PCI 6th Edition - PowerPoint PPT Presentation

1 / 104
About This Presentation
Title:

PCI 6th Edition

Description:

PCI 6th Edition Headed Concrete Anchors (HCA) Presentation Outine Research Background Steel Capacity Concrete Tension Capacity Tension Example Concrete Shear Capacity ... – PowerPoint PPT presentation

Number of Views:215
Avg rating:3.0/5.0
Slides: 105
Provided by: JasonL159
Category:

less

Transcript and Presenter's Notes

Title: PCI 6th Edition


1
PCI 6th Edition
  • Headed Concrete Anchors (HCA)

2
Presentation Outine
  • Research Background
  • Steel Capacity
  • Concrete Tension Capacity
  • Tension Example
  • Concrete Shear Capacity
  • Shear Example
  • Interaction Example

3
Background for Headed Concrete Anchor Design
  • Anchorage to concrete and the design of welded
    headed studs has undergone a significant
    transformation since the Fifth Edition of the
    Handbook.
  • Concrete Capacity Design (CCD) approach has
    been incorporated into ACI 318-02 Appendix D

4
Headed Concrete Anchor Design History
  • The shear capacity equations are based on PCI
    sponsored research
  • The Tension capacity equations are based on the
    ACI Appendix D equations only modified for
    cracking and common PCI variable names

5
Background forHeaded Concrete Anchor Design
  • PCI sponsored an extensive research project,
    conducted by Wiss, Janney, Elstner Associates,
    Inc., (WJE), to study design criteria of headed
    stud groups loaded in shear and the combined
    effects of shear and tension
  • Section D.4.2 of ACI 318-02 specifically permits
    alternate procedures, providing the test results
    met a 5 fractile criteria

6
Supplemental Reinforcement
  • Appendix D, Commentary
  • supplementary reinforcement in the direction
    of load, confining reinforcement, or both, can
    greatly enhance the strength and ductility of the
    anchor connection.
  • Reinforcement oriented in the direction of load
    and proportioned to resist the total load within
    the breakout prism, and fully anchored on both
    side of the breakout planes, may be provided
    instead of calculating breakout capacity.

7
HCA Design Principles
  • Performance based on the location of the stud
    relative to the member edges
  • Shear design capacity can be increased with
    confinement reinforcement
  • In tension, ductility can be provided by
    reinforcement that crosses the potential failure
    surfaces

8
HCA Design Principles
  • Designed to resist
  • Tension
  • Shear
  • Interaction of the two
  • The design equations are applicable to studs
    which are welded to steel plates or other
    structural members and embedded in unconfined
    concrete

9
HCA Design Principles
  • Where feasible, connection failure should be
    defined as yielding of the stud material
  • The groups strength is taken as the smaller of
    either the concrete or steel capacity
  • The minimum plate thickness to which studs are
    attached should be ½ the diameter of the stud
  • Thicker plates may be required for bending
    resistance or to ensure a more uniform load
    distribution to the attached studs

10
Stainless Steel Studs
  • Can be welded to either stainless steel or mild
    carbon steel
  • Fully annealed stainless steel studs are
    recommended when welding stainless steel studs to
    a mild carbon steel base metal
  • Annealed stud use has been shown to be imperative
    for stainless steel studs welded to carbon steel
    plates subject to repetitive or cyclic loads

11
Stud Dimensions
  • Table 6.5.1.2
  • Page 6-12

12
Steel Capacity
  • Both Shear and Tension governed by same basic
    equation
  • Strength reduction factor is a function of shear
    or tension
  • The ultimate strength is based on Fut and not Fy

13
Steel Capacity
  • fVs fNs fnAsefut
  • Where
  • f steel strength reduction factor
  • 0.65 (shear)
  • 0.75 (tension)
  • Vs nominal shear strength steel capacity
  • Ns nominal tensile strength steel capacity
  • n number of headed studs in group
  • Ase nominal area of the headed stud shank
  • fut ultimate tensile strength of the stud
    steel

14
Material Properties
  • Adapted from AWS D1.1-02
  • Table 6.5.1.1 page 6-11

15
Concrete Capacity
  • ACI 318-02, Appendix D, Anchoring to Concrete
  • Cover many types of anchors
  • In general results in more conservative designs
    than those shown in previous editions of this
    handbook

16
Cracked Concrete
  • ACI assumes concrete is cracked
  • PCI assumes concrete is cracked
  • All equations contain adjustment factors for
    cracked and un-cracked concrete
  • Typical un-cracked regions of members
  • Flexural compression zone
  • Column or other compression members
  • Typical precast concrete
  • Typical cracked regions of members
  • Flexural tension zones
  • Potential of cracks during handling

17
The 5 fractile
  • ACI 318-02, Section D.4.2 states, in part
  • The nominal strength shall be based on the 5
    percent fractile of the basic individual anchor
    strength
  • Statistical concept that, simply stated,
  • if a design equation is based on tests, 5
    percent of the tests are allowed to fall below
    expected

Capacity
5 Failures
Test strength
18
The 5 fractile
  • This allows us to say with 90 percent confidence
    that 95 percent of the test actual strengths
    exceed the equation thus derived
  • Determination of the coefficient ?, associated
    with the 5 percent fractile (?s)
  • Based on sample population,n number of tests
  • x the sample mean
  • s is the standard deviation of the sample set

19
The 5 fractile
  • Example values of ? based on sample size are
  • n 8 ? 1.645
  • n 40 ? 2.010
  • n 10 ? 2.568

20
Strength Reduction Factor
  • Function of supplied confinement reinforcement
  • f 0.75 with reinforcement
  • f 0.70 with out reinforcement

21
Notation Definitions
  • Edges
  • de1, de2, de3, de4
  • Stud Layout
  • x1, x2,
  • y1, y2,
  • X, Y
  • Critical Dimensions
  • BED, SED

22
Concrete Tension Failure Modes
  • Design tensile strength is the minimum of the
    following modes
  • Breakout
  • fNcb usually the most critical failure mode
  • Pullout
  • fNph function of bearing on the head of the stud
  • Side-Face blowout
  • fNsb studs cannot be closer to an edge than 40
    the effective height of the studs

23
Concrete Tension Strength
  • fNcb Breakout
  • fNph Pullout
  • fNsb Side-Face blowout

fTn Minimum of
24
Concrete Breakout Strength
  • Where
  • Ccrb Cracked concrete factor, 1 uncracked,
    0.8 Cracked
  • AN Projected surface area for a stud or group
  • Yed,N Modification for edge distance
  • Cbs Breakout strength coefficient

25
Effective Embedment Depth
  • hef effective embedment depth
  • For headed studs welded to a plate flush with the
    surface, it is the nominal length less the head
    thickness, plus the plate thickness (if fully
    recessed), deducting the stud burnoff lost during
    the welding process about 1/8 in.

26
Projected Surface Area, An
  • Based on 35o
  • AN - calculated, or empirical equations are
    provided in the PCI handbook
  • Critical edge distance is 1.5hef

27
No Edge Distance Restrictions
  • For a single stud, with de,min gt 1.5hef

28
Side Edge Distance, Single Stud
  • de1 lt 1.5hef

29
Side Edge Distance, Two Studs
  • de1 lt 1.5hef

30
Side and Bottom Edge Distance, Multi Row and
Columns
  • de1 lt 1.5hef
  • de2lt 1.5hef

31
Edge Distance Modification
  • Yed,N modification for edge distance
  • de,min minimum edge distance, top, bottom, and
    sides
  • PCI also provides tables to directly calculate
    fNcb, but Cbs , Ccrb, and Yed,N must still be
    determined for the in situ condition

32
Determine Breakout Strength, fNcb
  • The PCI handbook provides a design guide to
    determine the breakout area

33
Determine Breakout Strength, fNcb
  • First find the edge condition that corresponds to
    the design condition

34
Eccentrically Loaded
  • When the load application cannot be logically
    assumed concentric.
  • Where
  • e'N eccentricity of the tensile force
    relative to the center of the stud group
  • e'N s/2

35
Pullout Strength
  • Nominal pullout strength
  • Where
  • Abrg bearing area of the stud head
  • area of the head area of the shank
  • Ccrp cracking coefficient (pullout)
  • 1.0 uncracked
  • 0.7 cracked

36
Side-Face Blowout Strength
  • For a single headed stud located close to an edge
    (de1 lt 0.4hef)
  • Where
  • Nsb Nominal side-face blowout strength
  • de1 Distance to closest edge
  • Abrg Bearing area of head

37
Side-Face Blowout Strength
  • If the single headed stud is located at a
    perpendicular distance, de2, less then 3de1 from
    an edge, Nsb, is multiplied by
  • Where

38
Side-Face Blowout
  • For multiple headed anchors located close to an
    edge (de1 lt 0.4hef)
  • Where
  • so spacing of the outer anchors along the
    edge in the group
  • Nsb nominal side-face blowout strength for
    a single anchor previously defined

39
Example Stud Group Tension
  • Given
  • A flush-mounted base plate with four headed
    studs embedded in a corner of a 24 in. thick
    foundation slab
  • (4) ¾ in. f headed studs welded to ½ in thick
    plate
  • Nominal stud length 8 in
  • f'c 4000 psi (normal weight concrete)
  • fy 60,000 psi

40
Example Stud Group Tension
  • Problem
  • Determine the design tension strength of the
    stud group

41
Solution Steps
  • Step 1 Determine effective depth
  • Step 2 Check for edge effect
  • Step 3 Check concrete strength of stud group
  • Step 4 Check steel strength of stud group
  • Step 5 Determine tension capacity
  • Step 6 Check confinement steel

42
Step 1 Effective Depth
43
Step 2 Check for Edge Effect
  • Design aid, Case 4
  • X 16 in.
  • Y 8 in.
  • de1 4 in.
  • de3 6 in.
  • de1 and de3 gt 1.5hef 12 in.
  • Edge effects apply
  • de,min 4 in.

44
Step 2 Edge Factor
45
Step 3 Breakout Strength
46
Step 3 Pullout Strength
47
Step 3 Side-Face Blowout Strength
  • de,min 4 in. gt 0.4hef
  • 4 in. gt 0.4(8) 3.2 in.
  • Therefore, it is not critical

48
Step 4 Steel Strength
49
Step 5 Tension Capacity
  • The controlling tension capacity for the stud
    group is Breakout Strength

50
Step 6 Check Confinement Steel
  • Crack plane area 4 in. x 8 in. 32 in.2

51
Step 6 Confinement Steel
  • Use 2 - 6 L-bar around stud group.
  • These bars should extend ld past the breakout
    surface.

52
Concrete Shear Strength
  • The design shear strength governed by concrete
    failure is based on the testing
  • The in-place strength should be taken as the
    minimum value based on computing both the
    concrete and steel

53
(No Transcript)
54
Front Edge Shear Strength, Vc3
55
Corner Edge Shear Strength, Modified Vc3
56
Side Edge Shear Strength, Vc1
57
(No Transcript)
58
Front Edge Shear Strength
  • Where
  • Vco3 Concrete breakout strength, single anchor
  • Cx3 X spacing coefficient
  • Ch3 Member thickness coefficient
  • Cev3 Eccentric shear force coefficient
  • Cvcr Member cracking coefficient

59
Single Anchor Strength
  • Where
  • ? lightweight concrete factor
  • BED distance from back row of studs to
  • front edge

60
X Spacing factor
  • Where
  • X Overall, out-to-out dimension of outermost
  • studs in back row of anchorage
  • nstuds-back Number of studs in back row

61
Thickness Factor
  • Where
  • h Member thickness

62
Eccentricity Factor
  • Where
  • e'v Eccentricity of shear force on a group of
    anchors

63
Cracked Concrete Factor
  • Uncracked concrete
  • Cvcr 1.0
  • For cracked concrete,
  • Cvcr 0.70 no reinforcement
  • or
  • reinforcement lt No. 4 bar
  • 0.85 reinforcement No. 4 bar
  • 1.0 reinforcement. No. 4 bar and
    confined within stirrups with a spacing 4
    in.

64
Corner Shear Strength
  • A corner condition should
  • be considered when
  • where the Side Edge
  • distance (SED) as
  • shown

65
Corner Shear Strength
  • Where
  • Ch3 Member thickness coefficient
  • Cev3 Eccentric shear coefficient
  • Cvcr Member cracking coefficient
  • Cc3 Corner influence coefficient

66
Corner factor
  • For the special case of a large X-spacing stud
    anchorage located near a corner, such that
    SED/BED gt 3, a corner failure may still result,
    if de1 2.5BED

67
Side Edge Shear Strength
  • In this case, the shear force is applied parallel
    to the side edge, de1
  • Research determined that the corner influence can
    be quite large, especially in thin panels
  • If the above ratio is close to the 0.2 value, it
    is recommended that a corner breakout condition
    be investigated, as it may still control for
    large BED values

68
Side Edge Shear Strength
Where Vco1 nominal concrete breakout strength
for a single stud CX1 X spacing coefficient
CY1 Y spacing coefficient Cev1 Eccentric
shear coefficient
69
Single Anchor Strength
  • Where
  • de1 Distance from side stud to side edge (in.)
  • do Stud diameter (in.)

70
X Spacing Factor
  • Where
  • nx Number of X-rows
  • x Individual X-row spacing (in.)
  • nsides Number of edges or sides that influence
    the X direction

71
X Spacing Factor
  • For all multiple Y-row anchorages located
    adjacent to two parallel edges, such as a column
    corbel connection, the X-spacing for two or more
    studs in the row
  • Cx1 nx

72
Y Spacing Factor
  • Where
  • ny Number of Y-rows
  • Y Out-to-out Y-row spacing (in) Sy (in)

73
Eccentricity Factor
  • Where
  • ev1 Eccentricity form shear load to
    anchorage centroid

74
Back Edge Shear Strength
  • Under a condition of pure shear the back edge has
    been found through testing to have no influence
    on the group capacity
  • Proper concrete clear cover from the studs to the
    edge must be maintained

75
In the Field Shear Strength
  • When a headed stud anchorage is sufficiently away
    from all edges, termed in-the-field of the
    member, the anchorage strength will normally be
    governed by the steel strength
  • Pry-out failure is a concrete breakout failure
    that may occur when short, stocky studs are used

76
In the Field Shear Strength
  • For hef/de 4.5 (in normal weight concrete)
  • Where
  • Vcp nominal pry-out shear strength (lbs)

77
Front Edge Failure Example
  • Given
  • Plate with headed studs as shown, placed in a
    position where cracking is unlikely. The 8 in.
    thick panel has a 28-day concrete strength of
    5000 psi. The plate is loaded with an
  • eccentricity of
  • 1 ½ in from the
  • centerline. The
  • panel has 5
  • confinement bars.

78
Example
  • Problem
  • Determine the design shear strength of the stud
    group.

79
Solution Steps
  • Step 1 Check corner condition
  • Step 2 Calculate steel capacity
  • Step 3 Front Edge Shear Strength
  • Step 4 Calculate shear capacity coefficients
  • Step 5 Calculate shear capacity

80
Step 1 Check Corner Condition
  • Not a Corner Condition

81
Step 2 Calculate Steel Capacity
  • fVns fnsAnfut
  • 0.65(4)(0.20)(65) 33.8 kips

82
Step 3 Front Edge Shear Strength
  • Front Edge Shear Strength

83
Step 4 Shear Capacity Coefficient
  • Concrete Breakout Strength, Vco3

84
Step 4 Shear Capacity Coefficient
  • X Spacing Coefficient, Cx3

85
Step 4 Shear Capacity Coefficient
  • Member Thickness Coefficient, Ch3

86
Step 4 Shear Capacity Coefficient
  • Eccentric Shear Force Coefficient, Cev3

87
Step 4 Shear Capacity Coefficient
  • Member Cracking Coefficient, Cvcr
  • Assume uncracked region of member
  • 5 Perimeter Steel

88
Step 5 Shear Design Strength
  • fVcs fVco3Cx3Ch3Cev3Cvcr
  • 0.75(47.0)(0.93)(0.53)(0.94)(1.0)
  • 16.3 kips

89
Interaction
  • Trilinear Solution
  • Unity curve with a 5/3 exponent

90
Interaction Curves
91
Combined Loading Example
  • Given
  • A ½ in thick plate with headed studs for
    attachment of a steel bracket to a column as
    shown at the right
  • Problem
  • Determine if the studs are adequate for the
    connection

92
Example Parameters
  • f'c 6000 psi normal weight concrete
  • ? 1.0
  • (8) 1/2 in diameter studs
  • Ase 0.20 in.2
  • Nominal stud length 6 in.
  • fut 65,000 psi (Table 6.5.1.1)
  • Vu 25 kips
  • Nu 4 kips
  • Column size 18 in. x 18 in.

93
  • Provide ties around vertical bars in the column
    to ensure confinement f 0.75
  • Determine effective depth
  • hef L tpl ths 1/8 in
  • 6 0.5 0.3125 0.125 6.06 in

94
Solution Steps
  • Step 1 Determine applied loads
  • Step 2 Determine tension design strength
  • Step 3 Determine shear design strength
  • Step 4 Interaction Equation

95
Step 1 Determine applied loads
  • Determine net Tension on Tension Stud Group
  • Determine net Shear on Shear Stud Group

96
Step 2 Concrete Tension Capacity
97
Step 2 Steel Tension Capacity
98
Step 2 Governing Tension
99
Step 3 Concrete Shear Capacity
100
Step 3 Steel Shear Capacity
101
Step 3 Governing Shear
102
Step 4 Interaction
  • Check if Interaction is required

103
Step 4 Interaction
104
Questions?
Write a Comment
User Comments (0)
About PowerShow.com