Title: Status of the TRASCO Project
1Status of the TRASCO Project
Oak Ridge National Lab June 25-26, 2001
SNS-Miniworkshop
Carlo Pagani INFN Milano-LASA University of
Milano
2The TRASCO linac INFN-TC-00-23
3TRASCO_AC Activities and Partners
- Source
- LNS
- Hitec
- Sistec
- Low and Intermediate Energy Section
- LNL
- Cinel
- Uni/INFN Bo
- INFN Ba
- High Energy Section
- INFN Mi
- INFN Ge
- CESI
- Saes Getters
- Zanon
4TRasco Intense Proton Source (LNSHITECSISTEC)
- High intensity (several 10s mA) proton sources
exist - Chalk River
- Los Alamos
- CEA-Saclay (Strong collaboration LNS/CEA)
- Critical problem for ADS is the source
reliability and availability - Additional efforts with respect to state of the
art are required for - Voltage and current stability
- Control of the low beam emittance
- Subprogram is aimed at the construction and
operation of the source
5TRIPS
- Design completed in 1999
- Source assembled in LNS in May 2000
- First beam of 20 mA _at_ 60 kV in Jan 2001
- Off-resonance microwave discharge source (2.45
GHz) - Based on SILHI (CEA/Saclay)
- Modifications focussed on increase of reliability
and availability - TRASCO II Optimized source with PM
6Low Energy Linac (LNLCINELBaBoNa)
- The low energy linac is split in two components
- A normal conducting CW Radio Frequency Quadrupole
(RFQ) from 80 keV to 5 MeV - A Superconducting linac (ISCL) from 5 MeV to 100
MeV - l/4, l/2 cavities at 176 MHz or 352.2 MHz
- Reentrant cavities at 352.2 MHz
TRASCO I Prototype of 1/3 of the full RFQ and
one of the SC cavities TRASCO II full RFQ
structure manifacturing
7The CW RFQ
- LANL LEDA 6.7 MeV RFQ achieved 100 mA CW (point
of comparison) - Huge engineering effort, complex design for very
high current, 3 klystrons - Different optimization procedure for TRASCO RFQ
- Limit to 1 RF source (1.3 MW CERN-LEP klystron)
- Lower design current of 30 mA (transmission of
96) - Peak surface electric field is 33 MV/m, 1.8
Kilpatrick limit - Simplified engineering/manufacturing choices
- Heat dissipation in the structure 600 kW total
8ISCL Linac
- The 5-100 MeV linac is made of independently
phased cavities - Re-entrant cavity geometry (single cell)
- Each SC cavity is fed by a small 15 kW solid
state amplifier (Activity in LNL) - Linac is very tolerant in terms of cavity
failures (0.5 MeV max cav gain) - Cavities can be designed multipactor-free
- The He vessel is integrated in the resonator in
order to provide mechanical stability
Mechanical analysis under 1 bar He bath pressure
Focussing Quadrupoles
9Other resonator types for low energy
- A more cost effective linac can be designed with
2 gap resonators - 1-1.5 MeV of energy gain per cavity
- In this case the linac is less tolerant to cavity
failures - Half Wave Resonators (dipole-free) and Quarter
Wave Resonators (like ALPI cavities) are under
analysis
beam
10The High Energy SC Linac (MIGEZanonSaesCESI)
- Linac Conceptual Design Beam Dynamics (INFN)
- RF Cavity design ? Done
- All e.m., mechanical technological fabrication
aspects - Linac design and non-linear beam dynamics ? Done
- Two frequency options analyzed
- 352.2 MHz (CERN LEP)
- Attractive if machine is built NOW, with help of
CERN infrastructures - Limited gradients, 4.2 K operation
- Components are ready (RF, ancillaries, ...)
- Long machine and huge infrastructures
- Cheap technology (sputtering)
- 704.4 MHz (CERN2)
- More components engineering but, after TESLA
achievements, more promising - Higher gradients, 2 K operation
- Components need to be developed (RF, ...) but can
be designed after TESLA/SNS - Shorter machine and small infrastructures
- Bulk niobium cavities
- Prototypes and engineering (with partners)
- High beta single and multi cell cavity at 352.2
MHz with CERN ? Done
11Extension to the TRASCO program
- TRASCO II extends the program to the end of 2001
- Main goals of TRASCO II
- Source
- TRIPS-PM (permanent magnet version for further
reliability) - Beam line to the RFQ (matching section)
- Low Energy
- Manufacturing of the Full RFQ structure
- Engineering of the re-entrant cavity components
tuners, couplers, etc. - High Energy
- Multicell cavity at 704.4 MHz (2) Collaboration
with CEA/IN2P3 - Engineering design of the cryomodule
- Treatment and test infrastructure in LASA
- Class 100 Clean Room
- High Pressure Rinsing station
- RF measurement infrastructure
- BCP is being set up in an external company
premises
12General Linac Design
From INFN/CEA/IN2P3 Meeting LASA, Feb 23-24,
1999
- Choices of cavity parameters
- RF Frequency
- b values
- Determined mainly by the machine energy range and
number of sections - Number of cells
- Determined by efficient use
- How many cavities per cryomodule?
- Many good use of space (beware of too much
acceleration in one lattice cell!) - Few waste of space
- Cavity design provides constraints
- Max B surface field (and Bpeak/Eacc)
- Max E surface field (and Epeak/Eacc)
- Longitudinal beam dynamics constraints
- Longitudinal phase advances
- Longitudinal focussing (synch. phase)
- Beamline space inventory
13The Scaling with Frequency
From INFN/CEA/IN2P3 Meeting LASA, Feb 23-24,
1999
- From the envelope equations, simple scaling laws
with the design frequency can be derived,
allowing to reproduce the same dynamics (scaling
properly emittances, currents, and beamline
parameters) - higher frequency means physically smaller
accelerator components - ? divide lengths by a factor 2 (700/350)
- ? use a beam physically smaller by a factor 2
- keep the same phase advances per period (the
basic linac design depends on the choice of the
phase advance) - ? the phase advance per meter doubles (the cell
size halves!) - ? the quadrupole gradients double, the length and
bore are halved - ? the cavity gradients double
- To have the same dynamics we need to divide the
emittances by a factor 2 - If we also keep the same ratio of the emittance
term to the space charge term, - ? use the same peak beam current (twice the
charge in the bunch) - In this way the envelope equation is formally the
same! Of course, the boundary condition at low
energy is different for the two frequencies - We did not consider the matching to the focusing
channel of the previous linac section, which will
be obviously different in the two cases due to
the frequency transition
14Linac Beam Dynamics (1 GeV TRASCO linac)
From EPAC 2000, Vienna, June 2000
- The beam dynamics of TRASCO has been analyzed in
detail - A multiparticle beam dynamics code with a 3D
space charge solver has been written - Time evolution (for space charge consistency)
- Beam propagation in a z-dependent sinusoidal
cavity field - 3D Poisson solver based on a Multigrid method
- Presented at the ICAP98
- Compares OK with 2D/3D Parmila versions (N.
Pichoff/CEA) - No substantial emittance growth/halo formation
can be seen from simulations (up to 100.000
particles)
Beam Emittances
Control of the particle distribution
15Preliminary XADS Beamline
- In response to INFN/ENEA/Ansaldo meetings on the
ADS interface, we studied the beamline for the
XADS case - 600 MeV proton energy
- 6 mA beam current
Study for the windowless solution Full width beam
spot size on target 40 x 80 mm Small beam size is
kept inside the last 90 bending Changes
suggested with respect to base line XADS
16Cavity Design
- Careful analysis of the low beta cavity
properties - Short cavity geometry leads to peculiar
problems, the cavity geometry needs to be
carefully optimized - Electromagnetic
- Smaller volumes implies higher surface fields
than electron cavities - High surface E field emission! ? Nb quality and
chemical/surface treatmens - High surface B thermal quenches ? Nb quality
- Multipacting may be worse than electron cavities
(no clear indication yet) - Mechanical
- Different aspect ratio of the cells (long/transv)
- Mechanical stability under vacuum can be critical
at low beta - Need for stiffening in case of pulsed operation
or microphonics - Criteria/codes developed for cavity optimization
have been used for - TRASCO/352 and TRASCO/704
- Collaboration INFN/CEA/IN2P3 _at_ 704 (MOU)
- SNS (MOU INFN/TJNAF for SNS being signed)
- RIA (MOU INFN/MSU under definition)
17Tools for the cavity parametrization
From SNS CCS Workshop TJNAF April 12-13, 2000
- We built a parametric tool for the analysis of
the cavity shape on the electromagnetic (and
mechanical)parameters - All RF computations are handled by SUPERFISH (no
need for another code) - Inner cell tuning is performed through the cell
diameter, all the characteristic cell parameters
stay constant R, r, ?, d, L, Riris - End cell tuning is performed through the wall
angle inclination, ?, or distance, d. - R, L and Riris are set independently
- End groups for a 4 die cavity can be tuned using
the end cell diameter (and a,d,R,L, Riris are set
independently)
- All e.m. cavity results are stored in a database
for futher parametric investigations. - A proper file to transfer the cavity geometry to
ANSYS is then generated
18Final Cavity Output
19Mechanical analysis of
From SNS CCS Workshop TJNAF April 12-13, 2000
Danilo.Barni_at_mi.infn.it
Half cell
- A postprocessor reads the SFO output and builds a
FEM model - Radiation pressure calculation (Lorentz forces)
- Evaluation of the Slater coefficients
- An automated ANSYS procedure performs all the
following calculations for 3 boundary conditions
- Lorentz forces effects as a function of the
stiffening ring radial positions - 2 bar vacuum load on the cavity
- Tuning sensitivity (N/Hz, N/mm, Hz/mm)
Full cavity
- Computation of the vibration eigenmodes of the
completely free cavity - Computation of their dependence from suitable
external knobs - Helium vessel fixtures for the transverse modes
- Stiffening ring radius for longitudinal modes
- What is the connection Lorentz force excitation ?
vibrations? - Contribution of the modes to the Lorentz forces Dn
20TRASCO Cavity Prototyping
- 350 MHz cavities with CERN
- Single cell sputtered b 0.86
- 5 cell sputtered b 0.86
- Cavity integration in a LEP type cryostat Under
way at CERN - 700 MHz Cavities with ZANON ( Saclay JLab) b
0.5 - One single cell - Built (Zanon) and Tested
(Saclay) RRRgt30 - Three single cells under construction (RRRgt30
RRRgt250) - One 2-3 cell under design for fabrication
optimization and stiffening prototyping - One or two 5-cell cavities
- Arranging for chemical treatments with a local
company (Delmet) possible? - Cryogenic RF Test Bench under Commissioning at
LASA
21350 MHz Cavities
- MOU with CERN for the fabrication and test of
- Single cell at high beta ? Done!
- 5 cell cavity at high beta ? Done!
- Extension of the contract for the insertion of
the 5 cell cavity in a LEP cryostat on the way
22The b0.85 Cavity Produced with CERN
- Left, the cavity before the insertion of the Nb
cathode in the clean room before sputtering - Below, the cavity after chemical etching
23Five Cell Cavity Results (Q vs. Eacc)
b0.85
Results of the measurements on the TRASCO 5 cell
module _at_ 4.5 K
- The results obtained reached the original TRASCO
goal! - The limitation on the operating point of the
cavity was due to the increase of the RF losses
with the increasing field due to the growth of
electron loading - This limitation is exactly the same limitation
experienced in the LEP cavities, indeed the
cavity performed as the best LEP cavities
24Measurements Results and Future Work
- The next step of the joint INFN-CERN development
will be the test of the 5 cell cavity fully
equipped with tuners and couplers in an
accelerator-ready cryostat (a modified LEP spare
cryostat) - Here the cavity is shown in its He tank, complete
with the tuner bars, before insertion in the
cryomodule
- This activity was delayed till November 2000 due
to the LEP-Higgs Blues - cryomodule availability
- Current planning
- Module completed by the end of March 2001
- Module tests (due Cryogenic Facility backlog)
May-June 2001
25700 MHz Cavities
- The 700 MHz activities are carried out in
parallel with CEA/Saclay and IN2P3/Orsay, to
optimise development efforts - Milano works on prototypes of the lowest beta
(0.5) - Saclay/Orsay works on prototypes of the
intermediate beta (0.65) - The design work is common between the labs
- So far
- 4 b0.5 single cell cavity have been built and 2
tested - 3 b0.65 single cell cavity have been built and
tested
26Summary of Main Cavity Parameters
27The b0.5 single cell cavity (Z101)
- Used low RRR Nb sheets RRRgt 30
- Built by Zanon (Partner)
- Treated at Saclay
- Standard BCP 1.1.2 (HF HNO3 H3PO4) 100 mm
removal on surface - HPWR with ultrapure water (18 MW) _at_ 100 bar
- Class 100 Clean Room Assembling
- Tested at CEA-Saclay gave very good results
(given the bad Nb used!) - The vertical insert was not arrived in Milano
- The cavity will be re-tested in Milano soon
- One other single cell with low RRR and two single
cells with the good high RRR Nb are being built
by Zanon
28Life cycle of the Z101 treated at Saclay
BCP
Assembling in the insert
HPWR
29TRASCO 700 MHz b0.5 Z101 Prototype
- Fabricated with Reactor Grade (RRRgt30) Niobium
at ZANON - Chemical Treatment and HPR at Saclay (no heat
treatment) - Tested at Saclay at 1.5 K
30SC RF Cavity Test Facility at INFN-LASA
Class 100 Clean Room
A Class 100 Clean Room has been commissioned A 18
MW clean water plant for high pressure rinsing
has been installed High pressure rinsing (HPR)
system is being installed
The RF bunker
Clean Water Plant
RF Measurement Bunker
The new insert with a 5 cell cavity
The old ARES (500 MHZ) Cryostat from LNF has been
adapted with a new insert (ZANON) to minimize He
consumption and allow fast cooldown times
Assembling of the clean room