Title: Telecommunications Infrastructure Upgrade Project
1Telecommunications Infrastructure Upgrade Project
Overview of TIU at CSU Monterey BayBased on a
presentation from Cal Poly SLO
2Todays Presentation
- Project Description
- Project Construction Stage
- Project Equipment Stage
- Project Information Resources
3TIU Project Team
- Information Technology (IT_at_CSUMB)
- Gil Gonzales, Chris Taylor, Don Kiser, Justin
Clausen - Campus Planning Development (CPD)
- Niraj Dangoria, Robin Katsuki, Michael Tebo,
Mehul Mody, Katie Timmerman - Stage 1 Consultant P2S Engineering
- Bill Leming
- Stage 1 Contractor Golden State Utility Co.
- Contact will be through CPD project management
- Stage 2 Consultant - SBC
- Donna Schoenecker, CCNA
4How Did We Get Here?
- Integrated Technology Strategy (ITS)
- Developed by CSU campus presidents in 1993 at the
request of the Chancellor. - Serviced by Technology Infrastructure Services
(TIS) in the CO - Telecommunication Infrastructure Master Plan
developed in 1996. - System-wide telecommunication standards developed
(TIP Standards). - Funding provided by Prop 1A and PropĀ 47.
5Project Goals
- Establish the CSU minimum baseline
telecommunications standards for all state-funded
classrooms and offices. - Pathways (i.e., conduits)
- Media (i.e., fiber cables)
- Spaces (i.e., telecom rooms)
- Network Equipment (i.e., switches)
6Project Goal Eliminate inefficient, unsafe,
crowded Telecommunications spaces
7... and create this
Neat and tidy Well laid
out
8How Is It Structured?
- Primarily funded from the Chancellors Office
resources. - Campus implementation is divided into three
phases - CSUMB is at the end of Phase III. - Each campus project has two major components.
- Stage 1 - physical infrastructure (TII)
- Stage 2 - network electronics (ITRP)
9CSUMB TIU Milestones
Bid Create Documents
Out to Bid
Bid Awarded Contract Estab- lished
Construction
July 2005
May 2001
Sept 2004
Jan2007
2002
2003/2004
10CSUMB Schedule
- Notice To Proceed issued to contractor on July
5th, 2005 - Contractor has 21 days to submit rough schedule,
to be reviewed by Project Team - Schedule will be further refined as the project
gets underway, and updates will be made available
through various methods. - Contractor has 30 days to start construction set
up. - Entire project is 18 months
2003/2004
11TIU on the CSUMB Campus
- Buildings 41A and 11
- Intrabuilding cabling
- Outside Plant work
- Added Electrical Upgrade Project
12Buildings 41A and 11
- Bldg 41A New lights out, telecom facility
located in the Bldg 41 parking lot. - Proper power, grounding, racking, air
conditioning - Sized for the future of the campus
- Bldg 11 Expanded Shelter
- Shelter is maxed out, doubles the size
- Includes proper racking and grounding
- Additional space for TIU added cabling
13Construction Stage 1
- Phasing
- Pilot building Bldg. 23 UHR
- 4 to 7 buildings in a Phase
- Contractor allowed in no more than two concurrent
Phases
14Major Areas Affected
- Classrooms and computer labs.
- Faculty and staff office space.
- Network equipment spaces (e.g., Telecom Rooms).
- Streets and other outdoor spaces.
15Building List Group 1
- 001 Administrative Center 1
- 002 Administrative Center 2/Faculty Offices
- 003 Administrative Center 3/Faculty Offices
- 004 Classroom Module 1/Dean's Offices
- 006 Classroom Module 2/Dean's Offices
- 008 Service Learning Module
- 010 Classroom Module 3/Learning Assessment
- 011 Equipment Shelter
- 012 Library Learning Complex
- 013 Science Wet Lab
- 016 Dining Commons
- 017 Instructional Center West/Faculty Offices
- 018 Media Learning Complex
- 021 Student Services 1
- 023 Administrative Services
- 027 Teledramatic Arts Technology
- 028 World Theater
- 029 University Center
- 030 Music Hall
- 045 Sixth Ave Classrooms
- 045A Academic / Office Complex 2
- 046 SIVA Center Annex
- 047 SIVA
- 048 World Language Cultures
- 049 World Language Cultures
- 050 Science Wet Lab
- 058 Faculty Offices
- 070 Instructional Building
- 071 Visual / Public Arts Complex 1
- 072 Visual / Public Arts Complex 2
- 073 Visual / Public Arts Complex 3
- 074 Instructional Building
- 075 Instructional Support Archive
- 080 Student Services /Health Center
- 081 Black Box Cabaret / Student Center
- 082 Public Safety / Classrooms / Offices
- 084 Administrative Office / Support Services
- 086 Administrative Offices / Instructional Space
16Intrabuilding Cabling
- Building 23 Pilot
- Full Recabling / New TRs
- Buildings 2, 3, 13, 18, 21, 23, 27, 41, 43, 86,
84, 80, 91, 93, 98 - Partial Recabling and/or remodeled TRs
- Buildings 1, 4, 6, 8, 10, 45, 46, 47, 70, 74,
75, 81 - Test only
- Buildings 28, 29, 30, 50, 71, 72, 73
- Not In project
- Buildings 14, 15, 16, 17, 35, 36, 37, 44, 53,
97, 100, 508, all Dorms
17Out of Scope
- Group 2 Group 3 Buildings
- Group 2 buildings qualify for Stage 2
electronics, but not Stage 1 infrastructure. - Group 3 gets nothing, are either Foundation
buildings (dorms, dining commons) or unused
buildings. - Desktop Equipment
- Computers
- Telephones
- Printers
- Information Servers
- Telephone Switch
- Video Head-end
- E-mail, Home Drive, Banner
18Construction (cont.) Stage 1
- Building Notifications
- Two weeks prior to construction start.
- Signage at each building entrance.
- Meeting with building managers and key personnel.
- Regular Updates
- Web site
- FirstClass
- Office entrance notification
19Construction (cont.) Stage 1
- Hours-of-Work
- Interior work predominately 1000pm to 600am.
- Exterior work and remote work will be done during
typical contractor work schedule (700am-300pm). - Summer and breaks will allow some daytime work.
- Some interior work will require day time
construction.
20Construction (cont.) Stage 1
- Safety Security
- Contractor identification
- Inspection
- Overnight campus representative
- Daily inspections by the Project Team
- UPD will be involved
- Notice to end users about personal items or
sensitive information
21Construction (cont.) Stage 1
- Clean-up
- Every night.
- Classrooms and offices accessible during the day.
- With a few exceptions
22Construction/Equipment Integration
- Two step project
- Stage 1 Construction Vendor BerkTek/Ortronics
- Stage 2 Network Equipment Vendor Cisco
- IT_at_CSUMB.EDU will coordinate equipment
installation after the Stage 1 contractor
completes each phase of construction. - SBC is the Stage 2 supplier/contractor
23Equipment InstallationStage 2
- System Integrator SBC Data Services
- Equipment manufacturer Cisco Systems
- SBC will install Cisco network equipment in all
Group 1 2 buildings. - Will follow Stage 1 Construction for each phase
of buildings.
24Outside Plant work
- Manholes, Handholes, and Conduit
- Augments current infrastructure, currently a mix
of University installed and existing Army
infrastructure.
- Army infrastructure mostly impacted with unused
and un-reusable cable. - Removes some of the unusable cable.
- Places conduit and manholes near future
construction.
25Outside Plant work (cont.)
- Manholes, Handholes, and Conduit
- Replaces a number of Army tank weight rated
manhole lids with lighter versions
26Added Electrical Upgrade Project
- New underground utilities
- Building 32
- Removal of poles down 6th Ave. New Street
lighting - Closure of 6th Ave. from B St. to south driveway
of the Building 27 parking lot. - New electrical switch enclosures along 6th Ave.
27Campus Disruption
- Construction Trailer Park, parking lot at the
corner of 7th Ave. Inter Garrison. - Open trenches in the street.
- Limited to 200ft. open trench
- Traffic congestion.
- Increased traffic from contractor employees,
suppliers, inspectors (campus and non-campus
based), project team. - One lane streets where digging is occurring.
- Overnight Intrabuilding construction.
28Overnight Intrabuilding Construction
- TR construction, cable installation/termination/te
sting. - Access and security by CSUMB employee, dedicated
to the project. - Contractor must clean up before the end of each
night shift. - Buildings that are being recabled will have
parallel systems until cut over - Raised floors in Building 18 computer labs.
29Campus Wide Cut Over Process
- First cutover will be Building 11.
- Stage II cut over will be in groups of buildings,
yet to be determined, but will closely follow
construction phasing. - Phone switch cut over.
30Building Cut Over Process
- Depends on what happens in the Building.
- New TR and Full Recable 2 cutovers
- New room built by Stage 1 contractor.
- New cable installed by Stage 1 Contractor.
- Alcatel switch installed in new room and
connected to new cable, workstations and phones
changed to new cable, all by IT_at_CSUMB.EDU. - Old cable removed by Stage 1 Contractor
- During Stage II, Alcatel switch replaced by SBC
with new Cisco switch. - Remodeled TR/added cable/test only 1 cutover
- Room construction completed by Stage 1
Contractor. - New cable installed and tested by Stage 1
Contractor. - Workstations and phones moved to new cable by
IT_at_CSUMB.EDU. - Replaced cable removed by Stage 1 Contractor.
- Stage II Cutover by SBC.
31Outcomes
- New Building 41A Real MDF.
- Expanded Building 11.
- Increased fiber counts to every building in the
project. - Increased number and better located data ports
within each building. - All new station cable will be Category 6.
32Outcomes (cont.)
- All TRs grounded to industry standards
- All TRs will be cooled.
- Most TRs will be sized to TIPS, at least
increased in size where possible. - Augmented building to building conduit system.
- Redundant link between Building 41A and Building
11.
33Contacts
- Construction Information
- Michael Tebo, Project Manager, CPD
- x3820 michael_tebo_at_csumb.edu
- Katie Timmerman, Construction Manager, CPD -
Douglas E. Barnhart - x4262 katie_timmerman_at_csumb.edu
- Technology Information
- Chris Taylor, Network Services
- x3557 chris_taylor_at_csumb.edu
- Justin Clausen, Network Engineering
- x3601 justin_clausen_at_csumb.edu
- CSUMB Project Website
- http//it.csumb.edu/projects/tii
- Chancellors Office
- http//tis.calstate.edu/ -- general, ongoing
information