Run 2 Upgrade Meeting August 13, 2003 - PowerPoint PPT Presentation

1 / 6
About This Presentation
Title:

Run 2 Upgrade Meeting August 13, 2003

Description:

Thursday, August 28 (?) - Slip-stacking. Committee: Jim Steimel, Brian Chase, Claudio Rivetta ... Slip-stacking. Quotation from vendor for amplifiers expected ... – PowerPoint PPT presentation

Number of Views:11
Avg rating:3.0/5.0
Slides: 7
Provided by: pushp
Category:
Tags: august | jim | meeting | run | slip | upgrade

less

Transcript and Presenter's Notes

Title: Run 2 Upgrade Meeting August 13, 2003


1
Run 2 Upgrade Meeting August 13, 2003
P. Bhat
  • Agenda
  • July Status Update (Ken/Dean)
  • Reviews update (Pushpa)
  • List and discuss pre-shutdown studies and
    shutdown activities (All)
  • All upgrade-related studies to be done before
    September shutdown
  • All shutdown activities
  • readiness
  • Resources dedicated? shared?
  • Overlaps, conflicts with other work

2
Reviews Update
  • Tuesday, August 26 - Helix/separators review
  • helix step-wise plan review
  • Committee H. Edwards (chair), Jerry Annala
  • Others suggested Dave Finley, someone from
    TD
  • 2nd part late September/early October?
  • Thursday, August 28 (?) - Slip-stacking
  • Committee Jim Steimel, Brian Chase, Claudio
    Rivetta
  • Tuesday, September 30 -Wire/BBC
  • Contacting a couple of CERN people
  • Committee Helen Edwards, John Marriner,
    Koutchouk/Zimmermann (CERN), TD-rep?
  • Thursday, October 2 - 2.5 MHz acceleration
  • Committee ?
  • Documents/updates to reviewers should be
    available about 10 days before the review meeting

3
Project Status
  • Slip-stacking
  • Quotation from vendor for amplifiers expected
    this week
  • Beam studies before shutdown
  • Review scope, design, results, implementation
    plan ? start this year?
  • Dean needs July status updates!

4
(No Transcript)
5
  • Discussion To do items by Oct 8 DOE
    mini-review (8 weeks left!)
  • (1) Shutdown plan
  • Be doing
  • Recycler vacuum
  • Sergei not present Seems to be no issues
  • Tev stands, align, vacuum, helix
  • Work to proceed as planned. Vladimir presented a
    table of planned tasks (see attached)
  • AP2 align and movable quad stands
  • Keith expressed concern over availability of
    surveyors for AP2 work
  • MI dampers
  • No anticipated problems
  • various e-cool at Recycler
  • No one to report
  • Plan for startup and commissioning
  • Paul Derwent expressed concern over study time
    for proton stacking studies that they would like
    to perform at the startup. This means change in
    the polarity of the magnets in the AP2 line,
    Debuncher, D/A line, and the Accumulator.  These
    studies of proton stacking, which is higher flux
    than pbar stacking, and forward 8 GeV protons
    through AP2 and Debuncher, will be combined. 
    The high flux enables comparison of measurements
    to simulations and calculations of cooling system
    behavior.

6
Other reviews in the near-future Early Oct IPM
Oct did we do Recycler vacuum and MI dampers
in shutdown (7), (8) Oct 1 technical review of
Tevatron BPM system (10) Oct 1 define
performance parameters for the Recycler (9)