Title: H' Haseroth
1- Overview of the CERN Neutrino Factory Machine
Studies -
- H. Haseroth
- for the
- Neutrino Factory Working Group
2- The Basic Concept of A
- Neutrino Factory
- Proton driver
- High-power proton beam onto a target
- System for collection of the produced pions and
their decay products, the muons. - Energy spread and transverse emittance have to be
reduced phase rotation and ionisation cooling - Acceleration of the muon beam with a linac and
RLAs (Recirculating Linear Accelerators) - Muons are injected into a storage ring (decay
ring), where they decay in long straight sections
in order to deliver the desired neutrino beams.
3Goal 10E21 muons/year
4- The original idea as expressed by Kurt had the
goal of having ready two future options for CERN
at the time when LHC is running CLIC and the
Neutrino Factory. - CLIC had been started much earlier and with this
argument a distribution of RD resources of 1/3
for the NF and 2/3 for CLIC has been justified. - Formally we are not too far away from the 1/2
ratio (of course we are lower!). It must,
however, be remembered - especially when we are
compared to the US - that in our case the proton
driver (SPL and accumulator / compressor rings)
is counted as "NF activity". The proton driver is
a substantial element in our CERN scenario. In
the US this is not really counted as NF activity,
but as a mere and simple upgrade of their
existing machines.
5- Activities concerning the Proton Driver
- (Main CERN Actors with substantial fraction of
their time) - SPL (Garoby, Lombardi, Vretenar)
- Accumulator Ring (Schonauer, Metral, Cappi)
- Compressor Ring (Schonauer, Metral, Cappi)
- Fast cycling Synchrotrons (Schonauer)
6Schematic Layout of the SPL (4 MW of Beam Power)
7The SPL on the CERN site
8RAL Accumulator (1)
2.2 GeV RAL Accumulator
ISR tunnel
Mean ring radius150 m
9RAL Accumulator CERN Compressor (2)
Accumulator Compressor
Accumulator
Compressor
in ISR Tunnel
1033 Hz Operation with 3.41 1014 p/p End of
Compression (Phase painting /- 90 deg)
10 turns
8 turns
11- Non Proton Driver Activities
- (Main CERN Actors with substantial fraction of
their time) - Target and collection (magnetic horn) work, i.e.
simulations of pion production, simulations of
capture and experimental work on target issues
(Ravn, Lettry, Volker, Maugain) - Simulation of the phase rotation (energy
reduction), of the cooling channel and of the
acceleration in the first linac (Lombardi, Hanke,
Holzer) - Simulation the RLAs (Recirculating Linear
Accelerators) and of the Decay Ring (Keil,
Verdier) - Work by ST for layout on the site (Poehler)
- Detector locations being investigated (Wenninger)
12(No Transcript)
13(No Transcript)
14Principle of Ionisation Cooling
Ideally a muon is stopped by passing through some
material and is being accelerated in the forward
direction. Because it would have decayed in the
meantime, only some reduction in longitudinal and
transverse momentum is applied. The longitudinal
momentum is being replaced again by RF
acceleration. Problem Heating because of
multiple scattering.
15Why a compressor ring? Why bunch rotation? (146
bunches during 3.3?s)
Pions (used)
Pions wasted
Protons after compressor
?p
Protons in accumulator
Muons after phase rotation
Pions (used)
Muons after drift
10 ns
10 ns
1 ns
10 ns
Works only if ? ? 1 (RF gradients)
Works only if ? lt 1
1 ns
? t
Pions after target
16Asymmetric 88 MHz cavities
17- Layout of 40/80 MHz Cooling Channel
beam in
beam out
18Parameters of Recirculating Linacs (RLAs)
Parameters of Decay Ring
19Preliminary Layout of Neutrino Factory
20(No Transcript)
21- Arguments for an International Muon Cooling
Experimental Demonstration - There are quite different opinions about the
necessity to do a cooling experiment, however,
the majority believes strongly that there is a
need to demonstrate that ionisation cooling is
indeed technically feasible. Some people feel
that even the relevant programs need checking by
experiments. One remark to answer criticism like
"we know Moliere scattering and Maxwell's laws"
is that in spite of knowing Maxwell's laws and
the properties of superconducting cable one has
built not only one but several magnet prototypes
for the LHC. Muon ionisation cooling is by no
means more trivial. - As a by-product of the discussions in the context
of the cooling experiment several new ideas came
already up, which were the result of stimulating
exchange of ideas, not limited to the SPL and the
target - The idea of "Beta - beams", i.e production of
neutrino beams by decay of radioactive isotopes - Very important findings about the H2 absorber
heat load due to electron beams from the
cavities.
22- A possible (poor man's ) Muon Cooling Experiment
- The main hardware is composed of the following
items - RF cavities
- RF transmitters, modulators and charging
supplies - Cavity sc solenoids
- Hydrogen absorbers
- Measuring lines at input and output including sc
solenoids and data acquisition
23(No Transcript)
24- To minimise the cost, the following distribution
of hardware contributions is envisaged (very
personal and provisional!) - 1) One 4 cell cavity from the US collaboration
(LBNL) - 2) CERN (One rf transmitter refurbished with
pieces from Linac1, one spare borrowed. Upgrading
of power with special tube (old 516) needed.
Russian manpower is sought to help) - 3) Swiss confederation, RAL, EU money?
- 4) American / Japanese collaboration (IIT et al.)
- 5) Collaboration of different physics institutes
(V. Palladino) - a Muon Beam (PSI or RAL)
25Cooling experiment at PSI?