Title: Antiproton Study Periods
1Antiproton Study Periods
- Keith Gollwitzer
- DOE Tevatron Operations Review
- March 21, 2006
2Simplified Review of Operations/Studies Mode
- Stacking
- 120 GeV protons from MI through P1-P2-AP1
- Target producing secondaries
- Li Lens
- Negative 8.9 GeV/c secondaries transported via
AP2 beam line - Debuncher Ring to compress phase space (7x ?)2
(50x ??) in 2s - Transfer via D/A
- Accumulator stack pbars while compressing phase
space (5x ?)2 build a core - Reverse Protons
- 8GeV protons from MI
- Transfer line is P1-P2-AP1-AP3
- Circulate in Accumulator
- D/A transfer (really A/D)
- Circulate in (or partial turn through) Debuncher
- Extract up AP2 towards target station
3Background
- We had reached the point where the
instrumentation and orbit control made it
possible to attempt - Determining the orbit offset with respect to the
center of the quadrupoles of the Debuncher ring
and the AP2 beam line - Correct the orbit to minimize the orbit-quad
center offsets - Set the AP2-Debuncher injection region
- Proposed two week period of studies
- Studies two shifts a day
- Third shift stack to support a lower luminosity
collider program - Set for early December
4Execution Round 1
- TeVatron breaks on Monday Nov 21
- Scramble to find people for holiday weekend for
start of studies - First finished preliminary studies to set
procedures to be used during studies period - Institute third shift to investigate D/A beam
line - 15 days of reverse protons
- Debuncher beam-quad center offsets, orbit
correction and centered devices about new orbit - D/A beam line done on owl shifts
- AP2 Debuncher Injection region scanning and
setting strengths of kicker and septum - AP2 beam-quad center offsets orbit correction
- 4 days of stacking studies/start-up
- Steer secondaries beam onto AP2 reverse proton
BPM positions - Center Debuncher devices about beam
- General tune-up of kickers, RF, cooling systems,
etc.
5Preliminary Work
- Checkout of BPMs
- Preparation of timeline to acquire beam without
much interruption to ? program - Commissioning of TBT program for D/A into
Debuncher for reverse protons - Procedures for extracting reverse protons from
the Debuncher into the AP2 beam line - Attempt to minimize the effects of the Debuncher
rotator cavities on the injected reverse protons
6Commissioned Items
- Debuncher Reverse Proton Turn-By-Turn system
- Debuncher Reverse Proton partial turn extraction
up AP2 - Debuncher Component Centering application
- Debuncher Orbit-Quad offset procedure
- AP2 Orbit-Quad offset procedure
- AP2 Beam Line Correction for reverse protons
- One-Shot Timeline for establishing circulating
Debuncher beam - Admittance measurements from data-logger
- Deb Heat Rev ps to AP2 sequencer aggregate
- Procedure for setting up the AP2-Debuncher
Injection region - Procedure for D/A Beam Based Alignment
- Accumulator local vertical bump at injection
7Debuncher Work - 1
- Determination of orbit-quad center offset
- Change quad excitation and look for orbit change
- 68 quads have shunts
- 10 quads have ability to control excitation alone
- The rest are paired symmetrically about mid-point
of straight section - Concern about excitation of two quads at one time
and determining offsets for each quad - Did quad excitation orbits for nominal orbits as
well as for two 1-bumps per plane - Checked for consistency of change in offset
determination with the change of orbit due to the
1-bumps - Vertical Orbit Correction
- Attempted global fit to minimize orbit-quad
center offsets - Re-checked orbit-quad center offsets no
improvement - Use of motorized quad stands as correction
devices - Local orbit corrections to minimize orbit-quad
center offsets - Re-check while working around the ring all lt1mm
offset
8Change in Debuncher Vertical Orbit
- Several places the orbit changed by 1cm
- Angle change at injection area
- All vertical trims and a majority of the
motorized quad stands were used to perform the
correction
9Debuncher Work - 2
- Horizontal Orbit Correction
- Injection Region was only done
- Horizontal orbit-quad center offsets determined
- Centered motorized devices about orbit
- Total of 72 motors
- Lattice measurements were performed
10Setting Injection Region
- Extracted beam up AP2 from Debuncher and
determine orbit-quad center for the three
down-stream most quads - Determined horizontal closed orbit and AP2 orbit
are centered in quads. - Set vertical closed orbit to nestle under the
septum - Determine kicker strength to center beam in
septum - Determine septum strength to put beam in the
center of the three AP2 quads
11AP2 Work
- Able to have reverse protons every 15 seconds
- Determine downstream AP2 orbit-quad center
offsets - Not able to do upstream due to bussed quads and
few BPMs to make offset determination - Corrected orbit to minimize offset
- Summary of orbit changes for reverse protons
- Several places big changes, largest 2cm
- Large vertical angle at the end of AP2
- Lattice measurements
- Installed new lattice which believed to better
match Debuncher
12AP2 Orbit Change
13Limiting Aperture
- Running wave pointed to Debuncher transverse
Schottkys
Will be discussed more in next talk
14Stacking Studies
- Steered secondaries to the vertical BPM positions
found during the reverse proton studies - Steered to horizontal downstream BPM positions
- Upstream, the momentum distribution affects the
horizontal position - Problems with AP2 orbit wandering
- Traced to 120GeV protons starting with Main
Injector - Associated with amount of time between cycles
- Consistent cycle time is best
- Developed auto orbit correction program
- Does 120GeV proton correction
- Then does AP2 secondaries correction
- Identified need for additional AP2 trims
- Centered Debuncher pickups
15Orbit Wandering Stabilizing Orbit
V
Wandering
H
AP1
Horiz. AP2 Vert
10mm
10mm
V
5mm
H
Stabilized
16Early January
- Wrote up results from the December studies period
- Prepared to install new AP2 trims
- Prepared to remove Debuncher transverse Schottkys
- Determined if had more Debuncher quad shunt
freedom, then be able to change lattice - Increase Debuncher admittance
- Removes Vertical Band 4 Arrays as limiting
aperture - Control was split for 6 pairs of quads
17Middle of January
- Second TeV failure allowed for more dedicated
time - Installed two of four AP2 trims
- Obstruction search of AP2 beam pipe
- Removed Debuncher transverse Schottkys
- Tune measurements, main function, replaced by
stochastic cooling pickups - Reverse protons to correct horizontal Debuncher
orbit to quad centers in straight sections - Correction in arcs would lead to energy change
that we were not prepared to do at the time - Installed new Debuncher Lattice
- Small change to AP2 lattice for matching
- Centered Debuncher Devices about reverse proton
orbit
18More January
- TeV repair period allowed
- Running Wave identified the Extraction Kicker as
the limiting aperture in both planes. - Vertically bumped beam 2mm and essentially
achieved goal - Horizontally could bump beam 8mm and make
admittance larger but bump in dispersion changes
beam energy - Await shutdown work to motorize the kicker stand
- Different horizontal orbit also affected
Extraction - Optimized Debuncher EXtraction bump for D/A
transfers - Ramp correctors near end of Debuncher stacking
cycle so that cooled smaller beam is closer to
septum when kicker fires - Also tuned extraction kicker and septum strengths
to steer beam in D/A beam line
19February
- Intensity Studies
- Measurement of intensities through the stacking
cycle - Function of stack cycle time (see next talk)
- Function of proton intensity on target (see next
slide) - Also monitored proton beam quality
- Accumulator Cooling studies
- Stacktail and Core systems (future slide)
- Accumulator Aperture
- Investigation for less than two days (next talk)
20Intensity study 4s cycle period
Cooling was optimized after each change of proton
intensity
Injected intensity into Accumulator
Intensity end of Debuncher cycle
Normalized to Beam on Target and 6 Booster turns
Early February
Intensity at end of AP2
Stacking rate
Many other diagnostics and settings were recorded
Flux to Accumulator is fine Look to
Accumulator Cooling
Proton beam on target
21Stacktail System and the Core 4-8 GHz System
- Had been using 4-8 GHz system as a helper for the
2-4 GHz core system. Decided it was time to move
to 4-8 GHz. - Because the 4-8 GHz core system runs at twice the
frequency, the electrodes are ½ the size so the
system has a factor of two smaller momentum
reach. - Moving the core closer to Stacktail to
accommodate the smaller reach resulted in system
instabilities at moderate stacks. - Several attempts were made and we learned from
each - We now
- Use the 2-4 GHz core momentum system to augment
the hand-off between the Stacktail and the 4-8
GHz core momentum system - Run the 4-8 GHz core momentum system at MUCH
larger gain. - Plans to increase the gain of the system
- Run the Stacktail during deposition debunching to
pre-form the distribution to match the Stacktail
profile - Result 20.1 mA/hr
Early February
22Stacking Performance
23Stacking Performance
Best stacking for 1 hour for each day Average
Stacking rate for a week
24Summary
- We were able to take advantage of the TeVatron
failures - Two long periods of studies
- Due to instrumentation and orbit control upgrades
of the past few years, significant progress was
done on the Debuncher admittance and progress
made on the AP2 orbit - How much? Next talk
- We understand how to keep the studies on track
for the lengthy time period - Three study chiefs met 2-3 times daily to access
progress and direction - See an almost 25 increase in stacking rate.