Section 10 WrapUp - PowerPoint PPT Presentation

1 / 2
About This Presentation
Title:

Section 10 WrapUp

Description:

All planning for T/V II is complete. All paper work to be ready by the end of this week ... repair effort S/C will not be ready for move to TV until the week of 6/25 ... – PowerPoint PPT presentation

Number of Views:27
Avg rating:3.0/5.0
Slides: 3
Provided by: mikec85
Category:
Tags: wrapup | section | this | tv

less

Transcript and Presenter's Notes

Title: Section 10 WrapUp


1
Section 10 Wrap-Up
. . . Mike Cully Swales Aerospace, Inc.
2
Wrap-Up
  • All planning for T/V II is complete
  • All paper work to be ready by the end of this
    week
  • S/C Fixturing complete and baked out
  • Chamber Cert complete
  • Thermal Analysis complete
  • Staffing identified and ready
  • Subsystem Trending Parameters identified
  • All S/C procedures ready to go by 6/15 (database
    frozen)
  • Due to SADA Cable Wrap damage and subsequent
    repair effort S/C will not be ready for move to
    TV until the week of 6/25
Write a Comment
User Comments (0)
About PowerShow.com