Beam Line BPM Upgrade - PowerPoint PPT Presentation

1 / 27
About This Presentation
Title:

Beam Line BPM Upgrade

Description:

Duane Voy, Charlie Briegel, Bob West, Brian Hendricks, Lin Winterowd. Review process ... Nathan Eddy, Bob Webber, Peter Prieto, Amber Larson, Elvin Harms. BPM ... – PowerPoint PPT presentation

Number of Views:40
Avg rating:3.0/5.0
Slides: 28
Provided by: loca260
Category:
Tags: bpm | beam | duane | eddy | line | upgrade

less

Transcript and Presenter's Notes

Title: Beam Line BPM Upgrade


1
Beam Line BPM Upgrade
  • Nathan Eddy Elvin Harms
  • 21 April 2005

2
Beam Line BPM Upgrade
  • Introduction/Motivation
  • History
  • Technical Overview
  • Status
  • Software
  • Implementation Steps
  • Acknowledgements
  • Summary

3
Beam Line BPM Upgrade - Introduction
  • Part of the Rapid Transfers Run II Upgrade
    Project
  • Beam Line Regulation
  • Software
  • Oscillation Feedback Control
  • Diagnostics
  • Commissioning
  • Ultimate goal
  • Accumulator to Recycler transfers every 30
    minutes and completed in 1 or 2 minutes

4
Beam Line BPM Upgrade - Motivation
  • 1.3.6.5.1 Beam line BPM upgrade
  • BPM current use
  • Reverse protons
  • Minimum 30 uniform 53 MHz bunches
  • A few E11 intensity
  • Beam conditions purposely varied during shot set
    up to minimize necessary intensity
  • currently no pbar beam line BPM data
  • Reverse proton data sufficient for good pbar
    transmission
  • Electronics limitations
  • Low intensity
  • bunch structure
  • Outdated DAQ
  • Difficult to integrate with existing software
  • Rapid Transfers - no routine reverse proton
    tuneup for rapid transfers
  • Use pbars to monitor beam line performance
  • Use data to feedback to beam lines tune

5
Beam Line BPM Upgrade - Motivation
  • Scope of work
  • P1, P2, AP1, AP3, A1
  • Use existing BPM pickups (53 MHz)
  • Upgrade electronics to support all expected beam
    modes
  • Modernize DAQ
  • Develop applications software to meet beam
    monitoring and tuning needs

6
Beam Line BPM Upgrade - History
  • Identified as part of Run II Upgrades/Rapid
    Transfers
  • Preliminary meeting, Requirements 8/11/03
  • No resources allocated/available
  • Inventory of existing systems March 2004
  • Manpower identified May 2004
  • Requirements document v 1.0 released May 2004
  • Requirements Review June 2004
  • Re-reviewed/notice to proceed with design - July
    2004
  • Rack at F23 September 2004
  • Installation Schedule developed October 2004
  • Project review October 2004
  • Crate running at F23 February 2005
  • First Pbar beam signals March 2005
  • Expected close out summer 2005

7
Beam Line BPM Upgrade Requirements
P1 line
Beams Document 1279-v3.3
8
Beam Line BPM Upgrade Requirements
P2 line
Beams Document 1279-v3.3
9
Beam Line BPM Upgrade Requirements
AP1 line
Beams Document 1279-v3.3
10
Beam Line BPM Upgrade Requirements
AP3 line
Beams Document 1279-v3.3
11
Beam Line BPM Upgrade Requirements
A1 line
Beams Document 1279-v3.3
12
Beam Line BPM Upgrade Requirements
Beams Document 1279-v3.3
13
Beamline BPM Upgrade Technical Overview
  • Use BPM pickups already in place (4 styles)
  • MI8, Main Ring, Accumulator, Debuncher
  • Use cables currently installed (RG8/RG213)
  • Examined whether pre-amps needed
  • Use Echotek digital receiver to digitize and
    process analog signals
  • Use D/S for position, S for intensity
  • Used in Recycler, NUMI, Tevatron
  • System design draws heavily upon Recycler, NUMI,
    and Tevatron systems
  • System Design based upon NUMI model
  • Front-end software from Recycler/NUMI
  • Same VME crate, Echotek Clock boards used in
    Tevatron

14
Beamline BPM Upgrade System Overview
Clock
Trigger
VME
Ethernet
PPC Controller Calculate Position Intensity
Echotek Digitize Downconvert
ACNET
VME Crate
A,B
Front Panel Cables
Analog Filter Gain/Att
Rack In Service Building
A
Pickup In Tunnel
Cables (RG8/RG213) to Service Building
Analog Filter Gain/Att
B
15
Beamline BPM Upgrade Electronics Overview
VME Backplane
PPC Controller handles front end software,
readout, and communication
Digital PS
CD Clock Board provides each Echotek board
with clock input (74MHz)
Echotek
Echotek
Echotek
Echotek digitizes downconverts the 8 analog
inputs (4 bpms)
Ethernet
IP Modules
Trigger Fanout
PPC Controller
CD Clock Board
Trigger Fanout generates trigger input for each
Echotek from BeamSync
IP Modules modules to decode TCLK, generate
triggers, calibration I/O
Analog Filter filters, attenuates, amplifies
analog signal as needed
Linear PS
Test/Ctrl Module handles setup of filter
modules including test pulses
Analog Filter
Analog Filter
Analog Filter
Test/Ctrl Module
Separate crate for Analog Modules linear PS
existing control software
BPM Cables from Tunnel
16
Beamline BPM Upgrade Analog Filter Module
  • 53MHz Bunched Beam
  • 1-4 large intensity bunches (TeV)
  • 7-84 consecutive bunches (rev P, Stacking)
  • 2.5MHz Bunched Beam
  • 4 bunches Accumulator to Main Injector
  • Test Feature (Electronics)
  • Inject 2.5MHz or 53MHz test signal
  • AB, AltB, AgtB
  • Proto Type 2 layer board
  • Done by EE support
  • Checkout since mid Feb
  • Production Boards
  • Expect 5 next week
  • Full Quantity (46) available in June

17
Beamline BPM Upgrade Test Application
18
Beamline BPM Upgrade Initial Testing
  • Teststand on 2nd floor Transfer Gallery for
    initial testing
  • Full VME system ppc, echotek, trigger modules,
    clock prototype and AWG for signal input
  • Using Prototype Analog Module
  • Using R25 diagnostic application
  • Used to evaluate system performance and digital
    filter testing

19
Beamline BPM Upgrade Initial Installation
  • New rack installed at F23
  • Split pickup signals to both old and new system
  • Use for beam commissioning in parallel with old
    system
  • Initial installation rack full infrastructure
    currently installed (minus required number of
    filter modules)
  • Used to evaluate Filter Module prototype

Data Logger
Fast Time Plot
20
Beamline BPM Upgrade Application Software
  • BPM Plots/List (I39, P54, T39)
  • Configuration control of beamline bpms, make
    measurements and archive data
  • APx Lattice (P143)
  • Perform orbit measurements and compare with
    archived data, apply orbit corrections
  • Reverse Proton Tuneup (P150)
  • Similar to P143 for reverse protons
  • Pbar Differential Orbit Measurement (P163)
  • Gathers orbit data while adjusting trims
    measuring lattice parameters
  • Shot Data Acquistion (SDA)
  • Expect existing applications to continue to see
    protons with minimal changes
  • More extensive modifications or new applications
    will be needed to monitor anti-protons

21
Beamline BPM Upgrade Installation Plan
  • Complete System Installation at F23 (AP1)
  • Infrastructure in place
  • Rack, crates, power supplys, cables, etc
  • VME electronics complete and operational
  • Front-end software complete and being used for
    testing
  • Expect to have 2-3 Filter Modules installed in
    mid May
  • Complete installation in early June (10 Filter
    Modules)
  • Remaining Locations
  • AP3 AP30, F27, P1 MI60S, P2 F2, A1 MI60N
  • Setup and perform initial checkout on 2nd floor
  • Remove old system and install new 1 rack at a
    time
  • User software must handle mix of old new for
    protons
  • Plan to begin mid June, complete in July

22
Beam Line BPM Upgrade - Acknowledgements
  • Hardware
  • John Van Bogaert, Bob Dysert, Claudio Rivetta
    (SLAC), Craig McClure, Glen Johnson, Bakul
    Banerjee, Bob Forster, Bill Haynes, Vince
    Pavlicek
  • Software
  • Duane Voy, Charlie Briegel, Bob West, Brian
    Hendricks, Lin Winterowd
  • Review process
  • Steve Werkema, Ioanis Kourbanis, Valeri Lebedev
  • Oversight, Consulting, etc.
  • Nathan Eddy, Bob Webber, Peter Prieto, Amber
    Larson, Elvin Harms

23
Beam Line BPM Upgrade - Summary
  • An upgrade to the P1, P2, AP3, AP3, A1 BPM
    systems has been identified as necessary and is
    included as part of Run II Upgrades/Frequent
    Transfers project
  • Upgrade design draws on recent BPM upgrade
    experience (Tevatron, Recycler, NuMI)
  • Unique design for both 2.5 and 53 MHz operation
  • Design is largely complete testing with beam is
    in progress at F23
  • Anticipated completion this summer
  • MI upgrade will build on this experience

24
Arm Trigger Events
25
53MHz Beam Signal Parameters
  • Max Echotek input 1.1Vpp
  • Measurement range requirements /-15mm
  • Yields 900mVpp maximum at 0mm (AB)
  • Choose to use 700mVpp to give some headroom

26
Filter Module Testing
  • 1st Prototype from EE Support in February
  • Miscommunication on how to evaluate two solid
    state switch candidates
  • Minimized usefulness of board (2 weeks)
  • 2nd Prototype from EE Support
  • Discovered issue with output op amp unable to
    supply enough current over entire signal range (1
    week)
  • Began Real Beam testing at F23 (3 weeks)
  • Found that gain/attenuation settings needed
    adjustment
  • Found large position variations SW120
    temperature
  • Decided to make Prototype run of full board (2
    weeks)
  • Total 2 months over estimated time to produce
    production boards

27
Beamline BPM Logistics
  • MI 60 South, P1 BPMs
  • 15 BPMs -gt 4 Echoteks, 8 Analog Modules
  • MI 60 North, A1 BPMs
  • 16 BPMs -gt 4 Echoteks, 8 Analog Modules
  • F1 Service, P2 BPMs
  • 9 BPMs -gt 3 Echoteks, 5 Analog Modules
  • F23 Service, AP1 AP3 BPMs (now 2 racks)
  • 19 BPMs -gt 5 Echoteks, 10 Analog Modules
  • F27 Service, AP3 BPMs
  • 10 BPMs -gt 3 Echoteks, 5 Analog Modules
  • AP30 Service, AP3 BPMs (now 2 racks)
  • 19 BPMs -gt 5 Echoteks, 10 Analog Modules
  • Totals for 6 racks
  • 88 BPMs
  • 24 Echoteks (8 ch) 46 Analog Modules (4 ch)
  • Max of 5 echoteks 10 Analog Modules per rack
Write a Comment
User Comments (0)
About PowerShow.com