Title: National Railway System Project Status 08/07/08
1National Railway System Project Status 08/07/08
- Prepared by Raisa Spector
- Presented by TBD
- Project team 3
- Roberto Masciovecchio
- Raisa Spector
- Suzanne Smith
- Omar Mahmoud
- Mark Sanbower
- David Saavedra
-
2National Railway System Project Status
- Accomplishment
- Revisited Scope Statement and Work Breakdown
Sturcture - Finished WBS Dictionary
- Planned Activities
- Risk Register
- Prioritized list of quantified risks
- Activity List and Cost Estimate Cost
- Budgeting
3National Railway System Project Status
Issues
No Descriptions Due Date Assigned
1 Team members are not familiar with the railroad bed (embracement) construction engineering, specification, and terminology needed for creating WBS, WBS dictionary. 08/07/2008 Roberto as having access to Venezuela site. Suzanne as a Technical Writer
2 Same difficulties with reaching Venezuela contracting company telephone and Internet connections in Venezuela do not provide desirable 24 hours service. During whole project Roberto
4National Railway System Project Status
No Description Due Date. Assigned
1 Difficulties with gathering information may complicate project development. Team
No Description Due Date Assigned
1 2 3 Team members are available only part time everyone has full time job. Project has to be completed and posted on the Web Site by 8/29/08 Not every member of the team has MS Project and MS PowerPoint. Work should be distributed in a logical way to those who have the software and those who don't. This will enable everyone to contribute in an equal and meaningful way Team Team Raisa Spector (PM)