Title: Pathfinder Working Group
1Pathfinder Working Group
- BT Centre Showcase,
- Registration 9.45 am
- Start time 10.00 am
2Pathfinder Working Group - Agenda
- .Introductions
- .Terms of reference and objectives of Pathfinder
Working Group - .Cardiff - The facts of InterconnectionÂ
- .BTs view of technical issues/risks inherent in
a hybrid interconnection model during Pathfinder - .Proposed transfer methodology from DLE to NGS
- .Requirements for Pathfinder Programme - a free
form brainstorming session designed to deliver a
set of requirements specific to Pathfinder. - .AOB
- Customer Communication Plan
- TSG Update
3Pathfinder Working Group
- Working Group Terms of Reference
- Keith Fowler - Pathfinder Programme Manager.
4Pathfinder Working Group
- Membership
- Industry representatives and BT Wholesale
(co-chair arrangement) - Proposed Terms of Reference
- Phase 1 (now until June 05)
- Agree to conditions for collaboration during the
Pathfinder period (Out of service Oct 05 Dec
05, In service Jan 06 March 06) - Capture Pathfinder Requirements from BTW
Customers (close by 28-Feb) This has already
begun through one-on-one calls - Agree to measurement points and reporting
structure to provide all Pathfinder participants
equal access to experiences and information - Phase 2 (July 05 April 06)
- Issue of System Alternation Notices for Cardiff
DLEs - Trial Industry collaboration in the migration of
- Interconnect (target beginning migration Oct 05)
- End Customers (mass migration Jan-Mar 06)
- Review of experiences and results
- Working Group Scope
- All matters relating to migration of interconnect
arrangements and consumer and business customers
to a 21CN environment, while not overlapping
other working groups. - Meeting Frequency
- Monthly or more frequently as required
5Pathfinder Working Group
- Within Scope of Pathfinder Working Group
- Determine criteria for collaboration during this
period - Issue of System Alteration Notifications in July
- Defined methodology for movement of end customer
lines - Defined methodology for movement of services
- Defined additional reporting requirements to test
effectiveness of trial. - Outside Scope of Pathfinder Working Group
- An agreed technical arrangement to enable DLE
closure (Interconnect Working Group) - Agreed commercial arrangements for rearranging
interconnects - Charging Principles (Interconnect Working Group)
- Contract Alterations (Standard Contracts Forum)
- Future interconnect (IP, etc.) (Interconnect
Working Group) - LLU (Broadband and LLU Working Group)
- Any other workgroup themes
6Pathfinder Working Group
- Cardiff The facts of Interconnection
- Mark Ward, Head of Interconnect Numbering
Services
7Cardiff Pathfinder area - Current Interconnect
Arrangements
- 9 impacted DLEs - 7 in Cardiff, plus Bridgend
and Pontypridd - Cardiff DLE units CF/TY, CF/UC, CF/UD, CF/UE,
CF/UF, CF/UG, CF/UL - Bridgend DLE unit BNP/DA Pontypridd DLE unit
PN/DA - All Cardiff DLE units are co-located with
Cardiff Iolite NGS - 7 impacted Altnets
- 80 of circuits from 3 Altnets
- Volumes are for all interconnect E1s, including
FRIACO
8Pathfinder Working Group
- BTs view of technical issues/risks inherent in a
hybrid interconnection model during Pathfinder
9Risks and Issues associated with Interconnection
arrangements and Pathfinder.
- Risks-
- Non Movement of CP DLE Capacity prior to
Pathfinder could result in- - Increased risk of call routing errors due to a
complex data set - (21CN legacy network CPs network)
- Increased risk of QoS issues e.g. call routing
errors over-used capacity - Any Operational issues resulting would cause
increased manpower demands on both BT and CPs - Complication of eventual movement of Capacity
prior to DLE closure. - Failure to fully test the full 21CN migration
process and amend process if required
10Risks and Issues associated with Interconnection
arrangements and Pathfinder.
- Issues
- Known issues include-
- Billing in line with commercial offer - EBC?
- Some unsupported products post end-customer
transfer e.g RBWF - Trial Contract
- CPS SAD calls
- Prove designs for continuity of Interconnect
products to/from end customers. - Fall Back arrangements and criteria.
- Availability of new 21C Interconnect Products
11Mitigating Risks
- Goal is to migrate CP Interconnect prior to DLE
end-user migration - Provide sufficient time to assure stability for
all - Avoid complex routing (21CN - NGS -CP)
- Avoid need to replicate legacy/PSTN routings and
data structures - Minimize impact on perceived QoS (complex call
routing/tromboning) - Can migrate CP circuits over time without need
for whole DLE at once migration - Disengage CP circuits from actual DLE closures
- Pathfinder offers the opportunity to collaborate
on the full migration process - Trial methodology for moving CP Interconnect
circuits over time (not directly tied to mass
migration schedule) - Trial methodology for migrating end-users whole
DLE at once - Provide feedback to improve processes prior to
main 21C roll-out
12Pathfinder Working Group
- Proposed Transfer Methodology from DLE to NGS
13Legacy TDM Support - Transfer Engineering
Proposals
- Aims -
- To de-risk the transfers by use of existing NGS
switches and network routings. - To provide separation of agreed transfer
activities from progress on 21C build and DLE
closures. - To enable balanced workload for all.
- Scenarios -
- 4 that will apply in most circumstances - mix
and match. - Last 2 may apply to balance NGS capacity
- Not exhaustive - other options inc. Ceasing
Capacity, new 21C products etc. - Not prescriptive - subject to bi-lateral
agreement with each individual customer.
14DLE SITE
?
NGS
2 1 C N
DLE 2
M G W
METRO NODE
3 E1s
CP Switch
13 E1s
NGS SITE
BT Capacity
CP Capacity
Figure 1a - Configuration 1 - ISI Direct to
DLE and NGS Sites No Spare NGS CP Route Capacity
- Interconnect Scenario Before Transfer
15DLE SITE
?
NGS
2 1 C N
DLE 2
M G W
METRO NODE
3 E1s
3 E1s
CP Switch
13 E1s
NGS SITE
BT Capacity
CP Capacity
Figure 1b - Configuration 1 - ISI Direct to
DLE and NGS Sites No Spare NGS CP Route Capacity
- Interconnect Scenario After Transfer
16NGS
2 1 C N
M G W
METRO NODE
13 E1s
?
CP Switch
DLE 2
3 E1s
IEC
DLE SITE
NGS SITE
BT Capacity
CP Capacity
Figure 3a - Configuration 3 - ISI Direct to
NGS Site with IEC to DLE Site No Spare NGS CP
Route Capacity - Interconnect Scenario Before
Transfer
17NGS
2 1 C N
M G W
METRO NODE
13 E1s
?
CP Switch
DLE 2
3 E1s
DLE SITE
NGS SITE
BT Capacity
CP Capacity
Figure 3b - Configuration 3 - ISI Direct to
NGS Site with IEC to DLE Site No Spare NGS CP
Route Capacity - Interconnect Scenario After
Transfer
18DLE SITE
?
NGS
DLE 2
2 1 C N
M G W
METRO NODE
NON PARENT NGS SITE
CP Switch
NGS
3 E1s
BT Capacity
13 E1s
CP Capacity
IEC
PARENT NGS SITE
Figure 6a - Configuration 6 - ISI Direct to NGS
Site with IEC to DLE Site No CP Route to Non
Parent NGS - Interconnect Scenario Before Transfer
19New Route (if not already existing)
DLE SITE
?
NGS
DLE 2
2 1 C N
M G W
METRO NODE
NON PARENT NGS SITE
CP Switch
NGS
3 E1s
13 E1s
BT Capacity
CP Capacity
3 E1s
PARENT NGS SITE
Figure 6b - Configuration 6 - ISI Direct to NGS
Site with IEC to DLE Site No CP Route to Non
Parent NGS - Interconnect Scenario After Transfer
20- Requirements Capture for Pathfinder Programme.
21Pathfinder Working Group
- Within Scope of Pathfinder Working Group
- Determine criteria for collaboration during this
period - Issue of System Alteration Notifications in July
- Defined methodology for movement of end customer
lines - Defined methodology for movement of services
- Defined additional reporting requirements to test
effectiveness of trial. - Outside Scope of Pathfinder Working Group
- An agreed technical arrangement to enable DLE
closure (Interconnect Working Group) - Agreed commercial arrangements for rearranging
interconnects - Charging Principles (Interconnect Working Group)
- Contract Alterations (Standard Contracts Forum)
- Future interconnect (IP, etc.) (Interconnect
Working Group) - LLU (Broadband and LLU Working Group)
- Any other workgroup themes
22- ADDITIONAL TRANSFER ENGINEERING SLIDES FOR
INFORMATION ONLY
23DLE SITE
?
NGS
2 1 C N
DLE 2
M G W
METRO NODE
3 E1s
CP Switch
13 E1s 10 used for BH traffic
NGS SITE
BT Capacity
CP Capacity
Figure 2a - Configuration 2 - ISI Direct to
DLE and NGS Sites Spare NGS CP Route Capacity -
Interconnect Scenario Before Transfer
24DLE SITE
?
NGS
2 1 C N
DLE 2
M G W
METRO NODE
CP Switch
3 E1s
10 E1s
NGS SITE
BT Capacity
CP Capacity
Figure 2b - Configuration 2 - ISI Direct to
DLE and NGS Sites Spare NGS CP Route Capacity -
Interconnect Scenario After Transfer
25NGS
2 1 C N
M G W
METRO NODE
13 E1s
10 used for BH traffic
?
CP Switch
DLE 2
3 E1s
IEC
DLE SITE
NGS SITE
BT Capacity
CP Capacity
Figure 4a - Configuration 4 - ISI Direct to NGS
Site with IEC to DLE Site Spare NGS CP Route
Capacity - Interconnect Scenario Before Transfer
26NGS
2 1 C N
M G W
METRO NODE
10 E1s
?
3 E1s
CP Switch
DLE 2
DLE SITE
NGS SITE
BT Capacity
CP Capacity
Figure 4b - Configuration 4 - ISI Direct to NGS
Site with IEC to DLE Site Spare NGS CP Route
Capacity - Interconnect Scenario After Transfer
27DLE SITE
?
NGS
DLE 2
3 E1s
2 1 C N
NON PARENT NGS SITE
M G W
METRO NODE
CP
NGS
13 E1s
PARENT NGS SITE
BT Capacity
CP Capacity
Figure 5a - Configuration 5 - ISI Direct to DLE
and NGS Sites No CP Route to Non Parent NGS -
Interconnect Scenario Before Transfer
28DLE SITE
?
NGS
DLE 2
3 E1s
3 E1s
2 1 C N
NON PARENT NGS SITE
M G W
METRO NODE
CP
NGS
13 E1s
BT provided (funded)
CP provided (funded)
PARENT NGS SITE
Figure 5b - Configuration 5 - ISI Direct to DLE
and NGS Sites No CP Route to Non Parent NGS -
Interconnect Scenario After Transfer