LHC-DFBX - PowerPoint PPT Presentation

1 / 30
About This Presentation
Title:

LHC-DFBX

Description:

US LHC ACCELERATOR PROJECT Brookhaven - Fermilab - Berkeley LHC-DFBX DFBX Production Readiness Review Project Overview – PowerPoint PPT presentation

Number of Views:119
Avg rating:3.0/5.0
Slides: 31
Provided by: Willi578
Learn more at: http://www-eng.lbl.gov
Category:

less

Transcript and Presenter's Notes

Title: LHC-DFBX


1
US LHC ACCELERATOR PROJECT

Brookhaven - Fermilab - Berkeley
  • LHC-DFBX
  • DFBX Production Readiness Review
  • Project Overview
  • Joseph Rasson
  • LBNL
  • 23-24 October 2002, LBNL

2
Outline
  • Functional Flow Diagrams
  • Design Variants
  • DFBX Components
  • Engineering Activities Since May 02 Review
  • Technical Design Reviews
  • Design Change Summary
  • Acceptance Specifications and Travelers
  • Crating and Shipping Specifications
  • Project Schedule
  • Summary

3
DFBX Functional Flow Diagrams
IP1 IP5
IP2 IP8
  • IR Cryogenic and Electrical Distribution Box

4
Design Variants
  • Eight cryogenic distribution boxes
  • 6 Slightly different designs with many common
    components
  • Major variation results from connection to either
    cold or warm dipole

5
DFBX Components
  • Major subsystems
  • Power leads HTS VC leads
  • Vacuum vessel
  • Cryogenic piping
  • LHe vessel
  • Thermal shield
  • Power lead chimneys
  • Instrumentation leads
  • Super insulation

6
DFBX Components (cont.)
  • Other subsystems
  • Jacketed beam tube
  • Bus duct assembly
  • Busses
  • Lambda plate
  • Bus duct
  • Interconnect hardware
  • Alignment tools
  • Support jacks

7
Engineering Activities Since May 02 Review
  • Enhanced the Engineering Team in the following
    areas
  • Mechanical design
  • Daryl Oshatz is leading the mechanical design
    effort
  • Added more designers (2 FTEs
  • Engineering analysis
  • Steve Virostek is responsible for structural
    analysis
  • Lambda Plate RD
  • SUPERCON technician group headed by Roy Hannaford
    is supporting Jon Zbasniks effort
  • Vapor Cooled Lead
  • SUPERCON group supporting the mechanical design
    and layout
  • Ron Scanlan prepared the lead design
    specification document

8
Engineering Activities Since May 02 Review (cont.)
  • Fermilab Engineering Support
  • Cryogenic Engineering
  • Tom Peterson is providing cryogenic design
    oversight
  • Don Brown (cryogenic consultant) provided
    reviewed the design
  • Interface Specification
  • Phil Pfund is very active in supporting the
    interface specification effort
  • Kerry Ewald is generating mechanical interface
    drawings
  • High Temperature Superconducting (HTS) Lead
    Testing
  • Sandor Feher will head the HTS testing effort at
    FNAL

9
Engineering Activities Since May 02 Review (cont.)
  • Fermilab Engineering Support (cont.)
  • Procurement Effort
  • Review procurement documents
  • Participated in interaction with vendors
  • Reviewed proposal evaluation effort
  • Acceptance Criteria
  • Provided thorough review of acceptance plan
  • Jim Strait is negotiating the acceptance criteria
    with CERN

10
Recent Technical Design Reviews
11
Design Change Summary
  • More Robust Mechanical Design
  • Thrust loads and Pipe support
  • Most of pipe thrust loads were eliminated by use
    of flex hoses
  • Bus duct and overflow tank support were modeled
    and redesigned
  • Magnet G-10 spiders are no longer load path
    components
  • QRL G-10 spiders were simplified and stiffened up
  • Pipe thermal contraction
  • Thermal contraction up to 1 inch is possible with
    flexhoses

12
Design Change Summary (cont.)
  • More Robust Mechanical Design (cont.)
  • Helium tank support
  • Added invar rods for vertical support
  • Redesigned lateral and longitudinal supports
  • Modified access panel and rib thickness
  • Modified weld preps to conform to ASME Pressure
    Vessel Code
  • Completed a detailed FEA model
  • Pressure Vessel Safety Note written and approved
    by LBNL Safety Committee

13
Design Change Summary (cont.)
  • More Robust Mechanical Design (cont.)
  • Optimized thermal shield design and cooling
  • Added trace cooling channels
  • Reduces wall thickness of all panels except top
    panel
  • Simplified the design by eliminating complex
    forming
  • Reduced number of vertical supports
  • Give vendor more flexibility in forming and
    attaching panels

14
Design Change Summary (cont.)
  • Enhance Design for Manufacturability
  • More relaxed tolerances
  • Design intent is conveyed and moved tight
    toleranced to top level assemblies
  • Maintained tolerances that are tied to interface
    specifications
  • Give vendor more flexibility to manufacture pipe
    assemblies
  • Vendor can select construction and fabrication
    method
  • Vendor can substitute for elbows, Ts and
    rearrange routing
  • Simplify welding and assembly process
  • Added weld rings to address warping during
    welding which allows vendor to meet the design
    intent

15
Design Change Summary (cont.)
  • Bus Duct and Lambda Plate RD
  • Completed RD effort
  • LBNL fabrication and test plan has been developed
  • Bus duct assemblies will available at the
    cryogenic system 2 months before the first pair
    is needed

16
Design Change Summary (cont.)
  • Beam Tube
  • Beam tube cooling jacket design complete
  • Cold to warm transition layout is underway (to be
    completed Nov 02)
  • Bore tubes to be shipped to LBNL (Jan 03)
  • LBNL to fabricate and test beam tube assemblies
    then ship them to cryogenic system fabricator
  • Beam tubes are scheduled to be delivered 3 months
    before the first beam tube is needed for
    installation

17
Design Change Summary (cont.)
  • Current Lead Splice Procedures
  • Current lead splice process developed and
    prototyped
  • Used the DFBX mock-up to demonstrate the process
  • Issued purchase orders to the vendors to
  • Transfer the technology by training the vendors
    before the RFP is released
  • Assess vendors capabilities
  • By making the vendors comfortable with the
    process, we remove uncertainties that could lead
    to bids
  • Roy Hannaford visited the vendors with tools and
    fixtures to train them
  • Both vendors showed good capabilities as
    demonstrated by the samples they produced on
    their own

18
Status ofMechanical Interface Specifications
  • Fermilab is supporting the magnet mechanical
    interconnect hardware design effort
  • Not all interconnect hardware proposals have been
    accepted by CERN yet
  • Reviewing dipole as-built pipe positions (some
    are out of tolerance)
  • Pipe ends will be capped since pressure and
    vacuum leak tests will be repeated at CERN
  • Therefore pipes will be fabricated with capped
    long stubs
  • Pipe ends will be measured and cut during
    installation at CERN

19
(No Transcript)
20
Status of the fabrication drawing package
  • Detailed fabrication drawing package for DFBX-G
    and C are released
  • Top level configuration drawings for the other 5
    variations are complete
  • Bill of Materials is complete
  • All remaining unique pipe drawings ready for
    release by end of November

21
High Temperature Super Conducting Leads(HTS)
  • A total of 40 lead assemblies (20 lead pairs) are
    required
  • Full current tests of the prototype pair were
    performed at CERN in Nov 2001
  • Authorized Pirelli to start production in May
    2002
  • Cold test facility is under construction at
    Fermilab

22
High Temperature Super Conducting Leads (HTS)
(cont.)
  • HTS Production Schedule
  • Pirellis initial production schedule slipped 1.5
    months
  • Latest Pirelli schedule as of 21 Oct
  • 1st 5 pairs _at_ FNAL Dec. 2002
  • 2nd 5 pairs _at_ FNAL Jan. 2003
  • 3rd 5 pairs _at_ FNAL Feb 2003
  • 4th 5 pairs _at_ FNAL Mar. 2003
  • Leads for first box will be delivered to the
    vendor at least 4 months before they are needed

23
Vapor Cooled Leads
  • VC Leads required
  • 16 sets of 600A-3pair
  • 8 sets of 600A-1pair
  • 8 sets of 120A-5pair
  • Lead design layout was revised to provide more
    installation clearance
  • Eliminated Fisher connectors (high cost and long
    lead time)
  • Ron Scanlan prepared the performance/design
    Specification
  • Specification was reviewed by CERN and FNAL
  • Design reviewed by vendors in August

24
Vapor Cooled Leads (cont.)
  • Procurement Schedule
  • Issue RFQ 7 Oct. 2002
  • Bidder responses 8 Nov. 2002
  • Place order 10 Dec 2002
  • Deliver leads for DFBX-G Apr 2003
  • 2nd shipment_at_ LBNL May 2003
  • 3rd shipment _at_LBNL Jun 2003
  • Leads for DFBX-G will be delivered to the vendor
    3 months before they are needed for installation

25
Acceptance Specification and Travelerstatus
  • LBNL acceptance from vendor
  • Defines the tests and measurements required to
    meet functional and interface specifications
  • Defines in process inspection points that give
    the vendor flexibility in selecting the
    manufacturing process and assembly sequence
  • Defines the set of travelers to be completed by
    the vendor
  • LBNL final acceptance takes place after pressure
    and vacuum leak tests are completed at CERN

26
Acceptance Specifications and Travelers (cont.)
  • CERN acceptance from US-LHC is based on
  • Approval of LBNL-vendor Acceptance
    Specification,mainly
  • In-process tests and inspection
  • Final test/inspection prior to shipping
  • Inspection and tests at CERN after shipping
  • Approval of power lead Acceptance Specifications
  • Approval of LBNL-manufactured components
    Inspection Specifications
  • Completing a series of electrical tests at CERN
  • Hi pot and continuity tests of leads, bus duct
    and instrumentation conduits

27
Crating and Shipping Specification
  • Requirements based on FEA of shipping package
    with appropriate safety factors
  • Maximum vertical shock acceleration transmitted
    to DFBX /- 5.0 g
  • Maximum horizontal shock acceleration transmitted
    to DFBX /- 2.0 g
  • Free drop from a height of 6 inches without
    transmitting more than the vertical shock limit
    of 5.0 g
  • Crating and shipping specification document has
    been distributed to the vendors for review by
    their shipping subcontractors
  • Vendors feel comfortable with taking on the
    crating shipping responsibility

28
Project Schedule
  • Additional schedule constraints
  • US-LHC Accelerator Project Ends September 2005

29
Project Schedule (cont.)
  • Schedule forecast
  • Based on the LOI production schedule provided by
    the manufacturers
  • First DFBX Delivered 13 month ARO
  • Meets CERN requirement
  • Last (8th) DFBX Delivered 27-29 months ARO
  • Meets DOE-LHC requirement
  • However, production schedule is aggressive
  • To meet schedule extensive oversight is required
  • Highlights the urgency to get process started

30
Summary
  • Design team was enhanced
  • Fermilab is playing an active role in supporting
    the design effort
  • Mechanical design is more robust and simpler to
    fabricate and assemble
  • Detailed fabrication drawing package being
    readied for the RFP
  • LBNL components will be ready 2-3 months before
    need dates
  • HTS production has started
  • VC leads RFQ is released and order will placed in
    Dec 02
  • Project is ready to start the RFP process
  • Meeting production schedule is a major challenge
Write a Comment
User Comments (0)
About PowerShow.com