1
Warsaw CaseRevenue 5.2
  • Warsaw University of Technology
  • 2nd Revenue Seminar
  • Brussels, 29 June 2005

2
Warsaw
  • 1,6 million inh, agglomeration 2,4 million
  • 380 cars per one thousand inh.
  • Public transport share 66 of motorized trips
  • Revenues from farebox covering 45 of operating
    public transport costs
  • Congestion charging listed as longterm measure in
    policy adopted in 1995 but no plans to implement
    it in visible future

3
Parking charging - existing
4
Options
  • No charging (except parking charging)
  • Charging - toll cordon line around the center
    14 sq. Kms
  • Charging with revenues used to investment in a
    new arterial road with a bridge and rapid tram
    line.

5
Cordon
6
Gates
7
Traffic model
  • road traffic and PT
  • 383 zones (city 313, suburban - 70)
  • 2150 nodes
  • 2200 links (3923 km)
  • 7 trip categories

8
Options analyzed
  • Option 1 BAU
  • Option 2 tool - cordon with 33 gates
  • Option 3 revenues used for accelerating
    construction of crucial section of ring road with
    a bridge and rapid tram line can be financed
    using 28 months net revenues

9
FINDINGS
  • Road traffic reduction on the cordon
  • introduction of toll reduction by 30,
  • construction of additional North bridge (outer
    zone) no further impact
  • No of PT passengers crossing gates to the CBD
    area
  • introduction of toll growth 5,5 ,
  • additional North bridge small impact

10
FINDINGS
  • Speed increase (for vehicles)
  • whole area tool 0,6 km/h, toll plus bridge
    0,8 km/h
  • central area - tool 4,6 km/h, tool plus bridge
    5 km/h
  • Vehicle time saving in the whole network 4,5
  •  Welfare increase - ???