Title: Ulysses History How Ulysses was built
1Ulysses HistoryHow Ulysses was built
2Table of Content
- 1977 Out-of-Ecliptic
- 1979 -1982 ISPM Qualification Spacecraft
- 1983 ISPM Flight Spacecraft
- 1985 Recertification 1
- 1986 Launch Campaign 1
- 1988-1989 Recertification 2
- 1990 Launch campaign 2
31977 Out of Ecliptic
- First announcement of a mission to study the
north and south pole of the Sun was made 1959 and
finally 1977 again, called Out-of-ecliptic - Study performed by Dornier System in 1977 and
1978 - The name International Solar Polar Mission (ISPM)
was chosen. - Dornier submitted and won the proposal for this
challenging spacecraft design - Later on during the run of phase C/D, a contest
was held to choose another name. - ? Winner was Professor Bertotti with the name
ULYSSES - Remark the price was two bottles of Champagne
41978 ISPM
51979 - 1982 ISPM Qualification
- The qualification was reached via a very
luxurious approach by - A Structural model spacecraft
- An Engineering Model spacecraft
- A Qualification Model spacecraft
- The structural model was used for a static load
test to proof the strength of the structure - ? an accident happened at the preparation during
lifting of the trolley, the s/c glided back onto
the frame and as result, an RTG strut was
damaged.
61981 ISPM SM Integration
- Structure Model arrived at Dornier Cleanroom
71981 ISPM QM Integration
- Qualification Model integration at Dornier
81979 - 1982 ISPM Qualification
- The Electro Magnetic Compatibility Test at ESTEC
(June 1982)
91979 - 1982 ISPM Qualification
- The qualification Thermal vacuum / thermal
balance test at Intespace, Toulouse (July
August 1982)
101979 - 1982 ISPM Qualification
- The Magnetic Test at IABG (Sept 1982)
111979 - 1982 ISPM Qualification
- After a successful testing a small drink became
standard (here after magnetic test)
121979 - 1982 ISPM Qualification
- The qualification Vibration test at IABG, Munich
(Sep 1982)
131979 - 1982 ISPM Qualification
- The qualification Acoustic Noise test at IABG,
Munich (Sep 1982)
141979 - 1982 ISPM Qualification
- All qualification tests have been successfully
passed and the go-ahead for the flight model was
given. - Some technical data of Ulysses
- Mass 367 kg
- Dimensions 3,24 x 3,33 x 2,14 meters
- Power 284 W at begin of mission, source RTG
- Communication High Gain antenna 1,65m with 20 W
X-band transmitter - Data Handling Data storage 45 Mbit tape recorder
(2 off) - Reaction Control System with 33,3 kg of Hydrazine
- AOCS Spin stabilized (5 rpm) with sun sensors
and nutation dampers - Mechanism 1 radial boom 5,5m, 1 axial boom 7,5m
- ? Designed for a life time of 5 years
151979 - 1982 ISPM Qualification
- Work at the Check-out Station
161983 ISPM Flight Spacecraft
- The flight acceptance testing followed the same
approach as for the qualification model - The following tests were performed
- Thermal vacuum / thermal balance test at
Intespace, Toulouse (July August 1983) - Electro Magnetic Compatibility Test at ESTEC
(Sept1983) - Magnetic Test at IABG (October 1983)
- All tests have been successfully passed but the
launcher (Shuttle) was not ready and a new,
unexpected phase started ? Storage
171983 ISPM Flight Spacecraft
- The flight model spacecraft has undergone a
magnetic test at IABG successfully
18Ulysses is put into storage after his flight
acceptance tests (Dec 1983)
1983 ISPM Flight Spacecraft
191985 Recertification 1
- In 1984, NASA announced a launch date for Ulysses
in May 1986 - Therefore, a recertification phase started in
January 1985 and lasted till December 1985 with a
complete verification programme. This phase was
performed in the ESTEC premises. - Some Instruments were returned 1983 for upgrading
internally and had to be integrated and
functionally tested again during this period. - In December 1985 everything was ready and Ulysses
was shipped to the Kennedy Space Centre. The team
arrived January 3, 1986.
201986 Launch Campaign 1
- The launch campaign commenced in January 1986
with the full team deployed to the Kennedy Space
Centre, Florida - USA - All final functional testing was running well
till January 28, when the accident with the
Orbiter Challenger happened - ? continuation for Ulysses was open.
- Work had continued for some weeks at KSC, but
then finally stopped by NASA and Ulysses brought
back to Europe - ? another storage period was initiated with an
open status - Most of the instruments were returned to the
Investigators for special calibration work
211988 - 1990 Recertification 2
- The recertification phase 2 started beginning
1988 until March 1990. - It contained a short thermal vacuum test at ESTEC
and a spin balance test. - This test was necessary, because the launcher
approach was changed from Centaur upper stage to
IUS and PAM-S, which had a spin rate of 60 rpm
before separation of the spacecraft.
221988 - 1990 Recertification 2
- Interface Clarification Meeting at McDonald
Douglas (1988) with PAM-S
231988 - 1990 Recertification 2
- Visiting the Experimenters in USA 1988, before
re-delivering to Europe
241988 - 1990 Recertification 2
- The end of the recertification phase at ESTEC in
March 1990
251990 Launch Campaign 2
- The launch campaign started in May 1990 and
finished with the successful launch on 6 October
1990 - The spacecraft was transported by a flight from
Amsterdam to Orlando, Florida and then by trucks
to the Kennedy Space Centre. - Unloading of the trucks was performed by the
heavy gang of the KSC, but also the entire team
has been involved.
261990 Launch Campaign 2
271990 Launch Campaign 2
- Ulysses inside the Shuttle Cargo Bay on top of
the IUS and PAM-S
281990 Launch Campaign 2
- The Shuttle Discovery (STS-41) ready for take-off
291990 Launch Campaign 2
301990 Launch Campaign 2