Near the end of the Construction Phase? When MEP ... the commissioning plan Responsibilities (Cont.) CONSTRUCTION MANAGER Manage the ... business we cross ... – PowerPoint PPT presentation

Number of Views:226
Avg rating:3.0/5.0
Slides: 67
Provided by: Informat2070
Learn more at: https://sdashrae.org
Category:

less

Transcript and Presenter's Notes

Title: The%20Benefits%20of%20Building%20Commissioning


1
The Benefits of Building Commissioning
  • Carl N. Lawson
  • Hanson Professional Services Inc.

2
Rapid City South Dakota
  • ASHRAE

3
  • We are told never to cross a bridge until it is
    finished.
  • In this business we cross bridges every day
    that have not been finished.
  • And we will continue to do so.

4
What is the Total Building Commissioning Process
(TBCxP)?
  • A Quality Process
  • to VERIFY and DOCUMENT
  • that building systems and assemblies
  • meet the needs of
  • BUILDING OWNERS and OCCUPANTS.

5
What is TBCxP?
  • Owner orientated
  • Team Responsibility
  • Continuous improvement
  • Lower cost, more profits
  • Consistent delivery of construction projects

6
  • So, why are we here and what does TBCxP have to
    offer?

7
Essential Concept of TBCxP
  • It takes the uncertainty out of the delivery of a
    constructed projects
  • Does as well as any other approach, but at a
    lower cost
  • Has means to use statistical tools based upon
    probability distribution of outcome or based upon
    random estimate of expected outcome distribution
  • Has an element of continuous improvement
  • Transfers knowledge from planning to operations

8
Goals of TBCxP
  • Document owners goals and requirements
  • Keep project team focused on owners goals
  • Prevent or eliminate problems inexpensively
  • Lower overall costs for the owner
  • Increase profits for project team by decreasing
    costs

9
TBCxP Best Practice
  • Cost effective
  • Owners Project Requirement orientated
  • Team (commissioning process team)
  • Quality tools used
  • Orientated on delivery of the constructed project
    for owner, occupants, and OM

10
What Each Team Member Wants
  • ARCHITECTS
  • Design the next wonder of the world
  • Fewer change orders
  • Fewer RFIs
  • Contractor to build it like it is designed
  • No site visits
  • Do the engineers inspections
  • No attorneys involved

11
What Each Team Member Wants
  • ENGINEERS
  • Design that is not VEd to death
  • Fewer change orders
  • Fewer RFIs
  • Contractor to install it like it is designed
  • No inspections
  • Do their own CA
  • No legal hassle
  • Paid on time

12
What Each Team Member Wants
  • SUB-CONTRACTORS
  • Design he can change (for he believes his design
    is better)
  • A/E should stay off the job site
  • Work at his own pace
  • Get paid in a timely manner
  • Holds suppliers money since he has not been paid
    by the GC
  • Get off the job quickly
  • Hope he gets his retainage

13
What Each Team Member Wants
  • GC/CM
  • A design that works
  • To VE the daylights out of it
  • A/E should stay off the site
  • Do it his way
  • Paid 30 mobilization fee
  • Paid monthly on time
  • Hold subcontractors payment as long as he can
  • Get off the job and hope he gets his retainage

14
What Each Team Member Wants
  • OWNER
  • Project that is pretty, functions well and all
    systems work
  • Project is complete, on time and within budget
  • No change orders
  • No RFIs
  • Low interest construction loan
  • Makes excuses about paying designers and
    contractors on time
  • Hopes the building and systems work as
    anticipated.

15
What Each Team Member Wants
  • Manufacturers
  • Equipment and system approval
  • Ship equipment early
  • Warranty to start when equipment leaves factory
  • Why cant I submit on this project?
  • Take their time in completing project
  • Paid without penalty

16
The Three Systems of Buildings
STATIC SYSTEM (THE FRAME AND ENVELOPE)ENERGIZED
SYSTEM (THE BUILDING SERVICES)HUMAN SYSTEM
(THE TENANTS AND OCCUPANTS)
17
Building Relationships
18
Role of the Commissioning Authority
  • Determine what the owner really wants
  • Work with design team to implement a Basis of
    Design (BOD) document and Owners Project
    Requirements (OPR) document
  • Develop a plan to implement the BOD and OPR into
    the construction documents
  • Verify the right systems are being installed
  • Verify the operation of the systems
  • Document the entire project

19
Price vs. Cost
  • Price is something you pay one time
  • Cost is what it takes to operate

20
  • PRICE
  • QUALITY
  • SPEED
  • Pick any Two

21
Benefits and Cost Savings Potential vs. Cost to
Implement or Change
Cost to Change
Benefits and Cost Savings


Concept Design
Construction Acceptance
Occupancy

Phases
22
Commissioning Consultant
  • Definition of Consultant someone called in to
    share the blame.
  • The Blame GameDr. John Parker
  • Lawyer Have we left anything out?
  • Surgeon Have we left anything in?
  • Engineer Is there anything left?

23
What is Commissioning
  • Commissioning is a process to verify that the
    owner has received what they contracted for
    during the programming and design phases and
    during the construction phase. It also gives
    them a comfortable feeling of knowing someone is
    looking out for them throughout the project and
    the 1st year of occupancy
  • It also verifies that the architects and
    engineers have received the systems they designed
    and approved

24
The Principal Goal of Commissioning
  • The Principal Goal of the Commissioning Process
    is
  • The identification and correction of problems as
    early in the process as possible.

25
Top 10 Deficiencies Discovered by Commissioning
New Existing Buildings
  • Incorrect scheduling of HVAC and Lighting
    equipment
  • Incorrect heating and cooling Sequence of
    Operation
  • Incorrect Calibration of Sensors and
    Instrumentation
  • Lack of control strategies for optimum comfort
    and efficient operation
  • Malfunctioning air and water side economizers

26
Top 10 Deficiencies Discovered by Commissioning
New Existing Buildings (cont.)
  • Under-utilized computer-based control systems
  • Short cycling of HVAC equipment leading to
    premature failure
  • Lack of design intent and building documentation
  • Lack of training for building operators or
    service contractors on complex systems
  • Missing specified and pair-for equipment
    economizers

27
What Commissioning is NOT
  • Test and Balance
  • Start-up
  • Plan Review
  • Design
  • Contract Administration
  • Inspection

28
When Should Commissioning Begin??
  • Near the end of the Construction Phase?
  • When MEP systems installation begin?
  • When construction begins?
  • When design is complete?
  • When CDs are started?
  • When DDs are Started?
  • When SDs are started?
  • Prior to beginning design?

29
Commissioning Where it is going
  • It is mandatory to commission all LEED projects
    to a specified level
  • Some states have mandated that state owned or
    leased buildings be commissioned
  • US FEDERAL GSA has mandated that GSA buildings be
    commissioned
  • More and more hospitals are now requiring
    commissioning
  • Commissioning is a standard in Canada

30
Why Required?
  • Low quality construction- construction
    deficiencies
  • Complex systems difficult to test
  • Integrated systems do cause problems

31
ASHRAE Guideline 0-2006
  • Describes the commissioning process that will
    ensure HVAC systems perform in conformity with
    design intent and owners project requirements

32
Phases of Commissioning
  • Pre-Design
  • Design
  • Construction
  • Occupancy
  • Project Turnover
  • Warranty

33
How does the CxA meet his Responsibilities?
  • Conduct a OPR Charrette with the owner and design
    team.
  • Create and publish the OPR.
  • Review each step in the process to ensure
    compliance with the OPR.
  • Conduct regular meetings with the Cx Team to
    ensure communications are free flowing.
  • Document the entire process for the benefit of
    the owner and his staff.

34
Systems Commissioning
  • Verifies operation of components under various
    conditions
  • Verifies interaction between systems and
    subsystems
  • Documents performance of systems to design
    criteria
  • Instructs building personnel on proper operation
    of systems
  • Ongoing after building occupancy as requirements
    change

35
Cost Savings from Building Commissioning
  • Energy Savings of 20 to 50
  • Maintenance savings of 15 to 50
  • Reduction in claims from 2 to 20
  • Reduction of in-house overtime costs
  • Reduction of trouble-shooting costs

36
Who are the Players
  • Architect
  • Engineers
  • Owners Representative
  • Construction Manager
  • Mechanical Contractor
  • Electrical Contractor
  • Controls Sub-Contractor
  • Others as deemed necessary

37
Responsibilities
  • ARCHITECT/ENGINEER
  • Be a team player
  • Design the project with owners thoughts and
    requirements in mind
  • Be willing to make changes
  • Attend and participate in the commissioning
    meetings
  • Attend and participate in the owners project
    requirement meeting

38
Responsibilities (Cont.)
  • With the assistance of the CxA develop the basis
    of design document
  • Answer RFIs in a timely manner
  • Answer change orders in a timely manner
  • Attend and participate in the VE process

39
Responsibilities (Cont.)
  • OWNERS REPRESENTATIVE
  • Make decisions in a timely manner
  • Attend and participate in owners project
    requirement meeting
  • Attend and participate in commissioning meetings
  • Must own commissioning authoritys contract
  • Approve the owners project requirement document
  • Approve the commissioning plan

40
Responsibilities (Cont.)
  • CONSTRUCTION MANAGER
  • Manage the project
  • Coordinate sub-contractors work
  • Attend and participate in the commissioning
    meetings
  • Attend and participate in the owners project
    requirement meeting
  • Attend and participate in the VE process
  • Have coordination drawings developed

41
Responsibilities (Cont.)
  • MEP CONTRACTORS
  • Install their respective work
  • Complete the various checklist
  • Be part of the commissioning team
  • Attend and participate in the owners project
    requirement meeting
  • Attend and participate in the commissioning
    meetings
  • Attend and participate in the VE process
  • Be a team player

42
Responsibilities (Cont.)
  • COMMISSIONING AUTHORITY
  • Manage the commissioning process
  • Develop the commissioning plan
  • Develop the commissioning specifications
  • Work with all the other team members
  • Develop the owners project requirement document
  • With the assistance of the engineer develop the
    basis of design
  • Verify mold and mildew concerns

43
Responsibilities (Cont.)
  • COMMISSIONING AUTHORITY
  • Conduct the commissioning meetings
  • Review the project in a timely manner
  • Review the submittals for compliance
  • Review the warranties for the record
  • Review the checklist
  • Perform the FPT
  • Turn building over to the owner
  • Not responsible for the design

44
CxA Responsibities During Design
  • Review the SD documents and issue comments to the
    design team
  • Review the DD documents and issue comments to the
    design team
  • Review the CD documents and issue comments to the
    design team
  • Work with the VE process

45
To Correct Major Problems
  • The contract for the commissioning work should be
    awarded in the programming phase
  • The commissioning contract should be professional
    services directly contracted with the owner
  • Other contractual arrangements may and will lead
    to conflicts of interest

46
Common Technical Disagreements
  • Commissioning projects may experience
    difficulties if the design team does not take an
    active part in recommending an adequate solution
    to a found deficiency
  • It is not the responsibility of the CxA to
    dictate a design correction or change to solve a
    problem

47
Conflict Resolution
  • Responsibilities of the design team must be
    clearly defined by the commissioning plan
  • Design team required services and adequate fees
    also must be included in their contract
  • It is important that the commissioning authority
    and design team maintain a close relationship
    throughout the project

48
Common Technical Disagreements
  • Cx contract was not awarded until construction
    bids were received and awarded
  • The Cx contract is a subcontract under the
    mechanical contractor

49
O M Manuals
  • Should be received within 60 days after approved
    submittals have been returned
  • Review with owner and give comments back to
    contractor for compliance
  • Use this as your training Bible
  • Be careful what you get in the O M
  • You do not need installation material

50
Training
  • Factory witness testing on major pieces of
    equipment
  • Get factory training out of way up front
  • Training should be in a classroom setting and
    also at the respective piece of equipment
  • Use factory trainers not the local sales rep

51
Documentation Required
  • Owners Project Requirement Document
  • Commissioning Plan
  • Basis of Design
  • Contract Documents
  • TAB Report
  • Draft of the Final Commissioning Report
  • Warranties
  • O M Manuals

52
Documentation Required (Cont.)
  • Approved Change Orders
  • AS-Built Drawings
  • All testing data verification and documentation.
  • Sequence of Operation
  • Minutes of Meetings
  • Local jurisdictional inspection documentation and
    records

53
Benefits of the Commissioning Process
  • If the Commissioning Authority/Team for your
    project cannot clearly document that their fee
    has been recovered, you are not properly
    implementing the Commissioning Process

Project State Cost Project Cx Fee CxP Savings
Hospital IN 70 M Completed 744,000 340,000
Hospital Ohio 80 M Completed 856,000 375,000
PET Scan Facility NC 2.1 M Completed 25,000 40,000
ABMT NC 4.8 M Completed 36,500 100,000
Tissue Culture Lab NC 3.5 M Completed 35,000 75,000
Hospital NC 45 M Completed 325,000 900,000
Vivarium NC 28 M Completed 280,000 500,000
Prison TX 40 M Completed 225,000 400,000
CIEMAS NC 105 M Completed 1,200,000 3,000,000
Center for Human Genetics NC 42.5 M Completed 322,000 1,680,000
54
Example
  • Costs
  • 50M Laboratory Project
  • MEP Systems 27M
  • MEP Cx Costs 21/2 675K
  • Savings
  • CO reduction 1.5M
  • Construction Costs 2M
  • Energy Savings 750K
  • Legal Costs 500K
  • Early Occupancy 45 days _at_ 10K/day 450K
  • NET SAVINGS 5,200,000
  • ROI 1422.5

55
Benefits of Commissioning
  • Project on time
  • Establish maintain energy and maintenance
    budgets
  • Change orders are greatly reduced
  • Claims are greatly reduced
  • Punch list is non-existent
  • Operators have correct training
  • Enforce Start-Up Requirements
  • Reduce Post-Occupancy Corrective Work

56
Benefits of Commissioning (Cont.)
  • Absenteeism has diminished
  • Users have been able to take ownership
  • Lasting professional relationships have been
    developed
  • Buildings and systems are operating as owner
    predicted
  • Minimize Effects of Design Defects
  • Improve Indoor Environment and Employee
    Production
  • Reduce Energy and Operating Cost
  • Increase Value through Better Quality
    construction

57
Owners Comments
  • Kept politics out of project
  • Worth the money
  • Will definitely continue the process on other
    projects
  • Project was on time budget
  • Systems are working as requested
  • Occupancy is stable
  • Training was a major factor in the process
  • Maintenance is manageable and understands the
    systems

58
Coil Damaged Beyond Repair
59
Water Oil - OSHA Violation
60
Corrosion Inside Out
61
Inside ATS for 330kw Generator 1 Improper
installation requires hand operation.
62
Water Line Misplaced
63
Variable Frequency Drives installed w/o air space
64
  • Remember
  • Commissioning is
  • A
  • Quality Process

65
Questions
  • Thank You
  • Carl N. Lawson
  • Hanson Professional Services Inc.
  • West Palm Beach, FL
  • Phone 561-471-9370
  • Email clawson_at_hanson-inc.com

66