Title: The Daya Bay Reactor Neutrino Experiment
1The Daya Bay Reactor Neutrino Experiment
On Behalf of the Daya Bay Collaboration
CIPANP 2009
2Maki Nakagawa Sakata Matrix
Gateway to CP Violation!
CP violation
3ne Survival Probability
Dominant ?12 Oscillation
Subdominant ?13 Oscillation
- Clean measurements of q, Dm2
- No CP violation
- Negligible matter effects
4Daya Bay Nuclear Power Plant
- 4 reactor cores, 11.6 GW
- 2 more cores in 2011, 5.8 GW
- Mountains provide overburden to shield cosmic-ray
backgrounds - Baseline 2km
- Multiple detectors ? measure ratio
5Daya Bay NPP Location
55 km
6Experiment Layout
- Multiple detectors
- per site cross-check
- detector efficiency
- Two near sites
- sample flux from
- reactor groups
20T
Total Tunnel length 3000 m
7Antineutrino Detector
Calibration units
ne p ? e n n capture on Gd (30 ms delay)
20 T Gd-doped liquid scintillator
192 8 PMTs
Gamma catcher
Buffer oil
- 3 zone design
- Uniform response
- No position cut
- 12/v E resolution
Acrylic Vessels
SS Tank
8Muon Veto System
RPCs
Water Cerenkov (2 layers)
Redundant veto system ? 99.5 efficient muon
rejection
9Gd-Liquid Scintillator Test Production
Daya Bay experiment uses 200 ton 0.1
gadolinium-loaded liquid scintillator (Gd-LS).
Gd-TMHA LAB 3g/L PPO 15mg/L bis-MSB
500L fluor-LAB
Two 1000L 0.5 Gd-LAB
5000L 0.1 Gd-LS
0.1 Gd-LS in 5000L tank
4-ton test batch production in April 2009.
Gd-LS will be produced in multiple batches but
mixed in reservoir on-site, to ensure identical
detectors.
Production Steps 1. Produce Gd solid2. Dissolve
the Gd solid in LAB and get 0.5 Gd-LAB3.
Dissolve fluors in 500L LAB4. Mix 1000L 0.5
Gd-LAB, 500L fluors-LAB, and LAB, to form 0.1
Gd-LS
Daya Bay production of 185 ton of 0.1 Gd-LS,
4-ton per batch test batch production of 3.7
ton 0.1 Gd-LS
10Controlling Systematic Uncertainties
Measured Ratio of Rates
Storage Tank
flow mass measurement
Far
Near
11Target Mass Measurement
filling platform with clean room
ISO Gd-LS weighing tank
pump stations
20-ton, teflon-lined ISO tank
Gd-LS
MO
LS
detector
Coriolis mass flowmeters lt 0.1
load cell accuracy lt 0.02
12Efficiency Energy Calibrations
Prompt Energy Signal
Delayed Energy Signal
- Stopped positron signal using 68Ge source (2 x
0.511 MeV) - ? e threshold
- Neutron (n source, spallation) capture signal
- 2.2 MeV ? e energy scale
- 8 MeV ? neutron threshold at 6 MeV
13Calibration Program
Automated calibration system
- Routine (weekly) deployment of sources.
- LED light sources
- Radioactive sources fixed energy
- Tagged cosmogenic background (free) fixed
energy and time (electronics requirement)
Monitoring system for optical properties
e and neutron sources for energy calibration
s/E 0.5 per pixel Requires 1 day (near) 10
days (far)
14(relative)
15Rates and Backgrounds
9Li
n signal
16Site Preparation
Daya Bay Near Hall construction (100m underground)
Assembly Building
Tunnel lining
Portal of Tunnel
17Hardware Progress
SSV Prototype
4m Acrylic Vessel Prototype
Transporter
Calibration Units
18Detector Assembly
Delivery of 4m AV
SS Tank delivery
Clean Room
19Sensitivity to Sin22q13
90 CL, 3 years
- Experiment construction 2008-2011
- Start acquiring data 2011
- 3 years running
20Project Schedule
- October 2007 Ground breaking
- August 2008 CD3 review (DOE start of
construction) - March 2009 Surface Assembly Building occupancy
- Summer 2009 Daya Bay Near Hall occupancy
- Fall 2009 First AD complete
- Summer 2010 Daya Bay Near Hall ready for data
- Summer 2011 Far Hall ready for data
- (3 years of data taking to reach goal
sensitivity)
21(No Transcript)