Monthly Status Report IFMP ePayroll

Description:

Payroll and HR transactions successfully entered in FPPS for Pay Period ending 6 ... Began content customization for the Brio Insight class ... – PowerPoint PPT presentation

Number of Views:44
Avg rating:3.0/5.0
Slides: 18
Provided by: davidh45
Category:

less

Transcript and Presenter's Notes

Title: Monthly Status Report IFMP ePayroll


1
Monthly Status ReportIFMP e-Payroll
  • Ona Elliott
  • NASA Center
  • Date 7/22/2004

2
Table of Contents
  • Summary Status
  • Accomplishments
  • Activities in Progress
  • Milestones Hit Rate
  • Cost Status
  • Top 5 Issues
  • Reference Material / Backup

3
Summary Status
4

Accomplishments
  • Completed Parallel 1 Testing and Reconciliation
  • Payroll and HR transactions successfully entered
    in FPPS for Pay Period ending 6/12/2004
  • Successfully performed payroll calculation and
    produced labor cost files for all centers
  • All Centers successfully generated and posted
    bi-weekly labor data files in SAP
  • Incurred crosswalk and ledger errors
  • Had to manually load all production transactions
    that had occurred since May 3, 2004 due to old
    cross-walk data in test environment
  • SAP data revalidated and processed successfully
  • Labor Cost reconciliation completed
  • Known discrepancies documented and reviewed with
    the Centers
  • State Tax Calculations
  • NPPS and FPPS Table Errors
  • Change Requests (CRs) not scheduled until
    Parallel 2 (i.e., NEBA Insurance)
  • Keying Errors
  • Parallel 2 Prerequisite Activities
  • Completed Agency TRR and Steering Committee
    Review
  • Completed Interface Test Plan and distributed to
    Centers
  • Sent reports to DOI to be published for Parallel
    2
  • Began Payroll and HR transaction entry on July 19


5

Accomplishments
  • Functional
  • Conducted Operations Review with HR and Payroll
    Process Teams (July 15)
  • Reviewed To Be Processes
  • Discussed cutover strategy
  • Question and answer session
  • Technical Activities
  • Completed System Connectivity and Acceptance
    Testing for Center interfaces
  • Successfully completed Parallel 1 Testing of
    Priority 1 and 2 interfaces
  • Successfully completed an FPPS load test with the
    Centers
  • Completed the Integration Recovery and Restart
    and Integration Severity Level documents
  • Completed Center ORR presentation template and
    delivered to Centers
  • Scheduled Center ORRs for August 3 4
  • Constructed Installation Checklist templates and
    delivered to Agency and Center system owners for
    completion
  • Communications
  • Completed customization of the DOI Requesting
    Office WBT to NASA's needs
  • Began content customization for the Brio Insight
    class
  • Completed external Frequently Asked Questions
    (FAQ) and posted to e-Payroll Website
  • Developed FPPS Access form


6
Activities In Progress
  • Preparation for Key Milestone Events
  • War Room Planning July 12 30, 2004
  • Center Operational Readiness Review August 3rd
    and 4th, 2004
  • Agency Operational Readiness Review August 5,
    2004
  • Go-Live August 8, 2004
  • Formal Parallel 2 Activities
  • Test Activities will be managed at the IFM
    Competency Center
  • Parallel 2 transaction entry DOI visiting
    Centers throughout week of 7/19
  • Payroll Calculate and Generation of Labor Cost
    file schedule for week of 7/26
  • Technical Activities
  • Completing Agency report design and development
    23 of 26 complete
  • Completing Center interface development and
    testing for HEIDI and Center Transfers
  • Completing Center report development
  • OLA and Operations plan are in the final stages
    of review
  • Center-level ORR checklist template is in work
  • Interface cutover schedule is in work
  • Continuing to hold weekly transition meetings
    with the Centers
  • Completing Final Test Director updates for
    Parallel 1
  • Assessing Impact to Centers for Planned Delay of
    Converting NASAs Historical Data to the DOI Data
    Mart

7
Project Key Schedule Activities Metrics
  • Agency Report Development 23 of 26 reports
    complete

8
Top 5 Issues
9
Cost Status
10
Top 5 Risks
11
Reference / Backup
BACKUP
12
Issue Detail
13
Issue Detail
14
Issue Detail
15
Issue Detail
16
Summary Status
Program Criteria
17
Summary Status Criteria
Project Criteria