Watershed Planning - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Watershed Planning

Description:

Watershed Planning & the Corps of Engineers Robyn S Colosimo USACE - Headquarters – PowerPoint PPT presentation

Number of Views:109
Avg rating:3.0/5.0
Slides: 17
Provided by: Beth260
Category:

less

Transcript and Presenter's Notes

Title: Watershed Planning


1
Watershed Planning the Corps of Engineers
  • Robyn S Colosimo
  • USACE - Headquarters

2
Water Resources Challenges
Increasing Demand for Water
3
Watershed Planning
  • Not a new concept
  • But appears to be a new answer
  • Could be argued that all studies are watershed
    based
  • Scale is the segregating measure
  • But what is all the noise about watershed
    planning
  • Why is it getting so much attention?

4
Watershed Planning Success- Key Questions
  • What does right look like?
  • Is it one size fits all?
  • What is the role of the federal government? State
    government? Local government?
  • Are river basin commissions the only model for
    success?
  • Key Incentivizing watershed planning and not
    development of the plan

5
Mission Impossible
  • Modernize the Corps Civil Works Delivery Model
    (authorization)
  • Strategic Target 5 to 10 years out
  • Key Points
  • Apply lessons of the past
  • Avoid incremental change balance radical
    unacceptable change
  • Keep the goodness of the current project
    authorization process while removing the
    unnecessary constraints
  • Challenge thinking broadly, not narrowly not
    being deterred by the anti-change reaction
  • Real job Challenge conventional thinking
  • Key to future success Our ability to change
    (adapt)

6
Scope of Activity
  • 2 year effort
  • Year 1 research relationship cultivation
  • Year 2 cultivation of ideas
  • Targets of Opportunity
  • Policy Guidance
  • WRDA 10 (simpler measures/corrections)June 10
  • WRDA 11 (culmination of effort)- June 11

7
Progress to Date
  • Conducted Interviews of 50 individuals (March
    September)
  • Synthesizing Problem (not symptoms)
  • Rough list of ideas
  • Next Step Further solicitation of ideas
  • Begin to build support for ideas
  • Move out on actions concurrently

8
Fundamental Questions
  • Change or not to Change?
  • Or is Change Needed?
  • What is wrong with status quo?
  • Do we continue to ignore warning shots?
  • Do we let change happen to us?
  • What is on the table for consideration?
  • How can we best serve the taxpayers needs?

9
Problems (Perceived)
  • Lack of Federal Vision for Water
  • Outdated Federal Interest Definitions
  • Corps in Leadership Role
  • Complex Problems
  • Legal and Policy Constraints
  • Changing Workforce
  • Program that is a collection of projects

10
Problems (Perceived) Continued
  • Fiscal Limitations
  • Special Legislation
  • Authorization Vehicle
  • Review Process (Peer and Agency Technical)
  • Separation of Authorization and Appropriation
    Determinations
  • Cost-Sharing
  • Less Focused and Coordinated Action
  • Collaboration

11
Some Things I Have Learned in the Last Few Months
  • Congress is additive in providing direction
  • Corps may simply be a decision support agency
    (mission is to educate inform?)
  • Need to understand motivation of sponsor (money,
    permits, expertise or something else?)
  • Cost-sharing (WRDA 86) had strong unintended
    consequences
  • More tools science complicates decision
    making
  • Project by project decision making has the
    effect of incrementally building a program
  • Not good at dealing with competing interests
  • It is impossible to predict the future with
    accuracy

12
Some Things I Have Learned In the Past Few Months
(cont)
  • Technology is both a solution and problem
  • Corps litmus test for investment is best buy
    versus good enough
  • Good behavior must be incentivized
  • Cost codes/cost sharing undermine teamwork
  • Experts are few and far between ( spread thin)
  • Vision is owned by those in charge
  • Decision making IS political
  • Personalities matter
  • It is all about EXPECTATIONS/GOALS
  • Time for bold action is NOW

13
Some Initial Ideas
  • Move away from rigid b-c analyses
  • Alter cost-sharing in feasibility phase
  • Alter delivery of services to meet needs to
    region
  • Create specialized teams to work virtually with
    authority
  • Build support for federal priority setting
    (authorization appropriation)
  • Initiate priority setting through major basin
    studies
  • Build Federal State partnerships

14
Some initial ideas (continued)
  • Incentivize watershed planning
  • Grants?
  • Modify authorization appropriations processes
    (benchmark with other agencies)
  • No Chiefs Report
  • Modify Administration Review procedures
  • Create Study/Review Boards (Honest Broker)
  • Examine legal constraints remove them

15
Ultimate Goal
  • Simple, elegant, responsive, predictable and
    productive Civil Works program that meets
    contemporary and future water resources needs
  • Real goal make necessary adaptations before we
    are thrown under the bus

16
Questions ?
US Army Corps of Engineers BUILDING STRONG
Write a Comment
User Comments (0)
About PowerShow.com