Title:


1

Production Management Software for the Coal
Industry
2
Development
  • Gate Road Development involves the construction
    of roadways, to a set standard, from point A to B
  • This construction project can take up to 9 months
  • There are different levels of project planning,
    from monthly through to shift planning
  • There are various planning tools used within the
    industry for gateroad panels. Eg. MS Project
  • The effectiveness of these tools relies on the
    ability of the department to maintain up to date
    plans
  • This is easier at a monthly level and becomes
    increasingly more difficulty at the weekly and
    daily plan levels

3
Development
  • ULTIMINE utilises the mines Development Panel
    operating guidelines and process map as a
    framework for the construction of gateroad panels
  • ULTIMINE interfaces to the mines document control
    system and provides an auto print functionality
    for procedures and JSA etc
  • Ultimine interfaces with the mines work order
    system and delay recording systems
  • Collectively this functionality unites the mines
    current systems into one easy to use planning tool

4
Development
  • If you dont have a clear understanding of your
    Development process than ULTIMINE is not the
    answer
  • If you dont have discipline in maintaining the
    process, on all shifts, than ULTIMINE wont fix it
  • If the management at the highest level are not
    committed to supporting the Development process
    with the required resources ULTIMINE wont
    overcome it
  • If management dont insist that all shifts use
    the tool to create accurate shift plans,
    including valid productivity targets, then the
    effective use of ULTIMINE will be compromised

5
Menu
  • Development planning
  • Why United and XCN said YES to ULTIMINE
  • The new direction

6
Development Long term planning
Operational
Budget
Corporate
Long term plan
Statutory
Equipment
Longwall continuity
7
Development Weekly planning
Operation
Process
Long term plan
Weekly plan
Work Orders
Resources
Compliance
Leave
Assumptions
8
Development 24 hour planning
Unplanned delays
Previous 24 hours
Weekly plan
Work Orders
Unplanned work
24 hour plan
Reporting
Quality of information
Unplanned Leave
People
Sequence
9
Influences on the Shift planning
Unplanned delays
Weekly plan
24 hour plan
Work Orders
Shift Handover
Shift planning
Reporting
Quality of information
Unplanned Leave
People
Process tasks
10
The Development Shift plan provides
Work to do
Face positions
Safety
The shift plan
Resources
Lots of talk
Equipment
11
Why United and XCN said yes to ULTIMINE
Accurate shift expectations
Formalises communication
ULTIMINE
Monitors process compliance
One Development plan
Measures accountability
Easy to use
12
The new direction for managing the Development
plans
Task builder Maingate Admin Coordinator Weekly/
24 hr plan Shift planner Handover Live screen
Documents Shift plan doc