Title: LARP Accelerator Systems Overview: How are we doing?
1LARP Accelerator Systems OverviewHow are we
doing?
US LHC Accelerator Research Program
bnl - fnal- lbnl - slac
2Content
- Whats new after October05 Collaboration Meeting
- LARP Org Chart changes, communication, DocDB
- FY06 Budget spendings to date
- RC review Lumi Review
- DoE Review Nov05 ? LARPAC May06 ? DoE Review
Jun06 - RD Progress
- Instrumentation
- Commissioning
- Collimation
- Accelerator Physics
- New Proposals
3Accelerator Systems Org Chart
Changes Wolfram to lead AP
- Be discussed at this meeting
- Finish some L3 tasks
- Introduce new L3 tasks
- any org structure for new initiatives?
4Communication/Coordination
- Communication within LARP
- VideoConf of all AS L2sSteve once/mos
- One-on-one meetings (site visits, reviews, etc)
once/qrtr - Collaboration meetings twice/year
- Communication with CERN
- First long-termers (P.Limon et al)
- Visits (HC, BC, Instr, etc) gt1/mos
- Workshops (e.g. TAN) and reviews (e.g. RC)
once/qrtr - US-CERN meetings once/yr
- LARP Doc DB is functioning
- 180 docs uploaded from Oct05-Apr06
5FY06 Accelerator Systems Budget
Pete got extra 150k to cover past investments
BNL BC funds redistributed to FNAL and LBL ? -60k
RC hardware start delayed ? -350k
Nick got extra 50k for PhII irradition
extra 30k To build BB-Wires
6Accel.Syst. Spendings
1.2M/3.6M33 thru ½ year Mar.31, 2006 (compare
with 45 MAG)
7That tops the list of my worries
- Make sure that we achieve all milestones
- And spend approx as planned
- Reviews
- Be prepared and pass numerous reviews (small and
big one) - Next year planning/budget
- Have clear understanding of what will we do next
year - New initiatives
- Should always have a healthy pressure of new
proposals - Now anticipate some freed after diagnostics
development and fabrication finished in 2007 - This collaboration meeting is to address all
that - L2s will report Friday
8Speaking of Reviews Nov05 DoE
- The review committee was very pleased with the
presentations on beam instrumentation and
accelerator physics. In addition, they found the
idea of participation in the development of a
remote control room a very interesting
possibility for enhancing interactions with CERN
from afar via the Fermilab project LHC_at_FNAL. - Plans for commissioning of LHC hardware are
already being implemented, with the first U.S.
staff member (Peter Limon) already stationed at
CERN. It was reported by management that U.S.
laboratories will provide staffing for this
effort, and, in fact, FNAL has committed seven
persons to this task. LARP and CERN will cover
costs of travel and additional living expenses in
the Geneva area. - Finally, the committee again emphasized its
displeasure with the lack of formality in
dealings of LARP, and strongly recommended a more
effective bookkeeping system for managing
expenses and progress on all active tasks, and a
person who would be responsible for implementing
such a system.
9Internal Reviews by External Reviewers
- Rotating Collimator-1 CDR Review
- December 2005, chaired by W.Turner
- OK, advised to design jaw support before cut
iron - Luminsoity Monitor Final Design Review
- April 2006, chaired by T.OShea
- All positive, technical risks low to medium
10 TCFB on RHIC ramp
P.Cameron
11Luminosity Monitor - I
- The only real-time bunch-by-bunch luminosity
measurement in the LHC - 25 ns bunch spacing, 1 resolution
- RD phase has been completed
- Demonstrated 40 MHz performance using ALS X-ray
beamline - Beam test planned for RHIC run VI
- System intragation planning at CERN
- TAN instrumentation workshop on March 10
- Final Design Review at LBL
- Monday April 24
12Luminosity Monitor - II
- Technical Challenges
- Extremely high radiation levels
- up to 250 Grad
- Signal processing to avoid pileup
- 25 ns bunch spacing
- Status
- Completed RD and FDR
- Project Milestones
- Final Design Review (Apr 06)
- System test at RHIC (Summer 06)
- Four systems complete (Winter 06-07)
- Installation and integration support (07)
DAQ TAN
FE electronics
13LHC 4.8 GHz Schottky Design
R.Pasquinelli A.Jansson
- Remarkable Progress
- Final drawings ready for CERN inspection
- Data acquisition issues discussed at Apr25 mtg
at LBL - Next revision of EDMS is needed
- Final Design Review 06/19/06 at CERN
14LARP Hardware Commissioning Tasks
Installation Oversight
- Since DOE Review Last Fall
- First USLHC String
(Q1-Q3/Feedbox/D1) transported to tunnel - LARP Oversight and technology transfer for USLHC
interconnects - Transportation and Installation of Second IR
quad/DFBX/D1 on going. - Limited LARP oversight planned for all US
deliverable installations
Photos from Jan 2006 IR 8L installation
15LARP Hardware Commissioning Tasks
- Commissioning of US Deliverables and General HC
- LARP commissioners receive Project Associate
status, join a CERN group (AT/ACR or AT/MEL) for
nominally one year and contribute to the groups
general HC responsibilities as well as US
deliverables. - Short term HC support from US experts as needed
- One commissioner stationed at CERN now. 3-4
additional to follow in the fall of 2006. - Peak participation coincides with anticipated
peak commissioning period FY07.
16Beam Commissioning Status
- Several US visitors to CERN in January/February
06 - Nearly continuous presence for 6 weeks
- Chamonix workshop
- Beam Commissioning logistics
- Software
- CCC opening
- get to know LHC beam principals
- Informal review of LHC Beam Commissioning
structure completed - (results presented at this meeting)
- Beam Commissioning Expression of Interest
- (to be introduced at this meeting)
- Refining areas of involvement, beginning to
assign names/share with CERN counterparts - Gearing up for LARP presence during SPS running,
more so for Sector test - More detail in Breakout session
17LHC_at_FNAL Status
- Committees work complete
- Endorsement received from
- Fermilab Directorate
- Affected Fermilab Divisions/Sections (AD, PPD,
CD, FESS) - LARP management
- CMS management
- Construction plans in development
- Funds set aside/awaiting DOE approval
- Center planned to be open in September 2006
- More detail in Breakout session
18Status of Phase II Rotating Collimator Project at
10-06-2005 Pheasant Run LARP Mtg.
- SLAC and CERN agree on an initial set of
specifications for the first mechanical prototype
RC1 - Put a new vacuum tank with cylinder jaws that
fits LHC spatial constraints on a CERN Phase I
base and use CERN Phase I scheme for jaw
alignment and cooling input - Provide 12kW cooling to each 136mm x 95cm jaw
through flexible tubing - Relax 25um flatness tolerance but provide
flexible jaw support and a central stop mechanism
to ensure thermal bowing is AWAY from beam - 400 um sagitta for 1 hr beam lifetime engineering
steady state - 1200 um sagitta for 12min beam lifetime 10 second
transient
19Progress since 10-06-2005
- RC1 Prototype Conceptual Design Report
- reviewed and accepted by CERN and suggestions
incorporated - independent review 12/15/05
- Lou Bertolini-LLNL, Alex Makarov-FNAL, Bill
Turner (LBL) - Major Findings Fine, but .
- Do not cut metal until jaw support and stop
scheme developed - In progress
- Check thin-Cu over Stainless for performance v No
improvement - Increase engineering effort
- Full time engineer (Steve Lundgren) and designer
hired 3 April - Current Activities
- Braze tests of cooling coils beginning
- Prep for full cooling deformation tests
- Acquisition of Phase I support mover assemblies
- Redrawing of CERN parts for US fabrication
20FY06 Goals of Phase II Rotating Collimator
Project and Beyond
- Work Plan outlined 10/6/2005
- Single jaw thermal test one jaw with internal
helical cooling channels to be thermally loaded
for testing the cooling effectiveness and
measuring thermal deformations. - Full RC1 prototype a working prototype for bench
top testing of the jaw positioning mechanism,
supported to simulate operation in all necessary
orientations, but not intended for mounting on
actual beamline supports with actual beamline,
cooling, control and instrumentation connections. - Deliverables listed 10/6/2005
- Final version of RC1 CDR Awaiting
support/stopper design - External review of RC1 CDR v
- Performance report on RC1
- Progress delayed 6 months due to reviews
manpower issues - New Plan Slip schedule 6 months
- Single jaw tests, support/stopper design
write-up by EOFY06 - RC1 performance report by mid FY07
- 400k returned to LARP management in FY06
adjustment - Expect slippage of Jan 2008 beam-testable RC2
delivery consistent with CERNs latest schedule
21PHASE-I Irradiation and Analysis of 2D
Carbon-Carbon at BNLGOALS Determine resilience
of 2D CC against irradiation damage and assess
how the critical property of thermal expansion
changes with irradiation
Material Irradiation Studies
assembly
irradiation
Post-irradiation Analysis
RESULT PHASE-I 2D Carbon-Carbon self anneals
irradiation ramage through thermal cycling in
both strong and weak directions. Therefore, it is
expected to meet the 25 micron condition set as
goal
Phase-II LHC Collimator Material Irradiation
Planned for May 2006
- Primary Materials Annealed Copper and Glidcop
(85 Cu 15 Al) - Other Potential Candidates Super Invar, Gum
Metal, 3D Carbon-Carbon
22E-cloud since last Mtg
- Completed updated simulations of ecloud power
deposition in LHC dipoles - M. Furman and V. Chaplin, PRST-AB 9, 034403
(March 20, 2006) - Tedious exploration of parameter space with 2D
code POSINST (see below) - Peak SEY dmax now constrained to be lt1.2 for
nominal intensity bunch spacing - Code improvements
- 3D self-consistent code (WARP/POSINST)
- Jean-Luc Vay (LBNL) now 20 LARP funded (starting
FY06) - Initial qualitative results for one bunch in one
FODO cell (LARP mtg, Apr. 05) - New results for a train of 5 bunches with more
detailed model (see below) - Code improvements
- RHIC studies
- Feb. 2006 two CERN e detectors installed (some
not LARP funded, but important) - Common pipe region in IP10, warm section
- Polarized proton beams for this run
- Ping He doing RHIC simulations calibration
barely started
23Sample simulation ecloud at LHC dipoles(Furman
and Chaplin, PRST-AB 9, 034403)
- ecloud power deposition
- POSINST code
- LHC arc dipole magnet
- key parameters Nb, tb, dmax
- current result dmaxmust be lt1.2-1.3 (achievable
but not easy)
cooling capacity available for EC power
deposition
24Sample 3D self-consistent simulations
(WARP/POSINST)(courtesy J.-L. Vay)
- LHC FODO cell
- can now follow batch of bunches with photo- e
and secondary e - snapshot from run with 5 bunches
- Benchmark code against HCX experiment (LBNL)
- expt. and sim. agree quantitatively on
characteristics of e oscillations observed in
magnetic quadrupole flooded with electrons
WARP/POSINST-3D T 4.65?s
WARP/POSINST-3D T 0.3?s
Electrons bunching
experiment simulation
Beam ions hit end plate
Oscillations
25Future Plans
- 3D self-consistent simulations
- Study long-term behavior of beam
- This is a nontrivial exercise that may require
code improvements - Main new concern slow emittance growth
(Benedetto et. al. PRSTAB 8 124402 (2005) et.
seq.) - Also address old concern (ecloud-induced
head-tail instability) - Summer student to come to LBNL for 12 weeks this
summer - Simulate optimal conditioning scenario for LHC
- Understand leftover details from SPS measurements
- Contribute (time permitting) to 3D
self-consistent simulations - RHIC
- Analyze collected data obtained with CERN
detectors - Complete simulations
- Understand ecloud sensitivities and correlate
them to other observables (eg., P rise)
26IR Layouts
Baseline Layout Quads first Too many
parasitics Dipoles first layout Early
separation but .
Doublets
Triplets
27 IR Optics Issues
IR Magnet apertures and fields Energy
Deposition Major issue in all optics, but
dipole designs more challenging. Beam-beam
interactions Demonstration of wire
compensation would favor quads 1st. Chromaticity
and Nonlinear Correctors Corrector
strengths lower with quads 1st but independent
control of 2 beams with dipoles 1st. Luminosity
gain with lower L Larger gain with quads
1st. Flux jumps in IR magnets Chromaticity
jumps small (2 units) with ?b3 1 in both
optics if spurious dispersion in IR is controlled
to 1cm at IP. Nonlinear effects need to be
studied
Pole tip field T Aperture mm
Quads 1st Dipoles 1st triplets Dipoles 1st doublets 10 11 10 101 107 104
28Beam-beam experiments, simulations
- RHIC beam-beam experiments in April 2006
- Motivation Test of wire compensation in
2007 - Determine if a single parasitic at top
energy causes beam losses that need to be
compensated. Similar experiment done last year at
injection energy - found strong effects at
separations 6s. - 2 experiments done so far April 5th, April
12th - Analysis to be presented by W. Fischer
- Beam-beam simulations of 2006 experiments
- Motivation Tests and improvements of
codes, predictions of observations in 2006 and of
wire compensation - Four groups
- FNAL V. Ranjbar, T. Sen SLAC A.
Kabel LBL J. Qiang University of Kansas J.
Shi - Website http//www-ap.fnal.gov/tsen/RHIC
- for information exchange and results
29Beam-beam simulation results
No sextupoles
Kansas
Relative Lifetime
LBL
Emittance growth
FNAL
Losses
SLAC
BBSIM (VR, TS) simulations for lifetime show a
linear dependence on separation
30RHIC long-range beam-beam compensator design
In CY06 construct and install a wire
compensator in RHIC, downstream of Q3 in IR6
31New Initiatives to discuss
- AC dipole
- dB/B measurements
- Crystal collimation
- Super-SyncLite
- e-lenses for Head-on B-B Compensation
- Crab cavities
- 1.5TeV Injector in LHC tunnel LER-LHC
- Optical Stochastic Cooling
32Common questions to answer
- Title/subject
- Leader and participants
- Objectives
- Deliverables
- Time scale/schedule
- Resources needed
- Addl man-power (and type eng, phys, techs)
- Travel
- Labor
- MS and Equipment
33There is very little time left
34so - Work hard and be inventive!
35Slides
36Wire Beam-Beam Compensation Overall Plan
- FY2006
- Design and construct a wire compensator
- Install wire compensator in RHIC in summer 2006,
downstream - of Q3 in IR6
- Perform theoretical studies to test the
compensation and robustness - FY2007
- Study the wire compensation in RHIC with 1 proton
bunch in each beam and nominal conditions at flat
top and 1 parasitic interaction. - Beam studies to test tolerances on beam-wire
separation compared to beam-beam separation,
wire current accuracy and - current ripple
- FY2008
- Decide on scope of work for the LHC wire
compensation
37Detail of flex cooling supply tube
Stub-shaft (bearing not shown)
Contiguous with helical tube inside jaw. Formed
after assembly-brazing of jaw and installation of
bearing on stub-shaft Exits through support shaft
per CERN design Material CuNi10Fe1, 10mm O.D.,
8mm I.D.
Relaxed (as shown) coils 4
Relaxed (as shown) O.D. 111mm (4.4in)
full 360 rotation coils 5
full 360 rotation O.D. 91mm (3.6in)
full 360 rotation torque 9.1N-m (81in-lb)
Support shaft
381.3 LHC Collimation RD
- L2 Leader Tom Markiewicz (SLAC)
- FY06 budget 850 k
- Goals
- The LHC cleaning system must have exceptional
efficiency to meet its design parameters,
significantly beyond the state-of-the-art that is
achieved in existing colliders. It is crucial for
the success of the LHC that different paths are
explored in order to optimize the design,
hardware and operational procedures for the LHC
collimation system. In view of the exceptional
difficulty for the LHC it is essential to pursue
parallel RD studies in- and outside of CERN. The
phased approach for the LHC collimation system
will allow to test various proposals and to
implement the best solutions in an already
defined upgrade path to nominal performance. The
LHC Collimator RD will complement the work at
CERN and will be performed in close - L3 tasks
- Cleaning Efficiency Studies
- Rotating Collimators RD
- Tertiary Collimators Studies
- Material Irradiation Studies
391.3.1 Cleaning Efficiency Studies
- L3 Leader Angelika Drees (BNL)
- FY06 budget 50 k
- Goals
- The ultimate goal of this sub program is to bench
mark code(s), in particular SIXTRACKwColl, in a
variety of aspects with RHIC beams. - We plan to install and implement at BNL
accelerator tracking code identical with the one
used at CERN (K2, SIXTRACK with Collimators, i.e.
SIXTRACKwColl) and perform simulations of
collimation efficiencies and loss maps which will
then be compared to simulation results from
earlier studies done at RHIC with other codes
(Teapot, K2, ACCSIM) and with data. Various data
sets at two energies are available. - During the RHIC proton run collimator setup
procedures should be implemented into the RHIC
control system and tested with beam under real
operating conditions.
40Cleaning Efficiency Studies Overall Plan
- FY2006
- debug the code
- compare with other simulation and data, test
setup procedures, - finish reports
411.3.2 Rotating Collimators
- L3 Leader Tom Markiewicz (SLAC)
- FY06 budget 720 k
- Goals
- The ultimate goal is a successful design for low
impedance, high efficiency LHC secondary
collimators. The design will be validated with a
sufficient but small (1-3) number of prototypes
and beam tests. The design specifications and
the prototypes are the primary deliverables. The
time scale is set by the desirability of testing
the prototypes with LHC beam in 2008/09. Then,
CERN will decide whether or not to proceed with
the rotating collimator design. If a decision is
made to proceed, this sub-project will provide an
engineering drawing package to CERN and will
support the effort to commission the collimators
once they are manufactured and installed by CERN.
42June 15-17 CERN/SLAC Collaboration Meeting
- Attendees
- CERN Ralph Assmann (Project Leader, Tracking),
Allesandro Bertarelli (Mechanical Eng.), Markus
Brugger (Radiation Issues), Mario Santana (FLUKA)
- SLAC Tom Markiewicz, Eric Doyle (ME), Lew Keller
(FLUKA), Yunhai Cai (Tracking), Tor Raubenheimer - Radiation Physics Group Alberto Fasso, Heinz
Vincke - Results
- Agreement on basic design of RC1 (1st rotatable
prototype) - Transfer of many of CERN mechanical CAD files
- Lists of
- Further studies required
- Outstanding Engineering Issues requiring more
design work - Project Milestone List Action Items List
- Test Installation of New FLUKA
43Conceptual Design of RC1 (1 of 2)
- Mechanics must fit within CERN Phase I C-C
envelope - 224mm center-to-center with 88mm OD beampipes
- 1480mm longitudinal flange-to-flange
- 25mm adjustment/jaw (22.5mm relative to beam
w/5mm allowed beam center motion - and use Phase I alignment and adjustment scheme
- Two 75cm Cu cylindrical jaws with 10cm tapered
ends, 95cm overall length with axes connected to
vertical mover shafts - 136mm OD with 9mm taper
- Each jaw end independently moved in 10um steps
- Vacuum vessel sized to provide 8mm clearance to
adjacent beam and allow gross/fine 0, 45, 90
positions - Relaxed mechanical deformation specifications
- lt25 um INTO beam guaranteed by adjustable
mechanical stop(s) - Ride on groove deep enough to not be damaged in
accident case - Adjustable between 5 and 15 sigma (2-6mm)
centered on beam - lt325 um (750um) AWAY FROM beam _at_ 0.8E1p/s loss
(4E11p/s) - Flexible support on adjustment
44Proposed layout
136mm diameter x 950mm long jaws, vacuum
tank, jaw support mechanism and support base
derived from CERN Phase I
45Adjustable gap-defining stop
- Stop prevents gap closing as jaw bows inward due
to heat - Jaw ends spring-loaded to the table assemby
move outward in response to bowing - May use two stops to control tilt
- Slot deep enough to avoid damage in accident
- Stop far enough from beam to never be damaged
is out of way at injection
46RF Contact Overview
47LHC Phase I 2D carbon-carbon Irradiation Specimen
at BNL BLIP Facility
117 MeV or 200 MeV BNL LiNAC Protons (depending
on the isotope production requirements downstream)
Preliminary Assessment 2D CC specimens normal to
the planes of reinforcing fibers and close to the
center of the beam (receiving high dose)
experienced degradation. Less degradation was
seen in the specimens along the reinforcement.
? NOTE Total dose received MUCH HIGHER than
what LHC collimator jaws will see. Status Phase
I Carbon-Carbon irradiation completed Sample
activation measurements completed Thermal
Expansion of specimens started PLANNING of FY06
Post-Irradiation and Follow-up Irradiation Studies
48Phase-II LHC Collimator Material Irradiation
Planned for May 2006
- Primary Materials
- Annealed Copper and Glidcop (85 Cu 15 Al)
- Other Potential Candidates Super Invar, Gum
Metal, - Also
- 2D Carbon-Carbon and 3D Carbon-Carbon
Test for physical properties (thermal
conductivity, thermal expansion) And Stress-Strain
(mechanical properties)
49POST IRRADIATION ANALYSIS REVEALED THAT PHASE-I
2D Carbon-Carbon Self Anneals Irradiation Damage
through thermal cycling in both strong and weak
directions. Therefore, it is expected to meet the
25 micron condition set as goal
Annealing along strong (fiber plane) direction
Annealing along weak direction
Shown is annealing under different levels of
irradiation damage
50PHASE-I Irradiation and Analysis of 2D
Carbon-Carbon at BNLGOALS Determine resilience
of 2D CC against irradiation damage and assess
how the critical property of thermal expansion
changes with irradiation
Beam exposure and irradiation damage assessment
assembly
Post-irradiation Analysis
irradiation
At irradiation levels several orders of
magnitude than what the LHC collimator jaws will
see the 2D CC suffers structurally from
irradiation exposure
51 Physics Long Range _at_ RHIC
SPS t d5 measured 11/09/04 Tevatron
t d3 measured in HEP stores, TEL RHIC
t d4 or d2 measured 04/28/05, scan 4
52AC dipole
- Recent results from the Tevatron
- Collaboration formed including Fermilab, BNL and
CERN. - Formal proposal for LHC at this meeting
First AC dipole data in the Tevatron
53SyncLite Fiber ghost bunches measurement
(DeSantis, Byrd, Zolotorev)
5 105 protons emit 30 photons/turn in a 10
bandwidth. The electro-optic modulator/fast
pulser combination can map the entire LHC ring,
with the required resolution, every 500
orbits. In the allowed integration time, every
single 50 ps-long region is sampled 200 times. A
70 QE photodiode would accumulate gt4000
counts. We can estimate a total of -6/8 dB from
the coupling into the optical fiber and the
various insertion losses. Main noise sources are
the modulator extinction ratio ( 3 10-3) and the
photodiode dark current ( nA)
54 New Initiatives dB/B Fluctuations
Tevatron Stand-Alone Dipole measurements (Proc.
PAC01)
- LHC screen light and feels 20 K He flow
turbulence - B-flux is constant at 3kHz
- dB/B dR/R ? need
- dR lt 1A to blow horizontal emittance
- Can be measured at CERN MMF and in Tev
551.5 TeV SuperFerric Injector in LHC tunnel
J.Johnstone T.Sen, H.Piekarz
561.2 LHC Commissioning
- L2 Leader Michael Syphers (FNAL)
- FY06 budget 1,140 k
- Goals
- There is an overall benefit to the U.S.
high-energy physics program if the LHC turns on
rapidly and successfully. Our experimental
physics groups have invested heavily in the LHC
project, and the science produced there thus
represents a return on the U.S. investment. A
healthy and strong HEP activity at LHC will
surely be necessary to secure future
accelerator-based HEP projects in the U.S. The
information gained during the commissioning will
be available in a timely manner and will have
maximum positive effect on U.S. plans for LHC - L3 tasks
- Beam Commissioning
- Hardware Commissioning
- Toohig Fellowship
- New Initiatives
57Schottky Monitors Overall Plan
- FY2006
- S/N study of low intensity bunches in Tevatron
- Design pick-up structure, study PLL DAB board for
DAQ - complete an integration document, signed off by
both parties, and entered into CERN EDMS - Design and build front-end electronics Q1
- Joint LARP and CERN review of the proposed design
- FY2007
- Adapt Fermilab analysis software
- Hardware commissioning at CERN without beam
- FY2008
- Hardware commissioning at CERN with beam
- FY2009
- Beam studies of chromaticity measurements, ramp
effects