Title: INTERCONNECTION TRAINING WORKSHOP
1INTERCONNECTION TRAINING WORKSHOP
- Interconnection Co-location AspectsPresented
By - Emmanuel L. Amoah
Banjul, 11 15 July 2005
ITU/EC Regulatory Capacity Building Project for
ECOWAS countries
2PRESENTATION OUTLINEMETHODS OF INTERCONNECTION
- Co-location
- Virtual Co-location
- Customer Sited Interconnect (CSI)
- In-Span Interconnect (ISI)
3CO-LOCATION
Site Boundary
Incumbents Telephone Exchange Building
OLO
Cable Chamber
OLO
4CO-LOCATIONDRAWBACKS
- Access for other Operators personnel for
maintenance especially out side normal hours - Installation including access to cable runs
- Cost of providing secure accommodation
- Availability of accommodation especially for
future growth - Security including other facilities at the site
5CO-LOCATIONDRAWBACKS
- Access for other Operators personnel for
maintenance especially out side normal hours - Installation including access to cable runs
- Cost of providing secure accommodation
- Availability of accommodation especially for
future growth - Security including other facilities at the site
6VIRTUAL CO-LOCATION
Incumbents Telephone Exchange Building
Site Boundary
OLO Cab
Cable Chamber
7ADVANTAGES OF VIRTUAL CO-LOCATION
- Easier than co-location
- Equipment pre-installed
- Access only to site
- Cheaper with less planning than co-location
- As with co-location
- Security problems (slightly less?)
- Availability of suitable place
8VIRTUAL CO-LOCATION INSTALLATION
Planning
Civil Contract
Deliver Portacabin
Civil Work
Cable Installation
Exchange Equipment
Testing
Data Fill
9CUSTOMER SITED INTERCONNECT
Other Operators Switch or Base Station
Incumbent Operators Telephone Exchange
Standard Incumbent 2 Mbit/s Private Circuit
10CUSTOMER SITED INTERCONNECT
- Advantages
- Standard Installation Processes for Link
- Standard Maintenance Processes for Link
- Standard Deliver Time Scales for Link
- Standard Cost/Price
- Disadvantages
- Same as Collocation for other Operator but
probably less so
11CSI - INSTALLATION
Planning
Install 2 Mbit/s Link
Install Exchange Equipment
Switch Data Fill
Assemble and Test
12IN-SPAN INTERCONNECT
OLO Point of Presence
Incumbent Telephone Exchange
Foot Way Box
13SDH ISI - SEPARATION
Incumbents Telephone Exchange STM 1
OLO Telephone Exchange
Foot Way Box
14ISI INSTALLATION
Planning
Civil Contracts
Civil Work
Cable Installation
Transmission Equipment
Exchange Equipment and Data Fill
Testing
15Interconnection Training Worksop
- THANK YOU
- FOR
- YOUR
- ATTENTION!!!
Banjul, 11 15 July 2005
ITU/EC Regulatory Capacity Building Project for
ECOWAS countries