Title: US CM EMU - FNAL Site
1US CM EMU - FNAL Site G.Apollinari - Lyon Sep.
98
Status of the FNAL Site (also visit
http//tdpc01.fnal.gov/uscmsemu) Chamber RD
Engineering Status Procurement Status Status of
Setup of FNAL Site Factories Pre-Production
Prototypes Schedule/Site Organization
2Chambers RD
- Chamber Assembly
- Need
- Evaluation of flatness
- Plane Gap Uniformity (/- 12 mils)
- Dry Assembly of M234/2 Pro-production Prototype
- Test of Assembly Table
- Chamber Deflection in Horizontal Vertical
Position - Effects on Plascore Specifications
- Wire Quality
- Luma vs. Sylvania just started, presentation on
D0 gold flaking problem - Panel Cleaning
- Machine Needs in progress
3Chambers RD
- Panels Measurements
- Panels flat of a 5x10 granite table under their
own weight - Measured bowing in the y (acceptable) and x
(un-acceptable) directions
4Chambers RD
- Chamber Sagging
- Final Assembly
- bottom panel straight (5 mils)
- top panel sags (70 mils)
5Chambers RD
- Chamber Sagging
- Buttons-Gap Bars difference
374 mils
Still 30 mils unexplained
6Chambers RD
- Panels Deformation
- We believe the PLASCORE panels we are working
with have a 1/32 (20-30 mils) bow in the 5
direction - String Measurements on free standing panels.
- Laser Tracker measurements on granite table (see
slide) - Under gravity, for a single panel sitting on the
gap bars - Q Which kind of force is a sagging panel
exerting on the next lower panel through the
button ?
Sag (0 mils)
Sag (40 mils)
7Chambers RD
- Panels Deformation
- Measured the displacement vs. force for a panel
surface by pulling or pushing close to the button
hole location (for both orientations of a panel).
- For small displacements 1 lb./1 mil
elastically - Q Which kind of deformation do we have close to
a button hole for forces of the order of
10-20 lb. ? - Instron Measurements at TD Material Lab
8Chambers RD
- Grooves Depth
- Issue
- Avoid skips during the machining of the panels
- Grooves of different depths are exposing
approximately the same amount of G10 fibers - Panels with grooves of different depths have the
same mechanical strength.
9Engineering Status
- Work in Progress
- Tooling
- Finalization of Carts Drawings and Assembly Tools
- Gerber and Axxion transport cart
- In-process Panel Trans. Solder
- Chamber assembly Table
- Chamber Transport and RTV Gas Sealing Cart
- Tooling Design for Plascore QA/QC
- PLASCORE had no in-process QA capability
- Release for Procurement of the Cosmic Test Stand
- FNAL FAST Sites
10Engineering Status
- Work in Progress
- Chambers
- M234/2 Drawings Check
- Completed by V. Razmyslovich
- Check and finalize Engineering Drawings
generate Bills of Material - Started Activity on IHEP. PNPI drawings expected
by mid Oct. 98
11Engineering Status
- Goal
- Engineering Drawings completed and released for
ME234/2 by Dec. 98 - Plan
- Receive Wisconsin frames drawings by end Sep. 98
- Integrate Chamber Frames in Oct. 98
- Ready to proceed for the release pending approval
by L2. - Estimate 2-3 weeks for implementation of
engineering changes - November EDR
- Presentation of the current status, including all
the information provided to FNAL
12Procurement Status
- Major/Critical Procurements
- PLASCORE Panels
- Requirements and Specifications Understood..
- Available Panels
- Fail our specs in a single panel measurements
on a granite table. - Sagging problems in gap bars constrained
configuration prevented us from measuring a 10
mils bowing over 2 feet. - the Receive Wisconsin frames drawings by end Sep.
98 - Visit to PLASCORE (Aug. 98)
- PLASCORE has no tooling for QC. FNAL will provide
it ( Sep. 98) - PLASCORE identified 3 areas of possible
improvements - Core Cutting on 5 feet wide table
- Core Thickness measurement
- Control of the area of pressure on the Gluing
Press - Will order 14 panels with the above-mentioned
improvements
13Procurement Status
- Major/Critical Procurements
- Wire
- Specification writing based on D0 experience.
- RD on 1-2 Gold-Tg SYLVANIA wires.
- RD of flaking gold ? Which QC/QA does LUMA apply
? - Good QA Plane needed.
- Panel Cleaning Machine
- Impossible to do RD on final chamber
- Will make systematic measurements on interstrip
resistance and water retention on sample panels.
14Pre-Production Schedule
- Pre-production Milestones
- ME234/2 pre-production chamber ready Nov. 16
98 - ME2/1 pre-production chamber ready Dec. 8
98 - All pre-production chambers produced at MP9, with
the final tooling and training the final assembly
crew.
15Pre-Production Schedule
Example of List of Tasks (from schedule) for the
Winder Setup
- Thursday September 3, 1998
- Curtis Donner reassembles the electrical control
of the winding machine. - Friday September 4, 1998
- John Korienek Jon Blomquist setup the winding
machine. - 50 (bad) mm wire in Jons possession
- Oleg Prokofiev/Evgueni Borissov mount a panel for
the test - Karen Kephart sets up the N2 pressure needed for
the winding machine - Monday September 7, 1998
- Jon Blomquist winds a test panel
- Oleg Prokofiev/Glenn Smith eye-witness the
procedure - Week September 7-11, 1998
- Glenn Smith transfers all the panels the to MP9
- Glenn Smith transfers the Winding Machine to MP9
- Week September 14-16, 1998
- Glenn Smith, Evgeni Borissov, Kurtis Donner and
Jon Blomquist setup the winding machine in MP9. - Sherry Harrold and Oleg Prokofiev wind a panel
with bad wire, for a tension measurement by the
Purdue people.
16Site Organization
- Team Organization
- TD/PPD Agreement
- essential for
- tooling support
- tooling engineering for foreign sites
- Lab8, Lab 7 (PPD) and MP9(TD) interactions
- Organization Structure
17Setup of FNAL Site Factories
Production Flow
- FNAL Sub-sites
- Lab 8
- Gerber and Axxion Cutting
- MP9
- Chamber Assembly
- Kit Preparation
- Lab 7
- Cosmic Testing
- Chamber Repair
- Storage
- Need to be worked out
18Setup of FNAL Site Factories
- Lab 8
- Axxion Machine
- Head Alignment problems (PPD)
- Gerber Machine
- Floor Plan Available
- No Panel Cleaning Machine in Lab 8 (for now !)
- Panel Handling Tooling(Deering)
- Purpose
- Great Lakes (FNAL demo)
- Anver ( being contacted)
- Plans and Discussions
- Vendor and scheme choice by end-September
- PPD-TD Cost Sharing (i.e. Tooling vs. Building
Modifications)
19Setup of FNAL Site Factories
- MP9
- 20 of the building available to CMS-EMU
- All major mfg. tooling delivered to MP9 (winder
excluded). - Tooling setup in progress
- Clamping Table Oct. 98
- Gluing Table
- to be assembled fixed
- Solder Machine ready
- Wire Gluing Machine ready
- Ionized Cleaner ready
- Tension Measurement ready
- Clean Area ready
20Setup of FNAL Site Factories
Wire Tension and Position Measurement
Soldering Machine
21Clamping and Gluing Tables
Clean Area
22Setup of FNAL Site Factories
- MP9
- Pictures actually taken in Lab 6
Winding Machine operational and ready to be
moved
23Setup of FNAL Site Factories
- Lab 7
- Setup of Cosmic Test Stand
- space clearing
- floor modification
- space allocation
- Drawings Ready
- procurement for FNAL
- cost estimate for FAST sites
- Assembly by end-Oct.
24Setup of FNAL Site Factories
Cosmic Stand Setup (FAST Sites)
25Lyon Issues
- Chamber Production
- Start Chamber production after electronics
finalization. - P4 ready for Summer 99, chamber production
starting on Fall 99. - Engineering - FNAL Responsibilities
- Project Engineering definition of
responsibilities between FNAL (production) and
Wisconsin (Integration). - FNAL responsibilities for Foreign Sites.
- EDR
- Formal Reviewing ending with green light for
production. - Wisconsin (Integration) organize preparation for
EDR.