1
LEED Certification
2
U.S. Green Building Council LEED Certification
  • Leadership in Energy and Environmental Design
  • Authored by the U.S. Green Building Council
  • Non-Profit Coalition Promoting the Understanding,
    Development and Implementation of Green Buildings
    (www.usgbc.org)
  • The Recognized Standard for Green Buildings

3
U.S. Green Building Council LEED Certification
  • Evaluates Environmental Performance From a Whole
    Building Perspective Over a Buildings Life Cycle
  • Uses a Point Rating System
  • Up to 69 Points Maximum
  • Levels Include LEED Platinum, Gold, Silver, and
    Bronze

4
LEED Rating Categories
  • Sustainable Sites
  • Water Efficiency
  • Energy and Atmosphere
  • Materials and Resources
  • Indoor Environmental Quality
  • Innovation and Design Process

5
One of Americas FirstLEED - Certified Buildings
Pennsylvania Department of Environmental
Protection South Central Regional Headquarters,
Harrisburg, PA
6
USGBC - LEED Certification
  • Site Credit 7
  • Landscape and Exterior Design to Reduce Heat
    Island 1-2 Points
  • Use Energy Star Roof Compliant, High Reflective
    and Low Emissivity Roofing (Initial .65 and Three
    Year Aged Reflectance of at Least .50) When
    Tested With ASTM E-408 for at Least 75 of the
    Roof Surface OR Install a Green (Vegetated)
    Roof for at Least 50 of the Roof Area.

7
USGBC - LEED Certification
  • Site Credit 6
  • Storm Water Management 1-2 Points
  • No Net Increase in the Rate or Quantity of Storm
    Water Run-off From Existing to Developed
    Conditions OR, if Existing Imperviousness is
    Greater then 50, Implement a Storm Water
    Management Plan That Results in a 25 Decrease in
    the Rate and Quantity of Storm Water Run-off
    (Green/Vegetated Roofs)

8
USGBC - LEED Certification
  • Materials Credit 4
  • Recycled Content
  • Specify a Minimum of 25 of Building Materials
    That Contain in Aggregate a Minimum Weighted
    Average of 20 Post-Consumer Recycled Content
    Material, OR, a Minimum Weighted Average of 40
    Post-industrial Recycled Content Material 1
    Point
  • Specify an Additional Minimum of 25 (50 Total)
    of Building Materials That Contain in Aggregate,
    a Minimum Weighted Average of 20 Post-Consumer
    Recycled Content Material, OR, a Minimum Weighted
    Average of 40 Post-industrial Recycled Content
    Material 1 Point

9
Converting Low Slope Roof Areas to Standing Seam
Metal
10
Advantages
  • Improves Aesthetics of Facility
  • Retrofit can be Installed Directly Over Existing
    Roof System
  • Eliminates cost of removal of existing roof
  • Building remains watertight
  • Interior of facility never exposed to elements of
    weather

11
Advantages
  • Low Life Cycle Cost
  • Use of Lightweight Framing System Avoids Load
    Issues
  • Structural analysis completed before design
  • System engineered to assure excellent resistance
    to negative wind uplift pressures

12
Before Picture
13
RTU-3 Condenser Unit on Roof Top
RTU-3 7 ton unit will be relocated to custom
platform by crane.
14
HVAC Concrete Pad Pour
15
HVAC Units
HVAC Units relocated from roof to ground
16
FANG Building 2 3
Building 3 horizontal framing members layout.
Existing roof gravel removed to membrane.
17
Materials Lay Down Area
CURA Framing System materials arrive on job
site. Stored in laydown area until move to roof
top.

18
CURA Framing System
East Coast System mobilized. Initial installation
of CURA Framing System. Perimeter Channel
19
CURA Framing System
CURA Framing System materials moved to roof top
Horizontal and vertical purlins installed front
of Building 2
20
Core Cut of Skylight
Progress photos of roof replacement. R-Mer Span
Standing Seam panels installed over CURA Framing
21
Vertical Framing
CURA Framing vertical framing members with top
mount adjustable clips.
22
Vertical Member Installation
23
Front Roof Sections
Side view of Building 2 front roof section
installation. Roofing panels just installed over
framing system.
24
Exhaust Fan
Exhaust fan extension through new R-Mer Span Roof
25
Exhaust Fan
Exhaust fan upper photo
26
FANG Building 2 3
R-Mer Span Standing Seam roof panels installed
over CURA Framing
27
Front Photo Building 2
28
After Construction
29
After Construction
30
Design Build Delivery Method
31
Trend in Commercial Roofing
  • The Design Build Delivery Method
  • The Design Build Process Gives an Owner One
    Single Point of Contact
  • Turn Key Delivery From Architectural and
    Engineering Design Through The Final Punch List

32
Trend in Commercial Roofing
  • Advantages of Design Build Process
  • Single Source Accountability
  • Design Build Firm is responsible for all aspects
    of the project
  • Accelerates Completion Dates
  • Specifications/Drawing completed in 10-14 days
  • Optimizes Project Efficiencies
  • Other trades can be included in the process

33
Trend in Commercial Roofing
  • Eliminates Change Orders and Cost Overruns
  • Firm price is determined at the onset of the
    project
  • Eliminates Re-Designs
  • Design-Builder is 100 accountable for all
    outcomes
  • Guarantees Specified Performance
  • Design-Builder guarantees project is delivered on
    time and in budget

34
Q A
THANK YOU!!!