Introduction to LEED Building Commissioning - PowerPoint PPT Presentation

1 / 32
About This Presentation
Title:

Introduction to LEED Building Commissioning

Description:

LEED Objective Get Certified. LEED Rating Points Required ... Buildings Certified Under USGBC Guidelines. LEED- EA Prerequisite 1. Commissioning under ... – PowerPoint PPT presentation

Number of Views:685
Avg rating:5.0/5.0
Slides: 33
Provided by: markleaf
Category:

less

Transcript and Presenter's Notes

Title: Introduction to LEED Building Commissioning


1
Introduction toLEED Building Commissioning
Presented by Bob Alpers, PE TESTMARCx
Commissioning Solutions
2
Agenda
  • Benefits
  • Introduction to LEED Commissioning
  • Requirements and Deliverables
  • Process
  • Questions

3
Commissioning Purpose
  • How does the building function relative to the
    Owners Project Requirements?

4
When should we start Commissioning?
Benefits Cost Savings
Cost to Change

Concept
Design
Construction
Acceptance
Occupancy
Time
5
What is systems are impacted most?
  • Control System Problems
  • Comfort Problems
  • Air Quality Problems
  • Building Maintenance Costs
  • Operations Staff understanding

6
LEED Objective Get Certified
LEED Rating Points Required Certified 26-32
points Silver 33-38 points Gold 39-51
points Platinum 52-69 points
Buildings Certified Under USGBC Guidelines
7
LEED- EA Prerequisite 1
Commissioning under Energy and Atmosphere
8
WHAT ARE THE LEED Commissioning ACTIVITIES?
  • Energy and Atmosphere Credit Category
  • EA Prerequisite 1 ( required, must be completed)
  • Fundamental Commissioning
  • EA Credit 3 ( additional available point)
  • Enhanced Commissioning

9
Fundamental Commissioning
  • Pre-Requisite 1 Overview
  • Designate a third party Cx
  • Review OPR and BOD Document
  • Specify Commissioning in CD

10
Fundamental Commissioning
  • Prerequisite Overview (Contd)
  • Develop a Cx Plan.
  • Verify installation meets BOD
  • Verify performance of systems
  • Summary report
  • Certify Commissioned

11
Fundamental CommissioningEA Prereq. 1
  • The Process Under LEED

12
Project Milestones in Construction
Schedule
Commissioning Plan
Review Owners Functional Requirements Basis of
Design
Functional Testing
Verify Installation Pre-Functional Checklist
Scoping Meetings
Incorporate Commissioning Specification
Collect Start-up Check sheets
Final Cx Report
PLAN
DESIGN
ACCEPT
OCCUPANCY
CONSTRUCT
Project Timeline
13
Owners Project Requirements Workshops
  • Small groups to work out concepts

14
Owners Project Requirements
  • The commissioning team is responsible
  • OPR gets documented.
  • OPR is a Focus
  • OM, Efficiency, Easy of Maint., Functional
    needs.
  • Address HVAC, Lighting, Indoor Environment

15
Commissioning Plan
  • The commissioning plan must contain
  • Overview goals
  • Project information
  • Systems to be commissioned
  • Teams roles protocol
  • Describe Deliverables
  • List Key Milestones and schedule.

16
What Systems does LEED require Commission?
  • Systems and Assemblies having to do with
    operational efficiencies
  • HVAC Systems
  • Building Automation
  • Lighting Controls
  • Domestic Heating
  • Renewable Energy

17
Commissioning Specifications
  • Contract Divisions 1, 15 and 16

18
Written Test Procedures
  • Objective Must include the following
  • Verify systems installed.
  • Performs as Specified

CxA Writes the Test Procedures
19
Prefunctional Checklists (PFCs)
20
Installation Verification
Focus is OM
21
Prefunctional Check List
Electrical Conduit Wall Blocking VAV Box Access
22
Master Deficiency List
23
Verify System Performance
  • Functional Testing of Systems
  • Observe Startup Activities
  • Functionally Test Equipment and Systems

24
Functional Performance Tests (FPT)
25
Final Commissioning Report
  • Must be presented to the owner within reasonable
    time and must include
  • Executive summary
  • Testing results
  • Deficiency List and History
  • Outstanding Issues
  • BOD review.

26
Enhanced CommissioningEA Credit 3
  • The Process Under LEED

27
Enhanced Cx
  • EA Credit 3 ( additional credit 1 point)
  • Design Review
  • Contractor Submittals Review
  • Verify Training
  • 10th Month Warranty Operations Review
  • Systems manual

28
Fundamental Enhanced
Commissioning Plan
Cx Report and Systems Manual
Owners Functional Requirements Basis of Design
Submittal OM Review
Design Document Reviews Commissioning In
Specification
Functional Performance Testing
Warranty Review 10th month Operation
Revised Plan
Verify Installation Checklist
Scoping Meetings
Verify Training
Start-up
PLAN
DESIGN
ACCEPT
OCCUPANCY
CONSTRUCT
Project Timeline
29
Enhanced The Design Review
Review Mechanical Systems Sequence of Control for
Clarity
30
Enhanced -Submittal Review
Review Mechanical Equipment Submittal Documents
for Completeness
31
Enhanced Verify Training
32
Enhanced Systems Manual
Organizes the OM Manual by Commissioned System
All of Chilled Water Storage in one Section of
Manual
33
Enhanced -Verify Training
  • Training meets requirements
  • Review Spec
  • Verify meet Spec.
  • Include General Purpose of systems
  • Must include use of OM Manuals
  • Must include operation all modes
  • Must be Qualified Trainers

34
Enhanced-Warranty ReviewSeasonal Testing
Functional Tests for Summer vs. Winter Check
Warranty Status and advise
35
Issues Lessons Learned
  • General
  • Commissioning is Part of the Design Team
  • Contractors understand the commissioning TEAMs
    Role
  • Energy Efficient Systems
  • Controls Become Complex and increase Risks
  • Technology is beyond Contractor Experience
  • Coordination of interposing systems is critical
  • Control Systems
  • Integration is coordinated
  • Schematic diagrams, Sequence of control and point
    lists are necessary
  • Details of BMS get input from owner
  • Owner Training
  • Video tape or not?
  • Meeting with Staff to discuss needs
  • Detailed Description in Spec of OM needs.
  • Systems Manual training

36
Case Study
  • Community College Bldg.
  • Classroom Laboratories
  • MEP Commissioning
  • Started Late in Construction Phase
  • Issues
  • Integrate Phoenix Fume with ALC controls
  • System Balance
  • Unoccupied Mode Operation
  • Success
  • teamwork


37
LEED Commissioning
  • Questions?
Write a Comment
User Comments (0)
About PowerShow.com