QBPM system commissioning and concerns ATF2 Project Meeting - PowerPoint PPT Presentation

1 / 23
About This Presentation
Title:

QBPM system commissioning and concerns ATF2 Project Meeting

Description:

The QBPM system is the largest ATF2 instrumentation system ... Not easy disturbs ODR and feather' equipment. Preparation for testing QBPM ... – PowerPoint PPT presentation

Number of Views:27
Avg rating:3.0/5.0
Slides: 24
Provided by: mcr9
Category:

less

Transcript and Presenter's Notes

Title: QBPM system commissioning and concerns ATF2 Project Meeting


1
QBPM system commissioning and concerns ATF2
Project Meeting
  • System testing
  • Installation
  • Calibration
  • Schedule

2
QBPM project in ATF2 context
  • QBPM is the basis for most beamline tuning
  • The QBPM system is the largest ATF2
    instrumentation system
  • The system should be ready when operation begins
  • 2008
  • There will not be a stripline BPM system for
    commissioning

3
QBPM project in ILC instrumentation context
  • No large, high performance, ILC quality cavity
    BPM exists
  • This will be a demonstration project, in its own
    right, and will guide future ILC/FEL work
  • This may generate some additional effort
  • the QBPM system is large enough to provide
    experience with reliability and systematic errors
  • The ILC BPM system will depend on cavities must
    be able to engineer a robust system and have it
    tested
  • Initial experience with nanoBPM shows cavities
    can have significant systematic errors

4
Validation of performance comprehensive proof
specifications are met
  • Accuracy the quality of being near to the true
    value
  • Precision the quality of being reproducible
  • Resolution the minimum difference between two
    discrete values that can be distinguished
  • BBA provides the true value
  • Connection to magnet center must succeed at the
    few micron level ? define 3 microns
  • QBPM system must have adequate precision so that
    BBA need not be repeated too often ? define 1 day

5
Basic resolution requirement
  • 100 nm over 10s time
  • /- 200 micron range
  • Relative alignment between magnet and BPM should
    be better than this
  • These requirements support BBA

6
100 nm routine performance is the goal, with 3
micron longer term stability
  • Must be directly demonstrated.
  • Must be done with a set (gt3) of BPMs
  • How and where?
  • Not easy disturbs ODR and feather equipment

7
Preparation for testing QBPM
  • Test with or without quad?
  • Maybe test one with quad for BBA test
  • 2007
  • Movers
  • Precision of corrector current setting
  • Tests with correctors complement mover
  • Stiffeners for soft copper chambers
  • New spool pieces

8
QBPM calibration
  • Bench test plan
  • Electronics bench calibration
  • Electronics (cavity?) online calibration
  • Continuous gain monitoring
  • Initial phase offset measurements
  • Sign
  • Reference cavity(ies) performance and location

9
ATF Cavity BPM system 12.05
ATF (Inoue) 6553
BINP (SLAC) 6429
ATF2 6423
R
R
ATF2 downmix
downmix
downmix
LO Cornell
downmix
Complicated multi-frequency system Reliability /
LO
Digitizer - Struck
714 / 2.16
10
Mark Slater - Cambridge
11
(No Transcript)
12
(No Transcript)
13
(No Transcript)
14
(No Transcript)
15
(No Transcript)
16
(No Transcript)
17
(No Transcript)
18
(No Transcript)
19
(No Transcript)
20
(No Transcript)
21
(No Transcript)
22
(No Transcript)
23
Schedule
  • Initial testing December 2005
  • Results not available calibration using mover
    not possible
  • Many on-board mechanical failures ? now fixed (J.
    May)
  • Second prototype complete April 10
  • Testing at ATF during 2 weeks operation
  • Assuming success production complete June 5,
    2006
  • 1 (2?) VME crates and controllers with Struck
    (SIS) 14 bit digitizers
  • 70 channels (35 BPMs) spares (10)
  • RF infrastructure (LO, cal, triggering) complete
  • Mechanical details?