Title: Collimator Design
1 Collimator Design
Adriana Bungau The University of
Manchester, UK
Annual EuroTev meeting - Frascati, Italy, 23
- 25 January 2008
2Content
- Introduction
- - SWMD collaboration
- - Collimator design - requirements
- Wakefield Measurements at SLAC-ESA
- - T480 experiment (collimators, beam
parameters) - - data analysis
- Collimator Damage Tests at ATF
- - test plan
- - schedulle
- - test equipment
- - Conclusion
3People - SWMD collaboration
Birmingham N.Watson, M Slater SFTF L.Fernandez,
G.Ellwood, J.Greenhalgh, B.Fell, S.
Appleton CERN G.Rumolo, D.Schulte,
A.Latina Lancaster D.Burton, J.Smith,
R.Tucker Manchester R.Barlow, A.Bungau,
R.Jones Darmstadt M.Karkkainen, W.Muller,
T.Weiland Also a strong collaboration with SLAC
(S.Molloy and M.Woods) for wakefield beam tests
and KEK for collimator damage.
4Requirements
- Significant problems
- short-range wakefields -gtlead to emittance
dilution and beam jitter at the IP - impact of a no of high density bunches can
damage the spoilers
20 mrad
- 1. Spoiler geometry must reduce the wakefields to
an acceptable level - - long, shallow tapers of 20 mrad,
- - short flat upper section of 0.6
r.l. - - high conductivity surface coating
- the wakefield aspects of the design are
addressed by experimental work centered around
T480 project at SLAC-ESA and simulations with
Gdfidl, Echo, Merlin, Placet (see Daniels talk) - 2. Spoilers are required to survive 1 bunch at
250 and 2 bunches at 500 GeV - - use bulk material to minimise
fractures, stress but optimal for heat flow - - long path length for errant
beams striking spoilers (large r.l graphite,
beryllium etc) - the design approach consider simulations
with FLUKA, Geant4, EGS4, ANSYS and experimental
work at KEK
0.6 r.l
5T480 experiment at SLAC-ESA
6Wakefield tests at SLAC-ESA
Aim measure the beam kick and compare it with
theoretical predictions and simulations
Beam Parameters at SLAC ESA and ILC
Beam size 100 um vertically 0.5-1.5 mm
longitudinally
7(No Transcript)
8(No Transcript)
9Designed Collimators
10ESA beamline
11 Wakefield Box
- readings from each BPM were recorded together
with the bunch charge and energy - the kick was determined by performing a straight
line fit to the upstream BPM and a separate one
to fit the downstream ones - the kick was calculated as the difference in the
slopes of these fits
12Data analysis
Luis Fernandez - Daresbury
13a 324 mrad r 2 mm
Col. 1
a 166 r 1.4 mm
(r ½ gap)
Col. 6
Col. 3
a 324 mrad r 1.4 mm
Luis Fernandez - Daresbury
14 Measured and calculated kick factor
Note quoted errors are estimates
15 Collimator Damage Experiment at ATF
16Previous simulations
Aim the collimators can be damaged by the impact
of several bunches
Luis Fernandez - DL
17Stress wave
George Ellwood - RAL
18Purpose of the ATF test
- First run at ATF
- commisioning of the vacuum vessel, multi-axis
mover, beam position and size monitors - validate the mode of operation required for ATF
tests - measurement of the size of the damage region
after individual beam impacts on test target
(validation of FLUKA/ANSYS simulations of
properties of material) - ensure that the radiation protection
requirements can be satisfied - Next phase at ATF2
- measure the shock waves within the sample (VISAR
or LDV) for single bunch and multiple bunches at
ILC bunch spacing
19ATF Schedule
February 1st week - mover commisioning at
RAL 2nd week - installation at KEK 3rd week -
testing readout of beamline instrumentation 4th
week - measurement of samples - shock wave
measurements are planned at ATF2
20Test location
21Sample Target
- we would like to use a 100µm thick
- Ti-6Al-4V sample.
- the sample will probably be held
- between knife edge grips, similar to
- those illustrated.
- we could leave the top of the sample
- free from the grips.
Grip
Exposed edge of sample
22Reference Location
23Beam operation
- Once the reference edge has been found we will
use the VG manipulator to step the sample - a known distance in X and Y.
- We will then increase the charge and try to
damage the sample. - Then we will move the sample to a new location
and try to damage with a different charge. - We will continue to do this until we have
performed all the planned tests.
24Fluka Predictions
- after testing, we intend to measure the are of
damage of each impact with a Scanning Electron
Microscope - we will know the location of each damaged region
because know the distance from the reference
edge. - this will help validate our predictions on beam
damage.
Luis Fernandez - Daresbury
25SWMD Deliverable Summary
- Engineering design for ILC mechanical spoiler,
including prototype evaluations of wakefield and
beam-damage performance. - Wakefields T480 at SLAC to evaluate wakefield
performance of candidate spoiler designs,
benchmarking calculations/modelling - 16 jaw designs studied
- Beam damage detailed simulations of beam damage
to spoiler jaws, including transient shockwave
effects - Achieved designs which satisfy beam damage
requirements - Phase 1 of beam test to verify modelling, starts
at ATF 18 Feb. 2008 - Outcome of ongoing wakefield optimisation likely
to require further iteration on candidate designs - First conceptual design for mechanical spoiler
design available, to report at EPAC08.
26SWMD Deliverables Summary
- Specification of requirements for LC spoilers -
Complete - Eurotev Report 2006-015 and ILC RDR
- Report on applicability of bench tests for ILC
collimator design - Achieved - Initial report EPAC06/EUROTeV Report 2006-056
- 2007 work ? method not suitable for quantitative
tests of collimator jaws, had been identified as
risk in EUROTeVAnnex I (amended). - Final report in preparation.
- 3D simulation of wakefields for various candidate
spoiler prototypes - Achieved - For 16 ESA collimators, most recently using
non-conformal moving mesh GdfidL - Also for ECHO-3D at EPAC06
- Additional mesh dependence studies ongoing, esp.
for smallest sz - PAC07, EPAC06, EUROTeV-Reports 2006-055
(GdfidL) and 2006-103 (MAFIA) - Parametrised wakefield characteristics of
spoilers for full simulation of the BDS - See COLSIM WP
27SWMD Deliverables Summary
- Report on wakefield beam tests - Achieved
- Analysis of 2007 and 2006 T480 data for
publication in progress, including - BPM uncertainties/calibrations, bunch length
monitoring - Original plan was to use SCP and established
instrumentation See PAC07, EPAC06, EUROTeV
Reports 2007-044, 2006-059, 2006-060 - ECHO-3D new code suitable for LC regime (long
structures, short bunches), with predictions
verified by experimental data - No public version so far
- Report on spoiler damage estimates and comparison
with test beam data Partially achieved - Simulations carried out with Fluka, Geant4 (EGS
with Keller), see EPAC06 and EUROTeV Reports
2006-015 and 2006-021 - FEA studies in ANSYS3D/Fluka of transient stress
waves, see PAC07, EPAC06 - ATF beam test approved, see PAC07, scheduled for
run 18 Feb 2008 - Optimal spoiler design to achieve requirements
Partially achieved - We have designs for material and geometry which
can satisfy beam damage requirements - Outcome of ongoing wakefield optimisation likely
to require further iteration on candidate designs - First conceptual engineering design produced
28Previous Simulations
Aim quantify collimators damage from impact of
several bunches
Temperature increase from 1 bunch impact
melting temp.
Exceeds
fracture temp.
Best candidate designs