Title: Monthly Status Report Template V0.2
1SMS- Task Order 1 2006 Project Review
Presented to SMS/LRS Project Manager by JoAnn
Mattson Intergraph Friday, April 7, 2006
SMS Monthly Status Report Version 0.1 Monday, May
24, 2004
2Revision History
3Contents
- Project Overview
- Status Overview
- Current Stage
- Project Indicators
- Critical Issues
- Cost Status
- Technical and Schedule Status
- Issues and Concerns
- Risks
- Document List
- Accomplishments
- Summary and Discussion
4Project Overview
5Project Overview General Information
6Project Overview Description
- Project Description
- To develop a MLLRS maintenance environment for
the SDS and CDS, and to develop a High Crash
Location intersection inventory tool. - Business Problem Solved
- Maintenance of SDS CDS. Improvement of HCL
inventory.
7Project Overview Goals
- To develop, document and train NDOT on workflows
capable of maintaining and publishing NDOTs LRS
database, including the SDS, CDS and
corresponding LRMs. - To build a new baseline SDS, CDS and supporting
LRMs in a temporal-enabled maintenance
environment. - To develop and deliver enhanced data maintenance
software tools that are incorporated within
Intergraphs COTS GeoMedia Fusion, GeoMedia
Transaction Manager and GeoMedia Transportation
Manager. - Demonstrate and train users in the use of the
temporal environment for production analysis.
8Project Overview -Organization
9Project Scope - 3 Major Efforts
- Data Work CDS and SDS for Selected Counties
- Development of Maintenance Tools
- Development of HCL Application
10SMS Schedule
T1 Kick-off Original End Date
1/14/05 Actual End Date 1/14/05
T2 On-going SDS Maint Support Original End Date
4/19/05 Forecast End Date 8/29/06
T3 CDS Replacements Original End Date
9/27/05 Forecast End Date 6/13/06
T4 CDS Updates Original End Date
9/21/05 Forecast End Date 6/27/06
T5 SDS Updates Original End Date
9/26/05 Forecast End Date 8/22/06
T6 Deliver SW Maint Tools Original End Date
10/10/05 Forecast End Date 9/11/06
T7 Pilot SW Accept. Original End Date
3/23/06 Forecast End Date 1/9/07
T8 Production Support Original End Date
6/23/06 Forecast End Date 5/15/07
T9 HCL Design Original End Date 3/7/05 Actual
End Date 9/16/05
T10 HCL Development Original End Date
4/11/05 Actual End Date 1/19/06
T11 Del Trng. Workshop Original End Date
7/8/05 Actual End Date 1/6/06
T12 Accept. Pilot Original End Date
8/11/05 Forecast End Date 4/28/06
T13 Maint and Support Original End Date
8/14/06 Forecast End Date 4/30/07
11Status Overview
12Status Overview Major Tasks
13Status Overview Major Tasks
14Cost Status
15Cost Status Overview
- SMS Contract
- (750,000 awarded on 12/28/04, POP thru 9/1/06,
including 300k one time fee) - Total Funding Available 450,000.00
- Less Expended 362,337.69 (invoiced dollars)
- Funding Remaining 87,662.31
-
- Intergraph used 327,598.31 in 2005 will use
122,401.69 in 2006 - -------------------------------------------------
--------------------------------------------------
--------------------------------------------------
------------------------- - 2006 Monthly Burn Rate Estimated at 10,200.14
- (Travel Estimate Labor Estimate) (122,401.69 /
12 months) - 2006 Remaining Funding Estimate 9 months
- With 9 Months remaining, Remaining Funding
expected/monthly burn rate (87,662.31 /
10,200.14) 8.59
16Contractor Invoice Status
- Invoice Status
- Total Invoiced thru 3/31/06 362,337.69
- Invoice 1 (Jan) 13,812.88 Invoice date
3/21/05 - Pd - Invoice 2 (Feb) 32,730.00 invoice date
3/29/05 - Pd - Invoice 3 (Mar) 50,340.00 Invoice date
4/28/05 - Pd - Invoice 4 (Apr) 62,247.50 Invoice date
5/26/05 - Pd - Invoice 5 (May) 55,787.93 Invoice date
6/24/05 - Pd - Inv. 6 (June July) 56,945.00 Invoice date
8/16/05 - Pd - Inv. 7 (August) 8,695.00 Invoice date
9/26/05 - Pd - Inv. 8 (Sept.) 15,750.00 Invoice date
10/27/05 - Pd - Inv. 9 (Oct.) 11,925.00 Invoice date
11/18/05 - Pd - Inv. 10 (Nov.) 13,757.50 Invoice date
12/30/05 - Pd - Inv. 11 (Dec. Jan.) 17,944.38 Invoice
date 2/28/06 - Inv. 12 (Feb.) 1,869.44 Invoice date
3/30/06 - Net Outstanding 19,813.82
- Invoices Pending
- Invoice 13 (Mar.) 21,395.35 to be invoiced in
April
17Budget / ActualComparison by TASK
18Cost Status Summary
(Cumulative)
19Technical and Schedule Status
20Schedule Status By Task
21Schedule Status Deliverables
22Issues and Concerns
23See Risk List for issues and concerns
24Risks
25Risks Current List (April 7, 2006)
26Risks (March 10, 2006)
27Risks Current List (February 13, 2006)
28Risks (January 10, 2006)
29Risks (December 12, 2005)
30Risks November List
31Risks October List
32Risks September List
33Risks August List for reference
34Risks June/July List
35Risks May List Saved for Reference
36Risks April List for reference
37Risks (Historical list, kept for review)
38Document List
39Document List
40Accomplishments
41Accomplishments During Last Period
- March, 2006
- Delivered Washoe, NV dataset with validation
fixes for NDOTs analysis - Provided support for HCL
- Started work on SDS Data Conversion
42Summary Comments
43Summary Comments
- Intergraph has sent concerns with SDS source data
to NDOT - NDOT is in the process of reviewing the HCL
Application and providing feedback to Intergraph - NDOT is working on catching up with documents
- NDOT is validating Washoe fixes provided by
Intergraph - NDOT is validating Clark County delivery