Title: CHAPTER SIX:
1CHAPTER SIX
- DESIGN OF CHANNELS AND IRRIGATION STRUCTURES
26.1 DESIGN OF CHANNELS FOR STEADY UNIFORM FLOW
- Channels are very important in Engineering
projects especially in Irrigation and, Drainage.
- Channels used for irrigation are normally called
canals - Channels used for drainage are normally called
drains.
36.1.1 ESTIMATION OF CANAL DESIGN FLOWS (Q)
- For Irrigation Canals, Design Flows are
estimated Using the Peak Gross Irrigation
Requirement - For Example, in a Location with the Peak Gross
Irrigation Requirement of 7.69 mm/day. -
- Peak flow (Q) 7.69/1000 m x 10000 x
1/3600 x 1/24 x 1000 - 0.89 L/s/ha
- For a canal serving an area of 1000 ha, canal
design flow is then 890 L/s or 0.89 m 3 /s. - Typically, for humid areas, magnitude of
discharges are in the range of 0.5 to 1.0
L/s/ha.
46.1.2 Dimensions of Channels and
Definitions
5Definitions
- a) Freeboard Vertical distance between the
highest water level anticipated in the design and
the top of the retaining banks. It is a safety
factor to prevent the overtopping of structures. -
- b) Side Slope (Z) The ratio of the
horizontal to vertical distance of the sides of
the channel. Z e/d e/D
6Table 6.1 Maximum Canal Side Slopes (Z)
Sand, Soft Clay 3 1 (Horizontal Vertical)
Sandy Clay, Silt Loam, Sandy Loam 21
Fine Clay, Clay Loam 1.51
Heavy Clay 11
Stiff Clay with Concrete Lining 0.5 to 11
Lined Canals 1.51
7- 6.1.3 Estimation of Velocity in Channels
- The most prominent Equation used in the design is
the Manning formula described in 6.1.3. Values
of Manning's n can be found in standard texts
(See Hudson's Field Engineering). - 6.1.4 Design of Channels
- Design of open channels can be sub-divided into
2 - a) For Non-Erodible Channels (lined)
- b) Erodible Channels carrying clean water
8(No Transcript)
9Design of Non-Erodible Channels
When a channel conveying clear water is to be
lined, or the earth used for its construction is
non-erodible in the normal range of canal
velocities, Manning's equation is used. We are
not interested about maximum velocity in design.
Manning's equation is
Q and S are basic requirements of canal
determined from crop water needs. The slope of
the channels follows the natural channel.
Manning's n can also be got from Tables or
estimated using the Strickler equation n
0.038 d1/6 , d is the particle size
diameter (m)
10Design of Non-Erodible Channels Contd.
- LHS of equation (1) can be calculated in terms of
A R2/3 termed section factor. For a
trapezoidal section - A b d Z d2 P b 2 d (1
Z)1/2 - The value of Z is decided (see Table 6.1) and the
value of b is chosen based on the material for
the construction of the channel. - The only unknown d is obtained by trial and
error to contain the design flow. Check flow
velocity and add freeboard. -
11Example 6.1
- Design a Non-Erodible Channel to convey 10
m3/s flow, the slope is 0.00015 and the mean
particle diameter of the soil is 5 mm. The side
slope is 2 1. - Solution Q 1/n AR 2/3 S 1/2 .. (1)
- With particle diameter, d being 5 mm, Using
Strickler Equation, n 0.038 d 1/6 - 0.038 x 0.005 1/6
0.016
12Solution of Example Contd.
Z 2. Choose a value of 1.5 m for 'b For
a trapezoidal channel, A b d Z d2
1.5 d 2 d2 P b 2 d (Z2 1)1/2
1.5 2 d 51/2 1.5 4.5 d Try
different values of d to contain the design flow
of 10 m3/s
13Soln of Example 6.1 Contd.
d(m) A(m2 ) P(m) R(m) R2/3
Q(m3/s) Comment 2.0 11.0
10.5 1.05 1.03 8.74 Small
flow 2.5 16.25 12.75 1.27 1.18
14.71 Too big 2.2 12.98
11.40 1.14 1.09 10.90 slightly
big 2.1 11.97 10.95 1.09 1.06 9.78
slightly small 2.13 12.27 11.09 1.11 1.07
10.11 O.K. The design parameters
are then d 2.13 m and b 1.5 m
Check Velocity Velocity Q/A 10/12.27
0.81 m/s Note For earth channels, it is
advisable that Velocity should be above 0.8 m/s
to inhibit weed growth but this may be
impracticable for small channels. Assuming
freeboard of 0.2 d ie. 0.43 m, Final design
parameters are D 2.5 m
and b 1.51 m
14Final Design Diagram
T 11.5 m
D 2.5 m
Z 21
d 2.13 m
b 1.5 m
T b 2 Z d 1.5 2 x2 x 2.5 11.5 m
15Design of Erodible Channels Carrying Clean Water
- The problem here is to find the velocity at which
scour is initiated and to keep safely below it.
Different procedures and thresholds are involved
including maximum permissible velocity and
tractive force criteria. - Maximum Permissible Velocities The maximum
permissible velocities for different earth
materials can be found in text books e.g.
Hudson's Field Engineering, Table 8.2.
16Procedure For Design
- i) Determine the maximum permissible velocity
from tables. - ii) With the permissible velocity equal to
Q/A, determine A. - iii) With permissible velocity 1/n S1/2 R2/3
- Slope, s and n are normally given.
- iv) R A/P , so determine P as A/R
- v) Then A b d Z d and
- P b 2 d (Z2 1)1/2 ,
- Solve and obtain values of b and d
17Example 6.2
- From previous example, design the channel using
the maximum permissible velocity method. - Solution Given Q 10 m3 /s , Slope
0.00015 , n 0.016 - , Z 2 1
- i) From permissible velocity table, velocity
0.75 m/s - A Q/V 10/0.75 13.33 m
-
- iv) P A/R 13.33/0.97 13.74 m
- v) A b d Z d2 b d 2 d2
- P b 2 d (Z2 1)1/2 b
2 d 51/2 b 4.5 d - ie. b d 2 d2 13.33 m 2
........(1) - b 4.5 d 13.74 m
........ (2)
From previo
18Solution of Equation 6.2 Contd.
From (2), b 13.74 - 4.5 d
.......(3) Substitute (3) into (1), (13.74 -
4.5 d)d 2 d2 13.33
13.74 d - 4.5 d2 2 d
13.33
13.74 d - 2.5 d2 13.33 ie. 2.5 d2 -
13.74 d 13.33 0 Recall the quadratic
equation formula
d 1.26 m is more
practicable From (3), b 13.74 - (4.5 x
1.26) 8.07 m Adding 20 freeboard, Final
Dimensions are depth 1.5 m and width 8.07
m
196.1.5 Classification of Canals Based on Capacity
- Canals can be classified as
- (a) Main Canal It is the principal channel of
a canal system taking off from the headworks or a
reservoir or tail of a feeder. - It is a large capacity channel and usually there
is no direct irrigation from it. - Small capacity ditch distributaries running
parallel to the canal are taken off from the main
canal to irrigate adjoining areas. - Main canals deliver supply to branch canal and
main distributaries.
20Canals Contd.
- (b) Branch or Secondary Canal
- Branch canals take their supply from the main
canal and convey to the distributaries. - Very little direct irrigation is done from the
branch canals. - Sub-branch is a canal, which takes off from the
branch canal but has capacity higher than a
distributary.
21Canals Contd.
- (c) Major Distributary
- It is a distributing channel, which may take off
from a main canal, branch canal or sub-branch and
has discharge capacity less than that of a branch
canal. - It supplies water to another distributary.
- Distributaries and minors take off from it.
- Irrigation is done through outlets fixed
along it.
22Canals Contd.
- (d) Distributary
- It is a channel receiving supply from branch
canal or major distributary and has discharge
less than that of major distributary. - Minors take off from it, besides irrigation is
done from it through outlets.
23IRRIGATION STRUCTURES
- Structures are widely used in Irrigation, water
conservation, flood alleviation, river works
where water level and discharge regulation are
required. - These are hydraulic structures that are used to
regulate, measure, and/or transport water in open
channels. - These structures are called control structures
when there is a fixed relationship between the
water surface elevation upstream or downstream of
the structure and the flow rate through the
structure. - Hydraulic structures can be grouped into three
categories
24IRRIGATION STRUCTURES
25Hydraulic Structures Contd.
- (i) Flow measuring structures, such as weirs
- (ii) Regulation structures such as gates and
- (iii) Discharge structures such as culverts.
26Weirs
- Weirs Weirs are elevated structures in open
channels that are used to measure flow and/or
control outflow elevations from basins and
channels. - There are two types of weirs in common use
- Sharp-crested weirs and the broad-crested weirs.
- The sharp-crested weirs are commonly used in
irrigation practice
27 Sharp-Crested Weirs
- Sharp-crested or thin plate, weirs consist of a
plastic or metal plate that is set vertically
across the width of the channel. - The main types of sharp-crested weirs are
rectangular, V-notches and the Cipolletti or the
Trapezoidal weirs. - The amount of discharge flowing through the
opening is non-linearly related to the width of
the opening and the depth of the water level in
the approach section above the height of the weir
crest. -
28Sharp Crested Weirs Contd.
- Weirs can be classified as being contracted or
suppressed depending on whether or not the nappe
is constrained by the edges of the channel. - If the nappe is open to the atmosphere at the
edges, it is said to be contracted because the
flow contracts as it passes through the flow
section and the width of the nappe is slightly
less than the width of the weir crest (see
figure). - If the sides of the channel are also the sides of
the weir opening, the streamlines of flow are
parallel to the walls of the channel and there is
no contraction of flow.
29Figure 6.2 Rectangular Weirs
(b) Unsuppressed Weir (Contracted)
(a) Suppressed Weir
30(No Transcript)
31Sharp Crested Weirs Contd.
- In this case, the weir is said to be suppressed.
Some type of air vent must be installed in a
suppressed weir so air at atmospheric pressure is
free to circulate beneath the nappe. (See Figure
6.2 for suppressed and unsuppressed weirs).
32Sharp Crested Weirs Contd.
The discharge, Q (m3/s) over a rectangular
suppressed weir can be derived as
Where Cd is the discharge coefficient, b is the
width of the weir crest, m (see Figure 6.2 above)
and H is the head of water (m) above weir crest.
According to Rouse (1946) and Blevins( 1984),
..(2) Where Hw is the height of the
crest of the weir above the bottom of the
channel.
33Weirs Contd
This equation is valid when H/Hw lt5, and is
approximated up to H/Hw 10. If H/Hw lt 0.4,
Cd can be approximated as 0. 62 and equation (1)
reduces to Q 1.83 b H1.5
. (3)
This equation is normally used to compute flow
over a rectangular suppressed weir over the usual
operating range. It is recommended that the
upstream head, H be measured between 4H and 5H
upstream of the weir. For the unsuppressed
(contracted) weir, the air beneath the nappe is
in contact with the atmosphere and venting is not
necessary. The effect of side contractions is to
reduce the effective width of the nappe by 0.1 H
and that flow rate over the weir, Q is estimated
as Q 1.83 (b 0.2 H) H1.5
(4) This equation is acceptable as long as b is
longer than 3 H
34Cipoletti Weir
- A type of contracted weir which is related to the
rectangular sharp-crested weir is the Cipoletti
weir (see Figure 6.3 below) which has a
trapezoidal cross-section with side slopes 14
(HV). The advantage of a Cipolletti weir is
that corrections for end contractions are not
necessary.
35Cipolletti Weir Contd.
The discharge formula can be written as Q
1.859 b H1.5 .. (5) Where b is the
bottom width of the Cipolletti weir. The minimum
head on standard rectangular and Cipolletti weirs
is 6 mm and at heads less than 6 mm, the nappe
does not spring free of the crest.
Figure 6.3 A Trapezoidal of Cipolletti Weir
36Example 6.3
- A weir is be installed to measure flows in the
range of 0.5 to 1.0 m3/s. If the maximum depth
of water that can be accommodated at the weir is
1 m and the width of the channel is 4 m,
determine the height of a suppressed weir that
should be used to measure the flow rate.
37Solution to Example 6.3
The flow over the weir is shown in the Figure 6.4
below. The height of water is Hw and the flow
rate is Q. The height of water over the crest of
the weir, H is given by H 1
Hw Assuming that H/Hw , 0.4, then Q is related
to H by equation (3), where Q 1.83 b H 1.5
Figure 6.4 Weir Flow
38Solution to Example 6.3Concluded
Taking b 0.4 m, Q 1m3/s (the maximum flow
rate will give the maximum head, H), then
The height of the weir, Hw
is therefore given by Hw 1 0.265 0.735
m And H/Hw
0.265/0.735 0.36 The initial assumption
that H/Hw lt 0.4 is therefore validated, and the
height of the weir should be 0.735 m.
39V-Notch Weir
A V-notch weir is a sharp-crested weir that has a
V-shaped opening instead of a rectangular-shaped
opening. These weirs, also called triangular
weirs, are typically used instead of rectangular
weirs under low-flow conditions ( mainly lt 0.28
m3/s), where rectangular weirs tend to be less
accurate. It can be derived that the flow rate,
Q over the weir is given by
40V-Notch Weirs Contd.
41Parshall Flume
- Although weirs are the simplest structures for
measuring the discharge in open channels, the
high head losses caused by weirs and the tendency
for suspended particles to accumulate behind
weirs may be important limitations. - The Parshall flume provides an alternative to the
weir for measuring flow rates in open channels
where high head losses and sediment accumulation
are of concern. - Such cases include flow measurement in irrigation
channels. - The Parshall flume (see Figures 6.7 and 6.8
below) consists of a converging section that
causes critical flow conditions, followed by a
steep throat section that provides for a
transition to supercritical flow.
42Parshall Flume
43Parshall Flumes
44Parshall Flume Contd.
- The unique relationship between the depth of flow
and the flow rate under critical flow conditions
is the basic principle on which the Parshall
flume operates. - The transition from supercritical flow to
subcritical flow at the exit of the flume usually
occurs via a hydraulic jump, but under high tail
water conditions the jump is sometimes submerged.
45Parshall Flume Contd
- Within the flume structure, water depths are
measured at two locations, one in the converging
section, Ha and the other at the throat section,
Hb. The flow depth in the throat section is
measured relative to the bottom of the converging
section as illustrated in the figure below. - If the hydraulic jump at the exit of the Parshall
flume is not submerged, then the discharge
through the flume is related to the measured flow
depth in the converging section, Ha by the
empirical discharge relations given in Table 6.2,
where Q is the discharge in ft3/s, W is the width
of the throat in ft, and Ha is measured in ft.
46Parshall Flume Contd
- Submergence of the hydraulic jump is determined
by the ratio of the flow depth in the throat, Hb,
to the flow depth in the converging section, Ha,
and critical values for the Hb/Ha are given in
Table 6.3. - Whenever, the ratio exceeds the critical values
in the table, the hydraulic jump is submerged and
the discharge is reduced from the values given by
the equations in Table 6.2. - Corrections to the theoretical flow rates as a
function of Ha and the percentage of submergence,
Hb/Ha are given in the Figures 6.8 and 6.9 below
for throat widths of 1 ft and 10 ft.
47Parshall Flumes Contd.
48Parshall Flumes Contd.
- Flow corrections for the 1 ft flume are applied
to larger flumes by multiplying the correction
for the 1 ft flume by a factor corresponding to
the flume size given in Table 6.4. - Similarly, flow corrections for flume sizes
greater than 10 ft. are applied to larger flumes
by multiplying the correction for the 10 ft flume
by a factor corresponding to the flume size
given in Table 6.5. - Parshall flumes do not reliably measure flow
rates when the submergence ratio, Hb/Ha exceeds
0.95.
49Parshall Flume Correction
50Tables For Parshall Flume Correction
51Example 6.4
- Example 6.4 Flow is being measured by a
Parshall flume that has a throat width of 2 ft.
Determine the flow rate through the flume when
the water depth in the converging section is 2.00
ft and the depth in the throat section is 1.70ft.
52Solution to Example 6.4
From the given data W 2 ft, Ha 2 ft,
and Hb 1.7 ft. According to Table 6.2, Q
is given by In this
case Hb/Ha 1.7/2 0.85 Therefore,
according to Table 6.3, the flow is submerged.
Figure 6.8 gives the flow rate correction for a
1 ft flume as 2ft3/s, and Table 6.4 gives the
correction factor for a 2 ft flume as 1.8. The
flow rate correction, dQ for a 2 ft flume is
therefore given by DQ 2 x 1.8
3.6 ft3/s And the flow rate through the
Parshall flume is Q dQ, where Q dQ 23.4
3.6 29.8 ft3/s
53Gates
- Gates are used to regulate the flow in open
channels. - They are designed for either over-flow or
underflow operation, with overflow operation
appropriate for channels in which there is a
significant amount of floating debris. - The common types of gates are vertical and radial
(Tainter) gates, which are illustrated below. - Vertical gates are supported by vertical guides
with roller wheels, and large hydrostatic forces
usually induce significant frictional resistance
to raise and lower the gate
54Diagrams of Gates
55(No Transcript)
56Gates Contd.
Flow, Q through a gate could be
established to be Cc
Cc coefficient of contraction, y2/yg
0.61 for most vertical gates. For For Tainter
gates, Cc is generally greater than 0.61 and is
commonly expressed as a function of the angle
(degrees) shown in the diagram above.
57(No Transcript)
58Gates Concluded
It can be expressed as This equation
applies as long as the angle is least than 900.
All the equations apply where there is free flow
through the gates. See texts for situations
where the flows through the gates are submerged.
59Drop Structures
- Drop structures, typically constructed out of
concrete, can accommodate a sudden change in
elevation of the channel bottom while maintaining
control of the flow. - Drop structures are used in channels, which must
be laid along relatively steep gradients to allow
for dissipation of energy without causing scour
in the channel itself. - In such applications, the drop structure allows
the main channel to be laid on subcritical slope
while the excess potential energy of the flow due
to the steep topography is absorbed in the drop
structure. See Figure 6.12 of a drop structure
below
60Diagram of Drop Structure
61Example 6.5
- An irrigation channel with a design discharge of
2.265 m3/s is to be laid along a terrain having
an average slope of 0.005 m/m. To maintain
subcritical flow in the channel section, the
bottom of the channel must be limited to 0.001
m/m. The extra fall is to be absorbed by drop
structures such as the one shown above in the
diagram having a width of 3.048 m. Compute the
number of structures required in a 16.09 km
length of line if the drop height (dZ) is equal
to 1.829 m.
62Solution of Example 6.5
- Solution The total drop to be absorbed by
structures, ZT (St - So) L - Where St is the terrain slope, L is total
distance, and So is the slope of the channel. - ZT ( 0.005 m/m - 0.001 m/m ) 16.09 km
64.36 - The number of drop structures required,
- N ZT/dZ 64.36/1.829 36 Structures.