LARP Collimator Tasks - PowerPoint PPT Presentation

About This Presentation
Title:

LARP Collimator Tasks

Description:

US LHC Accelerator Research Program BNL - FNAL- LBNL - SLAC LARP Collimator Tasks 6 October 2005 LARP Collaboration Meeting-St. Charles, IL Tom Markiewicz – PowerPoint PPT presentation

Number of Views:124
Avg rating:3.0/5.0
Slides: 47
Provided by: JimSt53
Category:

less

Transcript and Presenter's Notes

Title: LARP Collimator Tasks


1
LARP Collimator Tasks
US LHC Accelerator Research Program
BNL - FNAL- LBNL - SLAC
  • 6 October 2005
  • LARP Collaboration Meeting-St. Charles, IL
  • Tom MarkiewiczSLAC

2
Four LARP Collimation Program TasksAddress
Efficiency, Reliability and Design of Phase I
Propose a possible solution for Phase II Conundrum
  • Use RHIC data to benchmark the code used to
    predict the cleaning efficiency of the LHC
    collimation system and develop and test
    algorithms for setting collimator gaps that can
    be applied at the LHC
  • Responsible Angelika Drees, BNL Task 2
  • Understand and improve the design of the tertiary
    collimation system that protects the LHC final
    focusing magnets and experiments
  • Responsible Nikolai Mokhov, FNAL Task 3
  • Study, design, prototype and test collimators
    that can be dropped into 32 reserved lattice
    locations as a part of the Phase II Collimation
    Upgrade required if the LHC is to reach its
    nominal 1E34 luminosity
  • Responsible Tom Markiewicz, SLAC Task 1
  • Use the facilities and expertise available at BNL
    and FNAL to irradiate and then measure the
    properties of the materials that will be used for
    phase 1 and phase 2 collimator jaws proposed new
    work package
  • Responsable Nick Simos, BNL Task 4

3
2005-06-01 DOE Review of Collimation Program A
  • "The activity in collimation is impressive, with
    the work being approached in a very professional
    manner. It is a critical problem, and solving it
    will have great impact on the ability of the LHC
    to reach design luminosity. Even the task sheets
    for this project were done very professionally,
    lending confidence in a well-managed and
    well-focused activity. (The synergy with the ILC
    is clearly evident here.)"

4
Task 2 Use RHIC Data to Benchmark LHC Tracking
Codes
  • Scope
  • Install SixTrackwColl particle tracking code at
    BNL and configure it to simulate RHIC performance
    for both ions and protons.
  • Take systematic proton and ion data and compare
    observed beam loss with predictions
  • Test (and perhaps help to develop) algorithms
    proposed for the automatic set up of a large
    number of collimators
  • Resources Required
  • 50 postdoc/student supervision travel
  • Timescale
  • Now until LHC beam commissioning
  • Comments
  • Preliminary data taken comparison programs being
    improved
  • Postdoc search ongoing

5
Task 2 Progress Since Pt. Jeff Meeting
  • Guillaume Robert-Demolaize from CERN visited BNL
    for 3 weeks after PAC.
  • Special' loss proton data (1 h beam time, 2
    times) taken at 100 GeV and in one ring only
    loss maps with single collimators obtained.
  • The newest version of the SixTrack ("colltrack")
    code was copied over from CERN and compiles
    modifications were made to implement the RHIC
    style collimators (dual plane, single sided).
  • A first pass on some simulations was made with a
    few hundred turns and a varying number of
    particles (up to a few thousands) and loss maps
    produced which were then compared with the data.
    However quantitative comparison was hindered by
    the necessary debugging required with the new
    code implementation.
  • Robert-Demolaize plans to continue to debug the
    RHIC simulation code at CERN and to produce
    simulated loss maps which will then be compared
    with the datasets. It is thought that these
    comparisons may begin in August or September
    after his other CERN responsibilities are
    addressed.

6
Tertiary Collimators in IP1/IP5
LARP Collaboration
Fermilab
Nikolai Mokhov, Fermilab
  • LARP Collaboration Meeting
  • Pheasant Run, St. Charles, IL
  • October 5-6, 2005

7
TERTIARY COLLIMATORS
  • Tertiary collimators at 8.4s around IR1/5 protect
    SC triplets from tertiary halo coming from
    particles leaking from 7s secondary collimators,
    upstream beam-gas and inefficiency of MPS if
    unsynchronized beam abort.
  • These TCTs must not induce peak energy deposition
    in the triplets above the quench limit (1.6mW/gm)
    with a safety margin of 3 nor induce detector
    backgrounds at level above IP produced
    backgrounds
  • 80 x 25 x 1000mm Cu jaws at .4s 145m from IP
    added to MARS15 Halo gt 8.4s assumed to go as
    1/r operational beam loss rate at TCTV/H assumed
    to be 1E6 p/s

8
TERTIARY BEAM HALO LOSS IN IP5
Without TCTs
With Cu TCTH, TCTV
9
MARS15 RESULTS FOR COPPER TCTs
Peak power density is 0.35 mW/g in Q3. Particle
fluxes on CMS similar to those from earlier
studied accelerator backgrounds. Conclusion
keep TCT scraping rates below 2x106 p/s.
10
TERTIARY COLLIMATORS PROGRESS PLANS
  • MARS runs with without TCTs MARS runs with CU
    W TCTs
  • File of TCT induced background rays sent to CMS
  • File of Beam1 loss in TCT region calculated by
    CERN 7 received 2005-09
  • Need similar file for Beam2
  • Need similar files for momentum cleaning
    insertion IR3
  • Plan to begin updating results using these files
    beginning mid-October

11
The LARP Collimation Program
US LHC Accelerator Research Program
BNL - FNAL- LBNL - SLAC
  • TASK 4 Summary
  • Material Irradiation Studies
  • Nick Simos
  • Nikolai Mokhov

12
Task 4 Irradiation Damage Assessment of LHC
collimator materials
  • Scope
  • Irradiate 2-D weave carbon-carbon and exact
    graphite used in Phase I jaws plus materials
    considered viable for Phase II jaws
  • BNL AGS/BLIP (117 200 MeV protons)
  • FNAL120 GeV protons behind pbar target planned
  • Measure material properties thermal expansion,
    mechanical properties, thermal conductivity/diffus
    ivity and thermal shock
  • BNL Hot Cell Sample Measurement Facility
  • Resources Required
  • Irradiation hot cell use fees
  • Sample prep, measurement apparatus improvement
  • Fraction of postdoc fraction of physicist
    travel
  • Timescale
  • 2005,2006 proton runs analysis into FY2007
  • Status
  • Phase I Carbon-Carbon irradiation completed
  • Sample activation measurements completed
  • Thermal Expansion of specimens started
  • PLANNING of FY06 Post-Irradiation and Follow-up
    Irradiation Studies

13
C-C samples arrive from CERN supplier and are
assembled and pre-tested before irradiation
14
LHC Phase I 2D carbon-carbon samples Irradiated
at BNL, Disassembled, Inspected Dose/sample
measured
Beam Spot during the short 200 MeV Irradiation
at the end of the cycle
Integrated 2D carbon Exposure micro-Amp Hours gt
100,000
Preliminary Assessment 2D CC specimens normal to
the planes of reinforcing fibers and close to the
center of the beam (receiving high dose)
experienced degradation. Less degradation was
seen in the specimens along the
reinforcement. NOTE Total dose received MUCH
HIGHER than what LHC collimator jaws will see.
15
LHC Phase I and Phase II Planned Activities
  • Irradiation Damage Assessment of 2D Carbon of
    Phase I
  • Using the nickel foils of the irradiation
    assembly and deduce exact beam position and
    profile through
  • radiographic analysis. These results, combined
    with the exposure record will provide the number
    of
  • protons seen by the different specimens.
  • USE results for irradiation damage (dpa)
    estimation.
  • Refine model for dpa estimation (based on MCNPX
    code and damage cross-sections)
  • Isotope generation
  • The isotopes generated in the composite will be
    fully assessed.
  • Preliminary results show that the predominant is
    Be-7. Such result is important for collimator
    servicing.
  • CTE set-up for 250 C thermal Cycling
  • Thermal expansion measurements with cyclic
    temperature profile between room temperature
  • and 250 degrees C (as requested by LHC collimator
    group.
  • Measure effects of irradiation on the coefficient
    of thermal expansion (CTE).
  • Upgrade Apparatus to Measure Irradiation Effects
    on
  • Thermal Condutivity/Diffusivity
  • Electrical Resistivity

16
Irradiation Tests at FNAL Pbar Target Area
PRELIMINARY Layout for FNAL Pbar Target
Irradiation
Proposed Target Stack
Beam time free but need to hire/pay for
technician
17
Task1 Studies of a Rotatable Metallic
Collimator for Possible Use in LHC Phase II
Collimation System
  • If we ALLOW (rare) ASYNCH. BEAM ABORTS to DAMAGE
    METAL JAWS, is it possible to build a ROTATING
    COLLIMATOR
  • that we can cool to lt10kW, keeping TltTFRACTURE
    and PH2Olt1 atm.
  • that has reasonable collimation system efficiency
  • that satisfies mechanical space 25um accuracy
    requirements
  • Scope
  • Tracking studies to understand efficiency and
    loss maps of any proposed configuration
    (SixTrack)
  • Energy deposition studies to understand heat load
    under defined normal conditions damage extent
    in accident (FLUKA MARS)
  • Engineering studies for cooling deformation
  • Construct 2 prototypes with eventual beam test at
    LHC in 2008
  • After technical choice by CERN, engineering
    support
  • Commissioning support after installation by CERN

18
Status of Phase II Collimator Conceptual
Designat 2005-06-01 DOE Review
  • Adequate software in place and MANY studies have
    been done but
  • We do NOT yet have a conceptual design for the
    1st of the 11 collimators needed (per beam) in
    IR7
  • 28 of 30 Phase II collimators will not have a
    heating problem
  • No magic design or material which could
    simultaneously provide good efficiency with
    combination of energy absorption, thermal
    conductivity, thermal expansion to maintain 25
    um flatness tolerance over length of jaw during
    1hr/12min (90/450kW) beam lifetime transients for
    nominal jaw length (1m) and gap setting (7s)
  • Focus on
  • 150mm O.D. 25mm wall Cu jaws with helical cooling
    tubes
  • 150mm O.D. solid Cu jaws cooled with axial flow
    over 36 of arc

19
Helical and axial cooling channels
20
ANSYS thermal and structural results for full ID
cooling and limited cooling arc showing 64 less
distortion with limited cooling

360 cooling of I.D.
36 cooling arc
Note transverse gradient causes bending
Note axial gradient
61C
89C
Note more swelling than bending
support
dx221 mm Spec 25mm
dx79 mm
64 less distortion
support
21
Material evaluations
Material Reasons for rejection in favor of Copper
BeCu Beryllium is forbidden by CERN management, low cleaning efficiency due to few particles absorbed
Super Invar Poor thermal conductivity gt high temperature (866C), exceeding (by 4x) temperature at which the material loses its low thermal expansion coefficient
Inconel 718 Poor thermal conductivity gt high temperature very high deflection (1039 um)
Titanium Poor thermal conductivity gt deflection 2.7 x Cu
2219 Aluminum Relatively poor cleaning efficiency, water channel fabrication difficulty
Tungsten High temperature on water side (207C - 18bar to suppress boiling) high power density - can't transfer without boiling
22
Directions under investigation negotiation at
time of 2005-06-01 DOE Review
  • Redefine secondary hybrid system to treat 1st
    collimator as special
  • Break 1st secondary into two (unequal?) lengths
    of perhaps different materials
  • Grooved expansion slots to limit deformation
  • Adjust gaps of the first carbon metal secondary
    to reduce heat load while maintaining efficiency
    with remainder of secondary system
  • Keep 1st C-C secondary collimators jaws at 7s
    and leave out 1st metal secondary collimator
  • Relax deformation tolerance relaxed to if jaws
    expand AWAY from beam
  • Begin to deal with LHC infrastructure
    operational constraints
  • 45mm jaw gap at injection incompatible with NLC
    inspired circumferentially mounted gap adjustor
  • Look into adopting Phase I adjustment mechanism
  • Spatial constraints of LHC beam pipes tunnel a
    challenge
  • Jaw dimensions, tank dimension

23
IR7 Collimator Layout
Primary Collimators
Beam Direction
Hard Hit Secondary Collimators
24
Possible Path to Immediate RC1 Prototype Leave
TCS1 Carbon-Carbon, Remainder Cu
Inefficiency   1C-10Cu All Cu
Horizontal 2.84x10-4  3.72x10-4 
Vertical 3.63x10-4   4.36x10-4 
Skew   4.57x10-4     3.85x10-4 
25
Mechanical Model 2005-06-01 Used NLC Concept of
Central Strongback with mid-collimator jaw gap
adjuster
26
June 15-17 CERN/SLAC Collaboration Meeting
  • Attendees
  • CERN Ralph Assmann (Project Leader, Tracking),
    Allesandro Bertarelli (Mechanical Eng.), Markus
    Brugger (Radiation Issues), Mario Santana (FLUKA)
  • SLAC Tom Markiewicz, Eric Doyle (ME), Lew Keller
    (FLUKA), Yunhai Cai (Tracking), Tor Raubenheimer
  • Radiation Physics Group Alberto Fasso, Heinz
    Vincke
  • Results
  • Agreement on basic design of RC1 (1st rotatable
    prototype)
  • Transfer of many of CERN mechanical CAD files
  • Lists of
  • Further studies required
  • Outstanding Engineering Issues requiring more
    design work
  • Project Milestone List Action Items List
  • Test Installation of New FLUKA

27
Conceptual Design of RC1 (1 of 2)
  • Mechanics must fit within CERN Phase I C-C
    envelope
  • 224mm center-to-center with 88mm OD beampipes
  • 1480mm longitudinal flange-to-flange
  • 25mm adjustment/jaw (22.5mm relative to beam
    w/5mm allowed beam center motion
  • and use Phase I alignment and adjustment scheme
  • Two 75cm Cu cylindrical jaws with 10cm tapered
    ends, 95cm overall length with axes connected to
    vertical mover shafts
  • 136mm OD with 9mm taper
  • Each jaw end independently moved in 10um steps
  • Vacuum vessel sized to provide 8mm clearance to
    adjacent beam and allow gross/fine 0, 45, 90
    positions
  • Relaxed mechanical deformation specifications
  • lt25 um INTO beam guaranteed by adjustable
    mechanical stop(s)
  • Ride on groove deep enough to not be damaged in
    accident case
  • Adjustable between 5 and 15 sigma (2-6mm)
    centered on beam
  • lt325 um (750um) AWAY FROM beam _at_ 0.8E1p/s loss
    (4E11p/s)
  • Flexible support on adjustment

28
Conceptual Design of RC1 (2 of 2)
  • Assumed worst case heat load (FLUKA)
  • 11.3 kW/jaw steady state, 56.5kW/jaw transient
    (10 sec)
  • Cooling boundary conditions
  • 200 C maximum temperature of Cu
  • 27 C input H2O temperature
  • 42 C maximum allowed return H2O temperature
  • Two Cooling Schemes under consideration
  • Helical tube more secure H2O-vacuum interface
  • Axial channels w/ diverter superior thermal
    mechanical performance
  • Sufficient pressure (3 atm.) to prevent local
    boiling in transient
  • Flexible supply lines to provide 360 rotation
  • Other
  • Vacuum lt1E-7 Pa (1.3E-5 torr)
  • RF shielding scheme has been proposed

29
Proposed layout 136mm diameter x 950mm long
jaws, vacuum tank, jaw support mechanism and
support base derived from CERN Phase I
30
Vacuum tank enlarged to accommodate jaw motion.
Relative location of opposing beam pipe near
interference in skew orientations 10 deviation
31
Helical cooling passages fabrication concept
Based on CERNs design no weld or braze between
water vacuum
  • Tube formed as helix, slightly smaller O.D. than
    jaw I.D.
  • O.D. of helix wrapped with braze metal shim
  • Helix inserted into bore, two ends twisted wrt
    each other to expand, ensure contact
  • Fixture (not shown) holds twist during heat cycle
  • Variations
  • Pitch may vary with length to concentrate cooling
  • Two parallel helixes to double flow
  • Spacer between coils adds thermal mass, strength
  • Electroform jaw body onto coil

32
Adjustable central gap-defining stop
  • Stop prevents gap closing as jaw bows inward due
    to heat
  • Jaw ends spring-loaded to the table assemby
    move outward in response to bowing
  • May use two stops to control tilt
  • Slot deep enough to avoid damage in accident
  • Stop far enough from beam to never be damaged
    is out of way at injection

33
Flexible end supports used in conjunction with
central gap-defining mechanism
Adjustable central jaw stops (not shown) define
gap Flexible bearing supports allow jaw thermal
distortion away from beam
Self aligning bearing
Leaf springs allow jaw end motion up to 1mm away
from beam
CERNs jaw support/positioning mechanism. Vacuum
tank, bellows, steppers not shown.
34
RF Contact Overview
35
Jaw Support Concept unresolved issues
interferences with RF parts
36
Flex cooling supply tube concept
37
Detail of flex cooling supply tube
Stub-shaft (bearing not shown)
Contiguous with helical tube inside jaw. Formed
after assembly-brazing of jaw and installation of
bearing on stub-shaft Exits through support shaft
per CERN design Material CuNi10Fe1, 10mm O.D.,
8mm I.D.
Relaxed (as shown) coils 4
Relaxed (as shown) O.D. 111mm (4.4in)
full 360 rotation coils 5
full 360 rotation O.D. 91mm (3.6in)
full 360 rotation torque 9.1N-m (81in-lb)
Support shaft
38
Final Expected Performance of RC1 Design
39
Outstanding RC1 Unresolved Issues
  • Jaw positioning
  • Acceptance of estimated deflection by
    CERN281/869um
  • Design concept for central stop gap adjust, 5
    central position float,..
  • Bearings springs attaching jaws to vertical
    movers
  • Load capacity of steppers
  • Jaw alignment perpendicular to collimation
    direction
  • Jaw rotation
  • Specification of mechanism on crowded jaw
  • Force required to rotate jaws against cooling
    coil
  • Misc
  • Spring arrangement for H, V, S orientations
  • Springs to ensure that device fails open
  • Motors, cables, temperature sensors, position
    probes,
  • Cooling
  • Possible local boiling in transient condition
    need for P3 atm. H2O system
  • More flexible yet vacuum safe water supply for
    helical cooling
  • Vacuum safe water connection/diverter for axial
    cooling scheme

40
Other Studies Planned
  • Tracking Studies Hit maps for each of 11 IR7
    collimators/beam and efficiency with 60cm C-C
    primaries and Cylindrical 75cm jaws which
    includes effect of tertiary collimators and
    absorbers
  • FLUKA energy deposition with 60cm primaries
    cylindrical 75 cm jaws Complete self consistent
    package of tracking, FLUKA ANSYS results to
    support design choices unambiguously
  • Better definition of RC1 thermal tests
  • Remnant Prompt Dose Rate calculations
  • Engineer damage assessment mechanism into design
  • Thermal shock studies
  • Studies/experiments to verify
  • assumed extent of damage in accident assume 1mm
    for now
  • Where metal slag will wind up
  • acceptable peak temperature of jaw assume 200 C
    for now

41
FY2005 Deliverables
RC1 CDR Draft 9/30/05 32 pages figures
Collimator Assembly Test Area (SLAC-ESB)
42
FY2006 Work PlanNon-beam Mechanical Thermal
Performance of RC1
  • Single jaw thermal test one jaw with internal
    helical cooling channels to be thermally loaded
    for testing the cooling effectiveness and
    measuring thermal deformations.
  • Heating by commercial electric resistance heaters
    coupled to the jaw with thermal grease
  • Operated in a tank purged with inert gas to
    protect the copper jaw from oxidation.
  • Flexible cooling supply that wont be intended to
    allow rotation of the jaw.
  • A FE model of the test jaw will be used as a
    benchmark to evaluate the response of the test
    jaw to the test conditions.
  • Full RC1 prototype a working prototype for bench
    top testing of the jaw positioning mechanism,
    supported to simulate operation in all necessary
    orientations, but not intended for mounting on
    actual beamline supports with actual beamline,
    cooling, control and instrumentation connections.
  • Lidded vacuum tank for easy access.
  • Cooling water feed-throughs and flexible
    connections as realistic as possible.
  • A reasonable effort will be made to test RC1
    under heat loading but this will probably prove
    to be impractical.

43
FY 2006 Deliverables
  • Final version of RC1 CDR
  • Nov. 1, 2005 ?
  • External review of RC1 CDR
  • Nov. 14-18, 2005 ?
  • Dec 12-17, 2005 ?
  • Performance report on RC1
  • Sept.30, 2006

44
Inter-Lab Collaboration
  • Excellent good will cooperation limited only by
    busy work loads on other systems
  • Exchange of mechanical drawing files
  • Installation of latest FLUKA at SLAC
  • Transfer of latest mod to SixTrack
  • Latest hit maps with 60cm primaries
  • Invaluable 3 day visit by 4 CERN staff
  • Monthly video meetings mostly killed
    April-present due to visit, other meetings,
    summer,
  • Next video meeting Oct 11, 2005
  • CERN review of SLAC draft CDR
  • CERN participation in RC1 CDR review
  • Exchange of detailed technical information will
    be crucial to delivering prototypes on time
  • Drawing of support structures for H, V Skew
  • Ideally, CERN would send old prototype parts
    (i.e. everything support structure with
    steppers, motors, bellows, LVDTs, except for
    the tank cylinder jaws) rather than have SLAC
    re-fab from drawings or from transcriptions of
    drawings

45
Task 1 Conclusions
  • To meet the Jan.1, 2008 RC2 ship date requirement
    SLAC and CERN collaborators have agreed on an
    initial set of specifications for the first
    mechanical prototype RC1
  • based on extensive but incomplete studies done to
    date
  • consistent with CERN beam mechanical
    constraints which uses Phase I design to
    maximum extent
  • RC1 Prototype Conceptual Design, while not 100
    complete, has been written up and serves as a
    start point for construction.
  • report to be finalized reviewed in FY2006
  • Fabrication of RC1 in two main steps in FY2006,
    with appropriate thermal mechanical tests, should
    validate most of the design issues
  • Design extension to RC2, a beam-test-capable
    prototype, will occur in parallel
  • Good (but of course could always be better)
    communication and exchange of information marks
    collaboration between labs
  • 100 devoted manpower required to ensure success

46
Action Items from Session
  • Tertiary Collimators
  • Prepare a better defined schedule of required
    inputs from CERN and delivered results from MARS
    team
  • Radiation Studies
  • Specify when results of first irradiation cycle
    will be ready
  • Understand financial requirements of both
    continued BNL program and expansion of effort to
    Fermilab 120 GeV area
  • Crystal Collimation
  • Develop a proposal LARP sponsored RD required to
    incorporate crystal collimation into LHC where,
    when, etc.
  • Rotatable Secondary Collimator Prototypes
  • Continue work on lists shown at session
Write a Comment
User Comments (0)
About PowerShow.com