Experiments confined efforts to remedial work
- Silicon Readout recoveries
- CDF Silicon Cooling system
- All Experimenters Meeting at 4 pm TODAY Curia
II
7Shutdown 2007
8Shutdown 2007
9Shutdown 2007
10Vulnerability Review
- Director commissioned a review of experiment
vulnerability - What can we expect to break?
- With what vulnerability?
- What are appropriate remedial actions?
- Committee
- Chair Dan Green array of detector experts
- Excellent Cooperation from the experiments
- No Show stoppers
- Need to work on preserving corporate knowledge
and expertise
11Neutrino Program
12SciBooNE
13MINOS Results
14MiniBooNE Results
15Future Neutrino Experiments
- MINERvA
- Neutrino Cross Sections
- To be mounted in front of MINOS Near Detector
- RD and construction preparation is well advanced
- Has full completed all CD3 requirements, awaiting
ESAAB (Nov. 1 ) and start of construction - NOvA
- Long Baseline, Off Axis from NuMI
- Enormous Far Detector
- Lots of RD and design work complete
- Successfully completed CD2 Baseline review
- Construction start of Road in Minesota in Spring
2008 - BNL-FNAL Long Baseline Study
16P5 Committee
- Tevatron Running in 2009 June 2007
- Concerned with
- the continued good progress of integrated
luminosity - The understanding of the collaboration manpower
- The understanding of the Laboratory support for
operations - Conclusion was clearly positive
- Tevatron Running in 2010 September 2007
- Wanted to see physics progress
- Understand opportunity cost
- Anticipated nothing new on effort front
17Tevatron Luminosity Delivery for Run II
FY10 start
Real data for FY02-FY07
FY09 and FY10 integrated luminosities assumed to
be identical
FY08 start
18Criteria for Tevatron Runningin FY 2010
- Pier Oddone
- September 24, 2007
19Criteria for running in 2010
- Important Physics
- Viable Collaborations
- Acceptable damage to other programs
20Important Physics
- We explore uniquely a large variety of physics at
the energy frontier until LHC detectors overtake
us - Sensitivity to 160 GeV Higgs at 95 CL, opens in
the next year - Low mass Higgs (Standard or lowest lying MSSM
Higgs below 150 GeV) is hard to reach early with
the LHC
21Road to Higgs and Beyond
?
Total Inelastic
BsBs Oscillation, ?b Discovery Precision Meas.
jets (qq, qg, gg)
mb -
-
-
bb
observed
?b -
MW 0.05
W Z
Mtop 1.2
nb -
-
tt
Observed WZ, Evidence for ZZ and Single Top
WZ, Single Top, ZZ
pb -
Higgs
WH,ZH
MHiggs lt ? GeV at 95 CL
Low Mass SUSY
fb -
-
-
-
100 120 140 160 180 200
Higgs Mass GeV/c2
22SM Higgs Searches
23Constraint MSSM (CMSSM)
With Electroweak precision measurements and cold
dark matter density (WMAP, )
Sven Heinemeyer, Georg Weiglein
24W and Top Mass, and SM Higgs
Will Tevatrons prediction and observation/exclusi
on agree with what LHC sees?
25SM Higgs Searches at Tevatron
26Important Physics
- From first collisions at the LHC in Summer 2008
and closure of Tevatron September 2009 is too
short for LHC detectors to wipe CDF/D0 out - Any delay in putting the hardware together no
float now - Delay in first beam to collisions only three
months now - Natural time to accumulate luminosity
- Debugging detector and software
- Physics analysis
27Viable Collaborations
- The collaborations should be viable through
FY2009 - To ensure collaborations are viable in FY2010, we
need to start working now to make sure there are
enough students/post-docs and know how - Early results from LHC could negatively impact
the collaborations in 2010 if most folks were to
decamp Should we be so lucky!!
28Viable Collaborations
- Conversely, if there are delays in getting
results from LHC, the Tevatron remains exciting,
producing physics for students/postdocs/faculty - In the middle, there could be a horse race to the
Higgs - To keep collaborations viable need agency support
of University groups for work at the Tevatron
beyond 2010
29Acceptable damage
- Running in 2010 delays slightly 700kW neutrino
beam capability - Running in 2010 has modest impact on NOvA
start-up (presently shut-down starts late 2010
physics run June 2011) - Requires additional resources not to slow down
the ILC RD, Project X, or neutrino program
approximately 30M
30Conclusion
- We believe strongly that DOE should plan to run
through FY2010 - An early recommendation by P5 would help the
planning effort for the lab and collaborations.
31Conclusions for IFC
- 2007 has been a very active year for Fermilab on
every front. - Accelerator and Detector Operations in 2007 were
great - Physics Output from Tevatron Collider is
phenomenal - Shutdown work was successfully accomplished
- Accelerator Complex is starting up
- With P5 we have
- Recommendation for 2009 running
- Proposed running Tevatron in 2010 decision in
2008. - Looking forward to a productive 2007