Title: PROJECT MANAGEMENT 101
1PROJECT MANAGEMENT 101
Your company name presents
2Course contents
- Overview Module Structure
- Lesson 1 Introduction to Project Management
- Lesson 2 Understanding Terminologies
- Lesson 3 PMBOK Fundamental
- Lesson 4 Enterprise Project Management
Each lesson includes a list of suggested tasks
and a set of test questions.
3Overview Module Structure
- The modules are structured into 4 building blocks
of knowledge levels. Each module is sub-divided
into Online Lecture Lesson and Workshop Lesson.
The 4 building blocks are as follows - PM 101 Basic Level
- PM 102 Intermediate Level (focus is Project
Team) - PM 103 Advance Level (focus is Project Manager)
- PM 104 Executive Level
4Course goals
- By completing all the lesson modules, you would
reach the following competencies - Build a good understanding of the fundamentals of
Project Management. - Build a good understanding of the methodology and
how it ties into your professional world as a
stakeholder. - Converse and understand conversation in the arena
of project management. - Build a high level of understanding of the
Enterprise Project Management Solutions.
5Lesson 1
- Introduction to Project Management
6Lesson 1 contents
- Lesson 1.1 The Finding at First Glance
- Lesson 1.2 What is a Project?
- Lesson 1.3 What is Project Management?
- Lesson 1.4 Change and how it impacts Projects
- Lesson 1.5 Balancing Four Elements
- Lesson 1.6 Process Methodology
Each lesson includes a list of suggested tasks
and a set of test questions.
7The Findings at a Glance
- KPMG survey demonstrates
- Boards executives are making increasing
commitments to achieve business results through
project outcomes. - These commitments are delivered through projects,
and are often articulated as project benefits to
a business case. - Both compliance performance initiatives drove,
and continue to drive, increases in project
activity, budgets and complexity.
8Reasons Why Projects Fail
- The Top 10 Reasons Projects Fail
- Inadequately trained and/or inexperienced project
managers - Failure to set and manage expectations
- Poor leadership at any and all levels
- Failure to adequately identify, document and
track requirements - Poor plans and planning processes
- Poor effort estimation
- Cultural and ethical misalignment
- Misalignment between the project team and the
business or other organization it serves - Inadequate or misused methods
- Inadequate communication, including progress
tracking and reporting
9What is a Project?
- A Project is
- A temporary endeavor undertaken to create a
unique product or service.
A StartDate Time
A FinishDate Time
10What is a Project?
- A Project is
- A temporary endeavor undertaken to create a
unique product or service.
This term means that a project
temporary Has a beginning and an end
endeavor Involves effort, work
to create Has an intention to produce something (project deliverables)
unique One of a kind, rather than a collection of identical items
product Tangible objects, but could include things like computer software, editorial or book
service Might include the establishment of a day-care center, for instance but NOT its daily operations
11What is Project Management?
- Project management is the application of
knowledge, skills, tools and techniques to
project activities to meet project requirements. - PMBOK (Project Management Body of Knowledge as
defined by the Project Management Institute -
PMI) -
- The planning, monitoring and control of all
aspects of the project and the motivation of all
those involved in it to achieve the project
objectives on time and to the specified cost,
quality and performance. - PRINCE2 Project Management Methodology
12What does it mean in simpler terms?
- A simultaneous management of four basic elements
of a project that lead to project success
Scope
Time
Budget
Resources/Performance
13Change how it impacts Project
- Changes to any one of the basic elements will
effect at least one other elements
14Balancing Four Elements
- In order to execute a project in harmony with the
four elements, we require a process
15Process
A process is a set of interrelated actions and
activities that are performed to achieve a
prescribed set of products, results or
services. PMBOK (Project Management Body of
Knowledge as defined by the Project
Management Institute - PMI)
TOOLS TECH
INPUT
OUTPUT
16Methodology
-
- A methodology is a repeatable process with
project-specific methods, best practices, rules,
guidelines, templates, checklists, and other
features for building quality systems that are
manageable and deliver value to the organization.
The methodology can be used and reused any number
of times. -
- Richard Murch (2005), Methodologies in IT
Comprehension, Selection, Implementation
17Lesson 1 Question 1
- A Project is defined as
- The work that must be done in order to deliver
the product and/or service. - A temporary endeavor undertaken to create a
unique product or service. - The amount of work in labor hours required to
complete a task. - A temporary endeavor undertaken to create a
repeatable product or service. - Answer B
18Lesson 1 Question 2
- PRINCE2 defines Project Management as the
application of knowledge, skills, tools and
techniques to project activities to meet project
requirements. - Is this true or false?
- Answer False. This is a definition of PMBOK not
PRINCE2 - The planning, monitoring and control of all
aspects of the project and the motivation of all
those involved in it to achieve the project
objectives on time and to the specified cost,
quality and performance. - PRINCE2 Project Management Methodology
19Lesson 1 Question 3
- PMBOK means
- Project Management Body of Knowledge
- Project Management Book of Knowledge
- Program Management Body of Knowledge
- Program Management Book of Knowledge
- Answer A.
20Lesson 1 Question 4
- PMBOK defines a process as a set of interrelated
actions and activities that are performed to
achieve a prescribed set of products, results or
services. - Is this true or false?
- Answer True.
21Lesson 2
- Understanding
- Terminologies
22Lesson 2 contents
- Lesson 2.1 Understanding Terminologies
- Lesson 2.2 Understanding PM Language
Each lesson includes a list of suggested tasks
and a set of test questions.
23Understanding Terminologies
- To better understand a methodology, we first must
understand the language.
24Understanding Project Management Language
- Like any other profession, project management has
a language of its own. Terminologies are like
vocabulary and we must understand them in order
to speak the language of project.
- Project Scope
- Scope Creep
- Baseline
- Milestone
- Risks
- Work Breakdown Structure
- Critical Path
- Critical Task
- Constraint
- Dependencies
- Lead/Lag Time
- Slack
25Lesson 2 Question 1
- Which is a TRUE statement for a Scope?
- The work content and products of a project or
component of a project. - Scope is fully described by naming all activities
performed, the resources consumed and the end
products which result, including quality
standards. - A statement of scope should be introduced by a
brief background to the project, or component,
and the general objective(s). - Answer A B.
26Lesson 2 Question 2
- What is a Critical Path?
- The original approved plan plus or minus approved
scope changes. - A sequence in which one task must be completed
before another task can start. - The sequence of tasks that form the longest
duration of the project that must be completed on
schedule for the entire project to be completed
on schedule. - Answer C.
27Lesson 2 Question 3
- What is a Milestone?
- A significant event in the project, usually
completion of a phase or of a major deliverable
with a 0 day duration. - A significant event in the project, usually
completion of a phase or of a major deliverable
with a 1 day duration. - A significant event in the project, usually
completion of a phase or of a major deliverable
with a of completion. - Answer A.
28Lesson 3
29Lesson 3 contents
- Lesson 3.1 Understanding Roles
- Lesson 3.2 Understanding Triple Constraint
- Lesson 3.3 Understanding Processes
- Lesson 3.4 Understanding Knowledge Areas
- Lesson 3.5 Understanding Project Plan
Each lesson includes a list of suggested tasks
and a set of test questions.
30Understanding Roles
Stakeholders
Sponsors
Customer
Co President
Project Manager
Project Team
31Understanding Triple Constraint
Quality
Time
Cost
Scope
32Understanding Processes
Initiate authorizes work, defines initial scope
Plan solidifies scope requirements
Execute/Control team performs the work,
measures variance, corrects (controls) as needed
Close formally ends phase or project
Execute
Initiate
Close
Plan
Control
33Understanding Knowledge Areas
ScopeMgt
TimeMgt
IntegrationMgt
ProcurementMgt
CostMgt
Project Management
CommunicationsMgt
QualityMgt
HRMgt
RiskMgt
34What is a Project Plan?
- A formal, approved document used to guide both
project execution and project control. The
primary uses of the project plan are to document
planning assumptions and decisions, facilitate
communication among stakeholders, and document
approved scope, cost, and schedule baselines. -
- PMBOK (Project Management Body of Knowledge as
defined by the Project Management Institute -
PMI) -
- A statement of how and when a project's
objectives are to be achieved, by showing the
major products, milestones, activities and
resources required on the project. - PRINCE2 Project Management Methodology
35What does it mean in simpler terms?
- A description what is to be done, what funds are
available, when it will be done and by whom of
the entire set of tasks that the project
requires.
Scope
Planning
Time
Managing
Schedule
Quality
Controlling
Risk
36What is NOT a Project Plan?
- Microsoft Project Schedule is NOT a Project Plan
- It is only a tool to facilitate a Project
37Lesson 3 Question 1
- Who are Stakeholders?
- Project Manager and Project Sponsor.
- Project Manager and his Project Team.
- Project Manager, Project Team and Project
Sponsor. - Individuals and organizations who are involved in
or may be affected by project activities. - Answer All Of The Above.
38Lesson 3 Question 2
- What is a Triple Constraint?
- It is Project, Program and Portfolio Management.
- It is to harmonize Scope, Time and Cost in order
not to compromise Quality. - It is to mitigate Risk, maintain Quality and Cost
in order not avoid Scope Creep. - None Of The Above.
- Answer B.
39Lesson 3 Question 3
- What are the 5 phases of a project according to
PMBOK? - Initiate, Plan, Execute, Monitor and Close.
- Initiate, Plan, Execute, Monitor and Control.
- Initiate, Plan, Execute, Control and Close.
- None Of The Above.
- Answer C.
40Lesson 3 Question 4
- What is a Project Plan?
- A document with Work Breakdown Structure, Gantt
Chart and Microsoft Project MPP file. - A formal, approved document used to guide both
project execution and project control. The
primary uses of the project plan are to document
planning assumptions and decisions, facilitate
communication among stakeholders, and document
approved scope, cost, and schedule baselines. - A statement of how and when a project's
objectives are to be achieved, by showing the
major products, milestones, activities and
resources required on the project. - Answer B C.
- B is based on PMBOK and C is based on PRINCE2
41Lesson 4
- Enterprise Project Management (EPM)
42Lesson 4 contents
- Lesson 4.1 Overview
- Lesson 4.2 Information Rollup
- Lesson 4.3 Information Connectivity
Each lesson includes a list of suggested tasks
and a set of test questions.
43Overview
- Enterprise Project Management (EPM) is the
strategic management of business and IT
priorities, investments, and projects across the
enterprise. The objective of EPM is to take full
advantage of the synergies across your enterprise
architecture, portfolio management, and project
management office disciplines to get maximum
strategic value and return on project
investments.
Enterprise Architecture
Portfolio Management
Enterprise Project Management (EPM)
PMO Project Program Management
44Information Rollup
WithoutEPM
WithEPM
HBM Executives
HBM Executives
Business Unit B President
Business Unit A President
Dependency Layer 1
Business Unit B President
Business Unit A President
Project Managers
Dependency Layer 2
Project Managers
Project Managers
Information is second-hand and has dependency
layers
Information is first-hand and on-time
45Information Connectivity
Silo Project Management Operation
Standards
Best Practices
Policies
Governance
Interconnected Project Management Operation
46Lesson 4 Question 1
- Which of the following is not incorporated into
the EPM System - Portfolio Management
- Strategic Initiatives
- Project Management
- Public Relations
- Answer d) Public Relations
47Lesson 4 Question 2
- TRUE OR FALSE
- The EPM Solution does not allow high level
executives to see detailed Business Unit
activity. - Answer False the EPM solution provides high
visibility at the corporate level
48Lesson 4 Question 3
- Which of the following information is not
available in the EPM Solution? - Best Practices
- Employee Benefits
- Standards
- Policies
- Governance
- Answer b) Employee Benefits