Instrument commissioning schedule - PowerPoint PPT Presentation

1 / 7
About This Presentation
Title:

Instrument commissioning schedule

Description:

Pre-ship review planned for early May, in Oxford (no date set) ... However, only 10 days lab time (possibly less) are available prior to this run. PALM-3000 ... – PowerPoint PPT presentation

Number of Views:30
Avg rating:3.0/5.0
Slides: 8
Provided by: Antonin7
Category:

less

Transcript and Presenter's Notes

Title: Instrument commissioning schedule


1
Instrument commissioning schedule
  • Antonin Bouchez
  • Team Meeting 7
  • 27 February, 2008

2
Palomar AO instruments
PHARO
SWIFT
P1640
  • Visitor instruments
  • Fiber nuller
  • LAMP
  • Future instruments
  • 888 Cam

3
Proposed observing schedule
  • May-July schedule is still uncertain due to
    proposed changes in LGS science night
    distribution.
  • April
  • April 9 1 night NGS engineering (PHARO
    re-commissioning)
  • April 10-11 2 nights NGS science
  • May
  • May 9-12 4 nights P1640 commissioning
  • May 13-14 2 nights LGS engineering
  • May 15-26 12 nights LGS or NGS science
  • June
  • June 12-13 3 nights SWIFT commissioning
  • June 14 1 night LGS engineering
  • June 15-25 10 nights LGS or NGS science
  • July
  • July 8-10 3 nights P1640 commissioning
  • July 11-14 4 nights NGS science
  • July 15 1 nights LGS engineering
  • July 16-23 up to 8 nights LGS science

3
4
PHARO
  • Modifications
  • Cradle modified to move PHARO 2.50 forward.
  • FM3 mounted to kinematic base.
  • FM3 enclosure cart suport post added.
  • Schedule
  • Early Feb. Initial image quality tests.
  • Mid-March Lab commissioning with PHARO.
  • AO in the lab through April 7.
  • April 9 1 night NGS engineering (PHARO
    re-commissioning)

4
5
Project 1640
  • Schedule
  • Pre-ship review planned for March 27, in New
    York.
  • Plan to ship by April 15.
  • Arrives at Palomar by April 28.
  • AO in lab April 13 - May 7.
  • April 13 - 27 Install SSMs (if not done
    previously)
  • April 28 - May 7 P1640 lab commissioning.
  • May 9 - 12 4 nights P1640 commissioning
  • July 8 - 10 3 nights P1640 commissioning
  • If SWIFT is delayed, P1640 could trade the three
    July commissioning nights for those in June.
  • If P1640 is delayed (some concern over vendor
    delays), May nights might have to be given back.

5
6
SWIFT
  • Schedule
  • Pre-ship review planned for early May, in Oxford
    (no date set).
  • Plan to arrive at Palomar by May 21.
  • AO in lab May 27 - June 10 (currently published
    schedule).
  • May 21 - 26 Instrument checkout without AO.
  • May 27 - June 10 Instrument lab commissioning
  • June 12 - 14 3 nights SWIFT commissioning
  • Subsequent commissioning runs requested in Aug.
    and Sep.
  • If SWIFT is delayed (some concern over detector
    procurement and testing), first commissioning run
    might slip to July. However, only 10 days lab
    time (possibly less) are available prior to this
    run.

6
7
Electronics rack locations
  • PHARO in rack 4
  • SWIFT and P1640 expect rack 6