Title: Caltrans Changes SECTION 39
1Caltrans ChangesSECTION 39Hot Mix Asphalt
- Presented by
- Terrie Bressette
- Caltrans
2What Changed? TERMS
- Hot Mix Asphalt (HMA) Asphalt Concrete (AC)
- Rubberized HMA (RHMA) Rubberized AC (RAC)
- Open Graded Friction Course (OGFC) OGAC
- RHMA-G RAC (Type G)
- RHMA-O -O-HB RAC (Type O) (Type O-HB)
- Tack Coat Paint Binder (Tack Coat)
- Geosynthetic Pavement Interlayer
- Pavement Reinforcing Fabric (PRF)
3What Changed?Section 39 AC vs. HMA
- Old Standard Specifications
- Section 39 AC 12,000 Words
- New Amended to Read
- Section 39 HMA 18,000 Words
- SSPs
- Section 39 AC 21 SSPs
- 58,000 Words
- Section 39 HMA 12 SSPs
- 28,500 Words
4What Changed?Standard Special Provisions
- 12 SSPs from 30 Old SSPs
- 39-AAA HMA Type A B
- 39-BBB OGFC
- 39-CCC RHMA-G
- 39-DDD RHMA-O RHMA-O-HB
- 39-EEE HMA (Misc. Areas)
- 39-FFF Minor HMA
- 39-GGG Rumble Strips (Ground in)
- 39-HHH HMA-Lime Slurry
- 39-III HMA-Dry Lime
- 39-JJJ HMA-Liquid Anti-Strip
- 39-KKK Prime Coat
- 39-LLL Replace AC Surface
5What Changed?Standard Special Provisions
- New SSPs
- 39-MMM Large Stone Mix
- 39-NNN High Stability Mix
- 39-OOO Bonded Wearing Course (Gap-Graded)
- 39-PPP Bonded Wearing Course (Rubberized)
- District Requested
- Extra testing required by aggregate issues
- Lime-slurry marination required
6Section 39 CHANGESMix Designs
- Still Hveem Method of Mix Design
- Dense Graded HMA (Type A B) Rubberized HMA
RHMA-G - Mix Design by Producer
- State Verifies JMF with Plant Mix
- Mix design good for 12-months
- Flat Elongated
- Open Graded OGAC, RHMA-O O-HB
- Aggregate qualities and gradation by Producer
- State determines asphalt content
- Mix design good for 12-months
7Section 39 CHANGESMaterials
- Aggregate Qualities
- Gradation (TV Tolerance)
- LA Rattler
- Sand equivalent
- Crushed Particles (2-face New)
- Fine Aggregate Angularity (New)
- Flat Elongated (New)
8Section 39 CHANGESMaterials
- Mix Qualities
- Binder Content
- Air voids content
- Stability (Mix Production)
- HMA moisture content
- Voids in Mineral Aggregate
- (Mix Design Verification)
- Voids Filled with Asphalt (Mix Design Only)
- Dust Proportion (Mix Design Only)
9Section 39 CHANGESMaterials
- CT371 Pilot
- California Test (CT) 371 ? AASHTO T283-03
- In QC/QA projects for 2 years
- Estimate approx 25 projects / year
- Producer tests mix with CT371
- Chooses treatment choice (TSR ? 70)
- Test HMA at least once during production
- District Translab tests also (FIO)
- Data analysis repeatability, lab / lab,
- mix vs. production
10Section 39 CHANGESConstruction
- Processes
- Standard
- HMA (Type A B)
- RHMA-G
- OGAC RHMA-O
- Method
- Small quantities
- QC/QA - gt10,000 tons
- HMA (Type A B)
- RHMA-G
11Section 39 CHANGES(3 Construction Processes)
- Standard
- Applies to the majority of HMA.
- Contractor QC plan tests at least twice daily
- Compaction (91 97 of Rice)
- State will test and results will be used for
acceptance and pay
12Section 39 CHANGES(3 Construction Processes)
- Method
- Applies to very small quantities of HMA
- The contractor will not perform QC
- Method compaction with roller and temperature
requirements - State will test and results will be used for
acceptance and pay. - Default for compaction when layer lt0.15-ft
13Section 39 CHANGES(3 Construction Processes)
- QC/QA
- All HMA quantities greater than 10,000 tons.
- QC tests for each 750 tons of HMA
- State will verify gradation binder
- 1 verification per 5 QC tests
- Statistical evaluation of gradation, binder and
compaction for pay. - Verified contractor QC for gradation binder
- Sate cores for compaction (92 96 of Rice)
14Section 39 CHANGESProduction
- Materials Production Quality Program
- HMA PCC (soon)
- Weights and Measures
- Safety
- Limited production unit requirements
15Section 39 CHANGESPlacement
- Lift Thickness gt 3 X NMAS
- e.g. ¾-inch mix 0.20-ft layer and above
- ½-inch mix 0.125-ft layer
- Must comply for compaction
- Contractor may change gradation of mix if ¾ mix
and 0.15 to 0.20 layer - Not required for Method
- Thin blanket Maintenance
- Leveling, etc.
16Section 39 CHANGES
- HMA must meet all specification requirements
throughout production and placement. - First out of spec Contractor Fix
- Second out of spec Stop, test, show RE before
starting up - In-place out-of-spec material
- RE determines status on case-by-case
17Thank you