Title: Introduction, requirements of the LHC and LHC injectors
1 OPERATION OF THE LHC BEAMS IN THE SPS
E. Métral
- Introduction, requirements of the LHC and LHC
injectors challenges - The LHC zoo ? Many (proton) beams required LHC
commissioning - Main SPS supercycle foreseen in 2008 user names
- Some procedures references for the nominal beam
- Some words about the ion beams ( early ion beam
produced in the SPS in 2007)
2- Many thanks to many colleagues from OP, ABP, RF,
BI for their explanations help during the
2007 run preparation of this course! - See also procedures references (from 2007) done
by Magali http//sps-documentation.web.cern.ch/SP
S-documentation/ - Please do not hesitate for any comment!
3INTRODUCTION (1/13)
- 2 main challenges involved in the design of the
LHC - Very high magnetic field to reach the collision
energies in the TeV range - Very high luminosity necessary to provide
significant event rates at this energy
Beam current
Brightness transverse bunch density
It is limited by - Space-charge effects in the
injectors... - Head-on beam-beam interaction
at collision
It is limited by - Collective instabilities -
Cryogenic load (synchrotron radiation and
wall current) - S.C. magnet quench
4INTRODUCTION (2/13)
- ? LHC injectors challenges
- Preservation of the transverse emittance
(brightness) - Generation of the longitudinal structure (25 ns
bunch spacing)
5INTRODUCTION (3/13)
SPS operates above transition ( 21 GeV) for
LHC-type beams
Duoplasmatron Source ? 90 keV (kinetic
energy) LINAC2 Linear accelerator ? 50
MeV PSBooster Proton Synchrotron Booster ? 1.4
GeV PS Proton Synchrotron ? 25 GeV SPS Super
Proton Synchrotron ? 450 GeV LHC Large Hadron
Collider ? 7 TeV
LHC (proton) beam in the injector chain
6INTRODUCTION (4/13) ? TRANSVERSE EMITTANCE
PRESERVATION
- The initial transverse emittance is given by the
duoplasmatron source - The beam is then adiabatically bunched and
accelerated in a Radio Frequency Quadrupole
(RFQ2) under high space charge conditions - Fine-tuning of the 50 MeV Drift Tube Linac (DTL)
and of the transfer line to the PSB
Normalised, at 1?
Depends on extraction aperture, electrode shape
and space charge
?
?
?
7INTRODUCTION (5/13) ? TRANSVERSE EMITTANCE
PRESERVATION
- The beams in the Linac2 are quasi square pulses
with a length which varies depending on the user
(the beam length varies between 25 µs and 120 µs
and it is limited at the source) - The nominal LHC requirement is a beam of 180 mA
in 30 ?s at the entrance of the PSBooster - The transverse normalised rms beam emittance is
1.2 ?m - ? Challenge of transverse emittance preservation
in the injectors -
- - PSBooster ejection ? 2.5 ?m
- - PS ejection ? 3 ?m
- - SPS ejection ? 3.5 ?m
- - LHC top energy ? 3.75 ?m
8INTRODUCTION (6/13) ? LONGITUDINAL BEAM STRUCTURE
- The generation of the nominal bunch train for LHC
(25 ns bunch spacing) is done in the PS
- Double-batch injection from PSBooster due to
space charge in the PSBooster ? Rings 3-4-2-1-3-4 - Bunch splittings used instead of debunching /
rebunching due to longitudinal microwave
instability
Must be the 1st!
LHC Design Report, Ch. 7, p. 45
9INTRODUCTION (7/13) ? SPS CHALLENGES
MKE kickers issues
- Impedance reduction programme in the SPS has made
a major contribution to the ability of the SPS to
produce the LHC beam - Shielding of specific equipment, such as the
magnetic septa, identified as an impedance source - Shielding of some 900 intermagnet pumping ports
has reduced significantly the resonant impedance
in the machine and increased the stability of the
LHC beam - The nominal beam has successfully been
accelerated to 450 GeV/c, despite the discovery
that the electron cloud effect is a major issue
for the SPS ? Continued machine development to
understand and cure the phenomena in the SPS has
been accompanied by additional studies using the
SPS as a test-bed for the LHC. Periods of beam
conditioning are now routinely used to scrub
the surface of the vacuum chambers, reduce the
secondary electron yield and minimise the vacuum
pressure rise
10INTRODUCTION (8/13) ? SPS BEAM PARAMETERS
Tolerance in bunch intensity? 10
Tolerance in trans. emittance? 20
Tolerance in long. emittance? 20
11INTRODUCTION (9/13) ? NOMINAL LHC FILLING SCHEME
- PS cycle length 3.6 s
- SPS cycle length 21.6 s
- LHC filling time (for the 2 rings) 8 min 38 s
( 12 SPS cycles of 21.6 s per beam ? 24 in
total, i.e. a filling time of 24 ? 21.6 s 518.4
s)
12INTRODUCTION (10/13) ? NOMINAL LHC BEAM IN THE
SPS IN 2004
3.3 ?1013 p at 450 GeV/c (i.e. 4 ? 72 288
bunches with 1.15?1011 p/b)
13INTRODUCTION (11/13) ? NOMINAL LHC BEAM IN THE
SPS IN 2006
3.6 ?1013 p at 450 GeV/c (i.e. 4 ? 72 288
bunches with 1.24?1011 p/b)
14INTRODUCTION (12/13) ? NOMINAL (LOW INTENSITY)
BEAM EXTRACTED FROM THE SPS IN 2007
Shown by S. Myers on 26/02/08 (AB meeting)
15INTRODUCTION (13/13) ? NOMINAL (LOW INTENSITY)
BEAM EXTRACTED FROM THE SPS IN 2007
Shown by S. Myers on 26/02/08 (AB meeting)
16THE LHC BEAM ZOO (1/4)
M. Benedikt, LHC-OP-ES-0002 rev 1.0 (2004)
Pilot safety beam
- Interest in the 50 ns variant has been
resuscitated (since few months) to try and
satisfy the need for low luminosity in IP2!
17THE LHC BEAM ZOO (2/4)
Needed before each physics coast
18THE LHC BEAM ZOO (3/4)
19THE LHC BEAM ZOO (4/4)
20MAIN SPS SUPERCYLE FORESEEN IN 2008 USER NAMES
(1/6)
26 GeV/c or acceleration up to 37 GeV/c
- SFTLONG1 (13 BP) CNGS1 (5) CNGS2 (5) CNGS3
(5) LHCFAST1 (7) MD1/2 (5) 40 BP 48 s - Later, when LHC is filling properly we will have
to switch to an LHC filling supercycle
21MAIN SPS SUPERCYLE FORESEEN IN 2008 USER NAMES
(2/6)
- In 2007
- SPS timing user names changed to beam-type names
- At the same time we got the possibility via LTIMs
to activate a given RF MMI stack for a given
timing user ? Tended to 'decouple' the RF MMI
stack name from the timing user name - The BI settings are organized by beam type and
can be loaded to any timing user ? This also
decouples the BI settings from the timing user
names - In 2008 ? The idea is to go back to a given
timing user associated to a certain SPS magnetic
cycle more than to a certain beam type - LHC1 LHC2 for nominal MAGNETIC LHC cycles
- LHCFAST1 LHCFAST2 for the short LHC MAGNETIC
cycles - LHCION1 LHCION2 for ion MAGNETIC cycles
22MAIN SPS SUPERCYLE FORESEEN IN 2008 USER NAMES
(3/6)
For the short magnetic cycles
24 in 2007
32 in 2008
23MAIN SPS SUPERCYLE FORESEEN IN 2008 USER NAMES
(4/6)
- ? Example of a Long MD cycle in 2008
- Timing user LHC1. LSA settings mapped to that
user - If we take a nominal beam on the cycle, RF MMI
stack for LHC1 mapped to stack LHC25NS. BI
settings for LHC-NOMINAL mapped to LHC1 - If we take a pilot beam on the cycle, RF MMI
stack for LHC1 mapped to stack LHCPILOT. BI
settings for LHC-PILOT mapped to LHC1 - 'Early' LHC filling SC with two fast LHC cycles.
Cycles are mapped to timing users LHCFAST1
LHCFAST2. LSA settings mapped to those users - If we take a pilot beam on the 2 cycles, RF MMI
stack for LHCFAST1 LHCFAST2 mapped to stack
LHCPILOT. BI settings for LHC-PILOT mapped to
LHCFAST1 LHCFAST2 - If we take an individual bunch on the 2 cycles,
RF MMI stack for LHCFAST1 LHCFAST2 mapped to
stack LHCINDIV. BI settings for LHC-INDIV mapped
to LHCFAST1 LHCFAST2 - If we take 12 bunches (1 PSB ring) on the 2
cycles, RF MMI stack for LHCFAST1 LHCFAST2
mapped to stack LHC25NS. BI settings for
LHC-NOMINAL mapped to LHCFAST1 LHCFAST2
24MAIN SPS SUPERCYLE FORESEEN IN 2008 USER NAMES
(5/6)
Different acceleration between NOMINAL and FAST
cycles
4320 (or 15120)
7590 (or 18390)
60 (or 10860)
25MAIN SPS SUPERCYLE FORESEEN IN 2008 USER NAMES
(6/6)
The (proton) LHC user names in the PS PSB
26ALTERNATIVE FILLING SCHEME!
SOME PROCEDURES REFERENCES FOR THE NOMINAL (4 ?
72 BUNCHES) BEAM
To see how things vary in this case
FILLING PATTERN (1/3)
NOMINAL FILLING SCHEME!
274 ? 72 bunches
FILLING PATTERN (2/3)
285 ? 48 bunches
FILLING PATTERN (3/3)
58
115
172
229
9
9
9
9
Batch 5
48
48
48
48
48
1.2 s
1.2 s
1.2 s
1.2 s
1.2 s
570
285
855
1140
29PROCEDURE TO SET UP THE INJECTION (1/4)
- Check that the PS is not in simulated frequency
6 BPM of TT2 4 BPM in TT10
Last 10 BPM of TT10
Couplers with logarithmic amplifiers in TT10 ? No
gain
30PROCEDURE TO SET UP THE INJECTION (2/4)
- Injection kickers settings
The first 3 kickers can give until 11 ?s,
whereras the 4th one gives 2.5 ?s
31PROCEDURE TO SET UP THE INJECTION (3/4)
32PROCEDURE TO SET UP THE INJECTION (4/4)
33PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(1/13)
ENERGY MATCHING PROCEDURE
- Inject the beam. Adjust BSPS till the first
turn is centered - Switch on RF (if not already
done) - Measure the orbit (about 100 ms after
injection) - Check the position at which the
beam is captured If the beam is not centered,
(that means the energy in the PS is such that
the revolution period in the SPS does not
correspond to the RF frequency in the SPS),
adjust BSPS till the beam is centered after
capture - The first turn is then no longer
centered - BPS should be adjusted (so as to
adjust the beam energy). - An excel spreadsheet
can be used to determine by which amount BPS
should be changed
34PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(2/13)
- Tunes (measured) ? To avoid slow beam losses from
resonances (ecloud, space charge tune spreads) - SPS Control ? SPS Beam Control ? New Trim editor
- Qx ? 26.13
- Qy ? 26.185
- When there are more than 1 injection, Qx
increases with the intensity and Qy decreases
with the intensity (Laslett tune shift) ? One has
to compensate for this effect - In order to keep the coherent tune constant the
Qx settings need to be decreased by 0.008 in
correspondence of every injection and Qy must be
increased by 0.005 - ? Jorg added in 2007 a menu in the MultiQ to
correct the tune shift for each injection GO in
the 'Tools' menu (main program toolbar) and check
the box 'Show LHC beam "Injection Q"....'. This
will make the appropriate menu/DV plot
appear/disappear
35PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(3/13)
- Chromaticities (measured) ? To stabilize the beam
with respect to the instabilities due to single
bunch (effects from electron cloud) - SPS Control ? SPS Beam Control ? New Trim editor
- ?x ? 0.2
- ?y ? 0.4
- BEWARE DO NOT TRIM THE RADIAL STEERING BEFORE
THE LAST INJECTION (even for chromaticity
measurements). This would change the RF frequency
we are sending to the PS - and the 40 and 80 MHz
cavities will not like it!!! The radial position
can be trimmed after the last injection - Octupoles settings ? To achieve a machine as
linear as possible - SPS Control ? SPS Beam Control ? New Trim editor
- H - 1 m-4 (Settings are not critical, but they
shouldn't be too high ? Not larger than about 1
m-4) - V 0
36PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(4/13)
- Transverse dampers ? The transverse dampers are
essential in the horizontal direction in order to
damp the instabilities due to coupled bunches
(effects from electron clouds and resistive
wall). In the vertical plane they are mainly used
to damp resistive wall instability - Gain (for the nominal beam)
- Horizontal 23 dB
- Vertical 15 dB
- For 1 bunch or 12 bunches OFF
- For 72 bunches ? There are 2 pairs of transverse
dampers per plane. They should be ON during the
whole cycle
37PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(5/13)
- Timings ? SPSOP CCM ? Working Set ? RF-SPEC ?
SPSRF7 - Switching on timings
- "tdamper h1 on opera"
- "tdamper h2 on opera"
- tdamper v1 on opera
- tdamper v2 on opera"
- Settings
- Timings defined with respect to event
SIX.F1KFO-CT - Coarse delay 995 ms (? i.e. 5 ms before 1st
injection) - Switching off timings
- "tdamper h1 off opera"
- "tdamper h2 off opera"
- tdamper v1 off opera
- tdamper v2 off opera"
- These should always be ENABLED
- Settings
- Timings defined with respect to event
SIX.F1KFO-CT - Coarse delay 20000 ms
Forewarning 1000 ms before first occurence of
injection
OFF timing should be a few ms after the timing
of the standard dump
38PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(6/13)
39PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(7/13)
40PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(8/13)
Averaging over 5 orbits
41PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(9/13)
BEAM DUMP SETTINGS
42PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(10/13)
TT2 / TT10 LINE
May be not the latest optics!
43PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(11/13)
Max ?y QD ODD number
Max ?x QF EVEN number
SPS RING
?? ? 90º
SPS transverse tune ? 6 ? (18 / 4) 27!
? Qx ? 26.13 and Qy ? 26.18
44PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(12/13)
TI2
45PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(13/13)
TI8
46PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(1/13)
- RF loops
- PHASE LOOP (measures the difference between the
phase of the RF and the phase from the beam and
tries to minimize it) - SYNCHRO LOOP ? We stay always on the synchro loop
instead of going at some point on the radial loop
for acceleration (we cannot do this with the FT
beams because transition is crossed) - BTRAIN is enabled at the beginning the ramp and
switch off at the end of the ramp (Bup and Bdown
are 0.1 Gauss)
47PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(2/13)
- 200 MHz TWC
- Feedforward (not used on FT beam) 1-turn delay
feedback together (send correction to the cavity
through a transmitter) ? To combat the beam
loading - Long. feedback (called also damper) ? Used since
the injection, and then the gain is adjusted
(high gain around the injections for injection
damping), to combat coupled-bunch instabilities - Injection into 2 MV bucket (mismatched)
- 800 MHz TWC
- Bunch shortening mode
Matched voltage is lt 1 MV
48PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(3/13)
- Timings
- At - 425 ms RF ON (TWC200)
- Phase loop ON (fprog) synchro loop ON
- 4 injections
- Before TWC 800 ON in bunch shortening mode after
the 4th inj. Now it is ON already from the
beginning due to the MKE kickers - Max Bdot 0.35 T/s
- At 270 GeV/c, longitudinal blow-up done with
phase modulation on 200 MHz (to have the shortest
bunch length on the flat-top, otherwise one has
coupled-bunch instabilities). It is active for
100-200 ms, with an efficient time of 10-20 ms - ?L 0.45 eVs at the end of the flat-bottom and
it is 0.6-0.7 eVs on the flat-top - Synchro with LHC
- Adiabatic voltage to send the shortest bunch
lengths
49PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(4/13)
? Example of bunch length with nominal (4?72
bunches) beam but low intensity ( 2.5E13 p)
V200MHz 104 V
Full (4?) bunch length ns/100
V800MHz 103 V
Beam momentum GeV/c
Must enter in the LHC 2.5 ns bucket
50PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(5/13)
- Injection frequency
- - Value 200.264550 MHz ? injection B field
1170.3 Gauss) - - Setting SPS Control ? SPS Equipment Control ?
SPS RF - ? SPS RF Control ? RF Synchro ? Injection B field
- ? select appropriate MMI target (MD1, or LHC25ns,
...) - ? Write 1170.3 Gauss (corresponds to 200.264550
MHz)
- Injection pulses ? Sets the delay on top of the
prepulse sent by - the PS machine, in bucket number
- - Value 5500
- - Setting SPS Control ? SPS Equipment Control ?
SPS RF ? SPS RF Control ? RF Synchro ? Injection
pulses - ? select appropriate MMI target (MD1, or
LHC25ns, ...) - ? Write 5500
51PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(6/13)
- Injection bucket selector ? Defines where the
beam is placed - in the SPS (bucket number for 1st bunch in 1st
batch) - - Value 3881 for first batch, 3881 400 ?
(n-1) for the nth batch - - Note this value could change from one day to
the - other in first turn, check that the first batch
is placed - in the right place
- - Display
- - SPS Control ? SPS Beam Measurements ? Mountain
Range - - The bunch should be in the centre
52PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(7/13)
- Measurement
- SPS Control ? SPS Beam Measurements
- ? LHC First Bunch Bucket Error
- This application measures the error with respect
- to the injection bucket selector. It should be 0.
- If not correct the injection bucket selector by
the - appropriate amount (indicated by the application
modulo 4620).
53PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(8/13)
- Setting
- SPS Control ? SPS Equipment Control
- ? SPS RF ? SPS RF Control ? RF Synchro ? Inj.
bucket selector - ? select appropriate MMI target (MD1, or LHC25ns,
...) - ? Write ...
54PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(9/13)
- Injection phase ? When there is a change of
injection bucket, - there might be a small injection phase error.
- The bunches will oscillate in the first few
turns. - The phase loop will try to correct this effect
quickly. - Value 99 (Note This value can change from one
day to another ) - Display
- SPS Control ? SPS Beam Measurements ? Mountain
Range - Some oscillations would be visible in the
mountain range - display
- Trouble shooting the bunch should be well
centered at 11 ns. - If it is off by 2.5 ns (half a bucket) the
"injection phase" is - wrong by 180 degrees.
- If it is off by 5 ns (one bucket) it is the
"injection bucket - selector" which is wrong by one unit
55PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(10/13)
- OASIS
- ? Connect global ? SPS ? RF LHC Loops
- If there is an offset, one should increase the
injection - phase accordingly (about 1 degree per 10 mV
offset) - Setting
- SPS Control ? SPS Equipment Control ? SPS RF
- ? SPS RF Control ? RF Synchro ? Injection phase
- ? select appropriate MMI target (MD1, or LHC25ns,
...) - ? Use only the 1st injection
- ? Write ...
56PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(11/13)
57PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(12/13)
- Phase sampling
- Value 3480
- Setting
- TWC 200 MHz Low level
- ? Phase Loop ? PL Cycle Select
- ? select appropriate MMI target (MD1, or
LHC25ns, ...) - ? Phase sampling
- ? Parameter set number 2
- BU Bunch 3480
58PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(13/13)
- B start ?This is the timing at which RF switches
to the frequency - program (following changes in magnetic field)
- MTG event "SX.ST-RAMP-CTM" enabled and set to
10860 ms - SPSOP CCM ? Working Set ? RF-SPEC ? SPSRF6
- "pLHC frequency program b pulses on"
- Settings
- Timing defined with respect to event
SX.S-RAMP-CT - (start of the ramp)
- Delay is 0
- "pLHC frequency program b pulses off"
- Settings
- Timing defined with respect to event
SX.S-SFLATTOP-CT - (end of flat top)
- Delay is 30
59MEASURING BEAM PARAMETERS (1/12)
- Transverse emittance
- In the PS
- Fast Wire Scanners (2 H with Dx ? 0 2 V)
- In the TT2-TT10 transfer line
- SEM wires SEM grids ? Without PS bunch rotation
(otherwise meas. perturbed by ecloud!)
60MEASURING BEAM PARAMETERS (2/12)
61MEASURING BEAM PARAMETERS (3/12)
- OTR (Optical Transition Radiation)
- 4 in TT10 1 in TT2
- Measurements can be performed without SPS
injection - At least 3 OTRs required for a measurement
62MEASURING BEAM PARAMETERS (4/12)
- In the SPS (SPS Control / SPS beam measurement /
SPS wire scanner) - Rotational Wire Scanner (6 m/s) 2 pairs in LSS4
2 pairs in LSS5 - Linear Wire Scanner (1 m/s) 2 pairs in LSS5
- ? DO NOT USE the Linear Wire Scanners as these
will burn with this high intensity beam (should
be used for the LHC pilot bunch)
Should be preferred
Should be preferred
LINEAR
63MEASURING BEAM PARAMETERS (5/12)
64MEASURING BEAM PARAMETERS (6/12)
65MEASURING BEAM PARAMETERS (7/12)
- IPM H (BIPMH51634) and V (BIPMV51734)
MD CYCLE
Gaussian of constant normalized emittance in blue
?x 2.68 mm
? Fanny is currently writing a program to have
the IPM measurement operational in 2008
?x 1.51 mm
66MEASURING BEAM PARAMETERS (8/12)
- Longitudinal emittance
- In the PS
- Tomoscope (should be preferred) or BSM
- In the SPS
- By measuring the bunch length as a function of
the RF voltage ? An application will be available
to compute this (Fanny)
- Intensity
- In the PS
- BCT gives the total intensity (of the 72 bunches)
- BSM gives the relative bunch by bunch intensity
- Transfer line ? (SPS Control / SPS beam
measurement / SPS FBCT) - 1 FBCT at the beginning of TT2 1 FBCT at the
end of TT10 - Absolute intensity, bunch by bunch
- Possibility to superimpose the measurements
obtained with 2 different FBCTs
67MEASURING BEAM PARAMETERS (9/12)
- In the SPS
- FBCT (Fast BCT) ? 1 (SPS Control ? SPS beam
measurement ? SPS FBCT) - Absolute intensity, bunch by bunch
- Possibility to superimpose the measurements
obtained with two different FBCTs - Normal BCTs ? 3
- 2 for high intensity (DBCTHIGH1 and DBCTHIGH3).
From 1010 p up to a few 1013 p) - 1 for low intensity (DBCTLOW4). From 108 p up to
a few 1011 p) - There is a difference of about 10 between the
FBCT and the normal BCTs. The normal BCT is used
for calibrating the FBCT - Use one of the 2 high intensity BCTs (DBCTHIGH1
or DBCTHIGH3)
68? EXAMPLE OF EVOLUTION OF THE BCT FAST BCT
(10/12)
NOMINAL 4 ? 72 bunches
ALTERNATIVE 5 ? 48 bunches
BCT 5?1010 p
V200MHz 104 V
V800MHz 103 V
Beam momentum GeV/c
69MEASURING BEAM PARAMETERS (11/12)
- Bunch length
- In the PS
- BSM
- In the SPS
- Application in BA3 Fanny
- Momentum spread ? Deduced from measurements of
bunch length and longitudinal emittance (deduced
from bunch length and RF voltage)
70MEASURING BEAM PARAMETERS (12/12)
- Transverse tunes and chromaticties
- In the PS
- Qmeter Bernards application
- In the SPS
- Jorg released in 2007 a totally re-factored
MultiQ application for the SPS based on the BBQ
system (The old BOSC Qmeter system is no longer
supported) - Jorg also implemented in 2007 an automatic
measurement of the chromaticity (linear and/or
nonlinear) in the AutoQ ? It is AutoQprime
71EXTRACTION (1/2)
- Once at 450 GeV/c the following actions take
place during the flat-top, which is approximately
1 second long - Ramping of the extraction elements (magnetic
septa and closed orbit bumpers) ready for
extraction - Fine re-phasing of the SPS with respect to the
LHC in order to inject into the LHC at the
required azimuthal position - Compression of the bunch length by an RF voltage
increase - Cleaning of the tails of the beam distribution
down to 3-3.5s by means of fast scrapers - The status and settings of various elements of
the LHC, the transfer lines, the SPS and the
extraction channel must be surveyed and checked
before extraction is permitted
72EXTRACTION (2/2)
- MKE extraction kickers
- LSS4
- LSS6
73CHANGES WHEN SWITCHING FROM FT TO
(High-intensity) LHC
- During (the scrubbing run and) the LONG MDs with
LHC beam the ZS are RETRACTED / HV to 0 kV / ION
TRAPS ON (inform the ZS expert). The cooling
circuit for the septa magnets (circuits 214, 414
and 614) should be switched OFF (by TI). Block
the fast vacuum valves OUT in the injection and
extraction areas (LSS1,LSS2,LSS6) - Equipment modifications for the MD
- Changed accelerator mode for FT no extraction
- NORTH extraction off
- MST/MSE girders retracted
- Servo off
- Switched off TT20 AUXPS
74REMAINING ISSUES IN 2008
- TIDVG outgassing
- Problem (only) when the beam is repeatedly
dumped at high energy (450 GeV/c) with the
nominal LHC beam ? We then have after few minutes
an interlock on the downstream MKP (to prevent it
from sparking) ? It is a problem in fact of
vacuum and not dump! - This is issue is currently under study
- MKDV1 outgassing
- The nominal LHC beam cannot be extracted to the
LHC if we dont find a solution! - During the 2007 MD we removed the last voltage
step (which reduces the bunch length at the very
end before going to the LHC) to allow the beam to
go to 450 GeV/c otherwise it would not have been
possible - L. Ducimetiere informed us that nothing was done
on this during the 2007-2008 shutdown
75(LEAD) IONS (1/2)
76(LEAD) IONS (2/2)
In the SPS in 2007
2007 MDs ? 90 of the design intensity (4?9E7?82)
with transverse emittances (rms, norm) 25
smaller than design (0.9 ?m instead of 1.2 ?m in
both planes)
? No ions in the SPS in 2008!