PCI 6th Edition - PowerPoint PPT Presentation

1 / 131
About This Presentation
Title:

PCI 6th Edition

Description:

PCI 6th Edition Fabrication Design Presentation Outline Planning Discussion Stripping Process Design and Analysis Prestress / Post Tension Effects Handling Devices ... – PowerPoint PPT presentation

Number of Views:461
Avg rating:3.0/5.0
Slides: 132
Provided by: JasonL159
Category:

less

Transcript and Presenter's Notes

Title: PCI 6th Edition


1
PCI 6th Edition
  • Fabrication Design

2
Presentation Outline
  • Planning Discussion
  • Stripping Process Design and Analysis
  • Prestress / Post Tension Effects
  • Handling Devices
  • Stripping Stress Examples
  • Storage Discussion
  • Transportation Discussion
  • Erection Discussion

3
Introduction
  • The loads and forces on precast and prestressed
    concrete members during production,
    transportation or erection will frequently
    require a separate analysis
  • Concrete strengths are lower
  • Support points and orientation are usually
    different from members in their final position

4
Pre-Planning Piece Size
  • The most economical piece size for a project is
    usually the largest, considering the following
    factors
  • Stability and stresses on the element during
    handling
  • Transportation size and weight regulations and
    equipment restrictions

5
Pre-Planning Piece Size
  • Available crane capacity at both the plant and
    the project site.
  • Position of the crane must be considered, since
    capacity is a function of reach
  • Storage space, truck turning radius, and other
    site restrictions

6
Planning and Setup
  • Once a piece has been fabricated, it is necessary
    to remove it from the mold without being damaged.
  • Positive drafts or breakaway forms should be used
    to allow a member to lift away from the casting
    bed without becoming wedged within the form
  • Adequate draft also serves to reduce trapped air
    bubbles.

7
Planning and Setup
  • Lifting points must be located to keep member
    stresses within limits and to ensure proper
    alignment of the piece as it is being lifted
  • Members with unsymmetrical geometry or projecting
    sections may require supplemental lifting points
    and auxiliary lifting lines to achieve even
    support during handling
  • Come-alongs or chain-falls are frequently
    used for these auxiliary lines

8
Planning and Setup
  • When the member has areas of small cross section
    or large cantilevers, it may be necessary to add
    a structural steel strongback to the piece to
    provide added strength

9
Planning and Setup
  • Members that require a secondary process prior to
    shipment, such as sandblasting or attachment of
    haunches, may need to be rotated at the
    production facility. In these cases, it may be
    necessary to cast in extra lifting devices to
    facilitate these maneuvers

10
Planning and Setup
  • When developing member shapes, the designer
    should consider the extra costs associated with
    special rigging or forming, and pieces requiring
    multiple handling


11
Stripping General
  • Orientation of members during storage, shipping
    and final in-place position is critical in
    determining stripping requirements
  • They can be horizontal, vertical or some angle in
    between
  • The number and location of lifting devices are
    chosen to keep stresses within the allowable
    limits, which depends on whether the no
    cracking or controlled cracking criteria is to
    be used

12
Stripping General
  • It is desirable to use the same lifting devices
    for both stripping and erection however,
    additional devices may be required to rotate the
    member to its final position

13
Stripping General
  • Panels that are stripped by rotating about one
    edge with lifting devices at the opposite edge
    will develop moments as shown

14
Stripping General
  • When panels are stripped this way, care should be
    taken to prevent spalling of the edge along which
    the rotation occurs
  • A compressible material or sand bed will help
    protect this edge

15
Stripping General
  • Members that are stripped flat from the mold will
    develop the moments shown

16
Stripping General
  • In some plants, tilt tables or turning rigs are
    used to reduce stripping stresses

17
Stripping General
  • Since the section modulus with respect to the top
    and bottom faces may not be the same, the
    designer must select the controlling design
    limitation
  • Tensile stresses on both faces to be less than
    that which would cause cracking
  • Tensile stress on one face to be less than that
    which would cause cracking, with controlled
    cracking permitted on the unexposed face
  • Controlled cracking permitted on both faces

18
Stripping General
  • If only one of the faces is exposed to view, the
    exposed face will generally control the stripping
    method

19
Rigging Configurations
  • Stresses and forces occurring during handling are
    also influenced by the type of rigging used to
    hook up to the member

20
Rigging Configurations
  • Lift line forces for a two-point lift using
    inclined lines are shown

21
Rigging Configurations
  • When the sling angle is small, the components of
    force parallel to the longitudinal axis of the
    member may generate a significant moment due to
    secondary effects

22
Rigging Configurations
  • While this effect can and should be accounted
    for, it is not recommended that it be allowed to
    dominate design moments

23
Rigging Configurations
  • Consideration should be given to using spreader
    beams, two cranes or other mechanisms to increase
    the sling angle
  • Any such special handling required by the design
    should be clearly shown on drawings

24
Rigging Configurations
  • Using a spreader beam can also eliminate the use
    of rolling blocks
  • Note that the spreader beam must be sufficiently
    stiffer than the concrete panel to limit panel
    deflections and cracking
  • Lifting hook locations, hook heights, and sling
    lengths are critical to ensure even lifting of
    the member
  • For analysis, the panel acts as a continuous beam
    over multiple supports

25
Stripping Design
  • To account for the forces on the member caused by
    form suction and impact, it is common practice to
    apply a multiplier to the member weight and treat
    the resulting force as an equivalent static
    service load.
  • The multipliers cannot be quantitatively derived,
    so they are based on experience

26
Stripping Design
  • PCI provides a table of typical values

27
Factor of Safety
  • When designing for stripping and handling, the
    following safety factors are recommended
  • Use embedded inserts and erection devices with a
    pullout strength at least equal to four (4) times
    the calculated load on the device.
  • For members designed without cracking, the
    modulus of rupture (MOR) , is divided by a safety
    factor of 1.5.

28
Stress Limits Crack Control
  • Stress limits for prestressed members during
    production are discussed in Section 4.2.2.2 of
    the the PCI Handbook
  • ACI 318-02 does not restrict stresses on
    non-prestressed members, but does specify minimum
    reinforcement spacing, as discussed in Section
    4.2.2.1. (PCI chapter 4 member design)

29
Stress Limits Crack Control
  • Members which are exposed to view will generally
    be designed for the no discernible cracking
    criteria (see Eq. 4.2.2.2), which limits the
    stress to .
  • In the case of stripping stresses, f'ci should be
    substituted for f'c
  • Whether or not the members are exposed to view,
    the strength design and crack control
    requirements of ACI 318-02, as discussed in
    Chapter 4 of this Handbook, must be followed.

30
Benefits of Prestressing
  • Panels can be prestressed, using either
    pretensioning or post-tensioning.
  • Design is based on Chapter 18 of ACI 318-02, as
    described in Chapter 4 of this Handbook. Further,
    tensile stresses should be restricted to less
    than , must be followed.

31
Benefits of Prestressing
  • It is recommended that the average stress due to
    prestressing, after losses, be within a range of
    125 to 800 psi
  • The prestressing force should be concentric with
    the effective cross section in order to minimize
    camber, although some manufacturers prefer to
    have a slight inward bow in the in-place position
    to counteract thermal bow
  • It should be noted that concentrically
    prestressed members do not camber, hence the form
    adhesion may be larger than with members that do
    camber

32
Strand Recomendation
  • In order to minimize the possibility of splitting
    cracks in thin pretensioned members, the strand
    diameter should not exceed that shown in the
    table below
  • Additional light transverse reinforcement may be
    required to control longitudinal cracking

33
Strand Recommendations
  • When wall panels are post-tensioned, care must be
    taken to ensure proper transfer of force at the
    anchorage and protection of anchors and tendons
    against corrosion
  • Straight strands or bars may be used, or, to
    reduce the number of anchors, the method shown
    may be used

34
Strand Recommendation
  • It should be noted that if an unbonded tendon is
    cut, the prestress is lost. This can sometimes
    happen if an unplanned opening is cut in at a
    later date

35
Handling Devices
  • Since lifting devices are subject to dynamic
    loads, ductility of the material is a requirement
  • Deformed reinforcing bars should not be used as
    the deformations result in stress concentrations
    from the shackle pin
  • Also, reinforcing bars may be hard grade or
    re-rolled rail steel with little ductility and
    low impact strength at cold temperatures

36
Handling Devices
  • Strain hardening from bending may cause
    embrittlement
  • Smooth bars of a known steel grade may be used if
    adequate embedment or mechanical anchorage is
    provided
  • The diameter must be such that localized failure
    will not occur by bearing on the shackle pin

37
Aircraft Cable Loops
  • For smaller precast members, aircraft cable can
    be used for stripping and erection purposes
  • Aircraft cable comes in several sizes with
    different capacities
  • The flexible cable is easier to handle and will
    not leave rust stains on precast concrete

38
Aircraft Cable Loops
  • For some small precast members such as coping,
    the flexible loops can be cast in ends of members
    and tucked back in the joints after erection
  • Aircraft cable loops should not be used as
    multiple loops in a single location, as even pull
    on multiple cables in a single hook is extremely
    difficult to achieve
  • User should ensure that the cable is clean and
    that each leg of the loop is embedded a minimum
    of 48 in.

39
Prestressing Strand Loops
  • Prestressing strand, both new and used, may be
    used for lifting loops
  • The capacity of a lifting loop embedded in
    concrete is dependent upon the strength of the
    strand, length of embedment, the condition of the
    strand, the diameter of the loop, and the
    strength of the concrete

40
Prestressing Strand Loops
  • As a result of observations of lift loop behavior
    during the past few years, it is important that
    certain procedures be followed to prevent both
    strand slippage and strand failure
  • Precast producers tests and/or experience offer
    the best guidelines for the load capacity to use
  • A safety factor of 4 against slippage or breakage
    should be used

41
Strand Loops Recommendations
  • In lieu of test data, the recommendations listed
    below should be considered when using strand as
    lifting loops.
  • Minimum embedment for each leg of the loop should
    be 24 in.
  • The strand surface must be free of contaminants,
    such as form oil, grease, mud, or loose rust,
    which could reduce the bond of the strand to the
    concrete

42
Strand Loops Recommendations
  • Continued
  • The diameter of the hook or fitting around which
    the strand lifting eye will be placed should be
    at least four times the diameter of the strand
    being used
  • Do not use heavily corroded strand or strand of
    unknown size and strength.

43
Strand Loops Recommendations
  • In the absence of test or experience, it is
    recommended that the safe load on a single 1/2
    in. diameter 270 ksi strand loop satisfying the
    above recommendations not exceed 8 kips
  • The safe working load of multiple loops may be
    conservatively obtained by multiplying the safe
    load for one loop by 1.7 for double loops and 2.2
    for triple loops

44
Strand Loops Recommendations
  • To avoid overstress in one loop when using
    multiple loops, care should be taken in the
    fabrication to ensure that all strands are bent
    the same
  • Thin wall conduit over the strands in the region
    of the bend has been used to reduce the potential
    for overstress

45
Strand Loops Recommendations
  • When using double or triple loops, the embedded
    ends may need to be spread apart for concrete
    consolidation around embedded ends without voids
    being formed by bundled strand

46
Threaded Inserts
  • Threaded inserts can have NC (National Course) or
    coil threads
  • Anchorage is provided by loop, strut or
    reinforcing bar
  • Inserts must be placed accurately because their
    safe working load decreases sharply if they are
    not perpendicular to the bearing surface, or if
    they are not in a straight line with the applied
    force

47
Threaded Inserts
  • Embedment of inserts close to an edge will
    greatly reduce the effective area of the
    resisting concrete shear cone and thus reduce the
    tension safe working load of the embedded insert
  • When properly designed for both insert and
    concrete capacities, threaded inserts have many
    advantages
  • However, correct usage is sometimes difficult to
    inspect during handling operations

48
Threaded Inserts
  • In order to ensure that an embedded insert acts
    primarily in tension, a swivel plate as indicated
    in should be used
  • It is extremely important that sufficient threads
    be engaged to develop the strength of the bolt

49
Threaded Inserts
  • For straight tension loads only, eye bolts or
    wire rope loops provide a fast method for
    handling precast members.
  • Do not use either device if shear loading
    conditions exist.

50
Proprietary Devices
  • A variety of castings or stock steel devices,
    machined to accept specialized lifting assemblies
    are used in the precast industry

51
Proprietary Devices
  • These proprietary devices are usually recessed
    (using a pocket former) to provide access to
    the lifting unit. The recess allows one panel to
    be placed against another without cutting off the
    lifting device, and also helps prevent spalling
    around the device
  • Longer devices are used for edge lifting or deep
    precast concrete members
  • Shallow devices are available for thin precast
    concrete members.

52
Proprietary Devices
  • The longer devices usually engage a reinforcing
    bar to provide greater pullout capacity, and
    often have holes for the bar to pass through as
    shown to the left

53
Proprietary Devices
  • These units have a rated capacity as high as 22
    tons, with reductions for thin panels or close
    edge distances
  • Supplemental reinforcement may be required to
    achieve these values
  • Shallow units usually have a spread foot or base
    to increase pullout capacity

54
Proprietary Devices
  • Reinforcing bars are required in two directions
    over the base to fully develop the lifting unit,
    as shown in Figure below
  • These inserts are
  • rated up to 8 tons

55
Proprietary Devices
  • Some lifting eyes do not swivel, so rotation may
    be a concern
  • In all cases manufacturer recommendations should
    be rigorously followed when using any of these
    devices

56
Wall Panel Example
  • This example and others in Chapter 5 illustrate
    the use of many of the recommendations in this
    chapter
  • They are intended to be illustrative and general
    only
  • Each manufacturer will have its own preferred
    methods of handling

57
Wall Panel Example
  • Given
  • A flat panel used as a loadbearing wall on a
    two-story structure, as shown on next slide
  • Section properties (nominal dimensions are used
    for design)
  • Solid panel Panel with
    openings
  • A 960 in2 A 480 in2
  • Sb St 1280 in3 Sb St 640 in3
  • Ix 5120 in4 Ix 2560 4 in4
  • Unit weight _at_ 150 pcf 100 psf 0.100 ksf
  • Total weight 35.2 kips (solid panel)
  • 29.2 kips (panel w/
    openings)

58
Wall Panel Example
59
Wall Panel Example
  • Stripping method
  • Inside crane height prevents panel from being
    turned on edge directly in mold, therefore, strip
    flat
  • Handling multipliers
  • Exposed flat surface has a smooth form finish
    with false joints. Side rails are removable. Use
    multiplier of 1.4

60
Wall Panel Example
  • f'ci at stripping 3000 psi
  • Allowable tensile stresses at stripping and
    lifting
  • Problem
  • Check critical stresses involved with stripping.
    Limit stresses to 0.274 ksi.
  • Compare Simple Solution to Mechanics Solution

61
Solution Steps
  • Step 1 Determine section properties
  • Step 2 Select number of pick points and
    determine maximum stress
  • Step 3 Determine stress from mechanic
    approach
  • Step 4 Check panel with opening
  • Step 5 Check rolling block solution
  • Step 6 Check transverse bending
  • Step 7 Check secondary effects

62
Step 1 Determine Section Properties
  • Solid panel dimensions
  • a 10 ft, b 35.2 ft, a/2 5 ft 60 in.
  • S for resisting section (half of panel width)

63
Step 2 4-point pick
  • Figure 5.36.1.1(a) (page 5-5)

64
Step 2 Check Stresses
  • 4 Point Stresses
  • Not Good try 8 point pick

65
Step 2 8 Point Pick
  • Figure 5.3.1.1(b) (Page 5-5)

66
Step 2 Check Stresses
  • 8 Point Stresses

67
Step 3 Mechanics of Materials
68
Step 4 Panel With Openings
69
Step 5 Rolling Blocks
  • If using a rolling block for handling as shown
    below, the panel cannot be analyzed with the
    previous method
  • Each leg of continuous cable over a rolling block
    must carries equal load

70
Step 5 Rolling Block
71
Step 6 Transverse Bending
  • Consider lower portion of panel with openings
  • Note that Figure Without the concrete in the area
    of the opening, the weight is reduced and
    unevenly distributed. Also, the resisting section
    is limited to a width of 4.7 ft.

72
Step 6 Transverse Bending
  • Section through lifters
  • From continuous beam analysis, load carried by
    bottom two anchors is 7.2 kips, therefore

73
Step 7 Secondary Effects
  • Check added moment due to sling angle
  • Using recessed proprietary lifting anchor
  • e 3.5 in

74
Step 7 Secondary Effects
  • Resisting Section
  • Therefore Section is OK

75
Prestressed Wall Example
  • Given
  • Same wallpanel as previousexample

76
Prestressed Wall Example
  • Problem
  • Determine required number of 1/2 in diameter,
    270 ksi strands pulled to 28.9 kips to prevent
    cracking in window panel. Assume 10 loss of
    prestress.
  • From previous example, tensile stress is 0.431
    ksi. The desired level of tensile stress is
    or 0.274 ksi

77
Solution Steps
  • Step 1 Determine additional compressive
    Required
  • Step 2 Determine the number of strands
    required based on stress
  • Step 3 Calculate the number of strands

78
Step 1 Additional Compressive
  • Compressive stress required
  • 0.431 0.274 0.157 ksi

79
Step 2 Of Strands Based On Stress
  • From previous the max moment/stress occurs at
    lifting points (-M). This results in tensile
    stresses on the top face.

80
Step 3 Number of Strands
  • 0.060(no. of strands) 0.019(no. of strands)
    0.157 ksi
  • No. of strands 3.8
  • Add four strands to panel (two on each side of
    opening)

81
Storage
  • Wherever possible, a member should be stored on
    points of support located at or near those used
    for stripping and handling
  • Where points other than those used for stripping
    or handling are used for storage, the storage
    condition must be checked

82
Storage
  • If support is provided at more than two points,
    and the design is based on more than two
    supports, precautions must be taken so that the
    element does not bridge over one of the supports
    due to differential support settlement

83
Storage
  • Warpage in storage may be caused by
  • temperature or shrinkage differential between
    surfaces
  • creep
  • storage conditions
  • Warpage can only be minimized by providing
  • Where feasible, the member should be oriented in
    the yard so that the sun does not overheat one
    side

84
Storage
  • By superposition, the total instantaneous
    deflection, ymax , at the maximum point can be
    estimated by

Ic , Ib moment of inertia of uncracked section
in the respective directions for 1 in. width of
panel
85
Storage
  • This instantaneous deflection should be modified
    by a factor to account for the time dependent
    effects of creep and shrinkage
  • ACI 318-02 suggests the total deformation yt, at
    any time can be estimated as

86
Storage
  • ? amplification due to creep and shrinkage as a
    function of '? (reinforcement ratio for
    non-prestressed compressionreinforcement,As/b?t)

87
Transportation
  • The method used for transport can affect the
    structural design because of size and weight
    limitations and the dynamic
  • Except for long prestressed deck members, most
    products are transported on either flatbed or
    low-boy trailers
  • Trailers deform during hauling
  • Size and weight limitations vary from one state
    to state
  • Loads are further restricted on secondary roads
  • The common payload for standard trailers without
    special permits is 20 tons.

88
Transportation
  • Low-boy trailers permit the height to be
    increased to about 10 to 12 ft.
  • However they have a have a shorter bed length.
  • This height may require special routing to avoid
    low overpasses and overhead wires

89
Transportation
  • Erection is simplified when members are
    transported in the same orientation they will
    have in the structure
  • For example, single-story wall panels can be
    transported on A-frames with the panels upright
  • A-frames also provide good lateral support and
    the desired two points of vertical support

90
Transportation
  • Longer units can be transported on their sides to
    take advantage of the increased stiffness
    compared with flat shipment

91
Transportation
  • In all cases, the panel support locations should
    be consistent with the panel design
  • Panels with large openings sometimes require
    strongbacks, braces or ties to keep stresses
    within the design values

92
Transportation
  • For members not symmetrical with respect to the
    bending axis, the following expressions can be
    used for determining the location of supports to
    give equal tensile stresses for positive and
    negative bending moments

93
Transportation
  • For one end cantilevered
  • Where
  • yb distance from the bending axis to the
    bottom fiber
  • yt distance from the bending axis to the top
    fiber

94
Transportation
  • For two ends cantilevered
  • Where
  • yb distance from the bending axis to the
    bottom fiber
  • yt distance from the bending axis to the top
    fiber

95
Erection
  • Precast concrete members frequently must be
    reoriented from the position used to transport to
    its final construction position
  • The analysis for this tripping (rotating)
    operation is similar to that used during other
    handling stages
  • In chapter 5 in the PCI handbook, maximum moments
    for several commonly used tripping techniques are
    illustrated

96
Tripping Design Guide
97
Erection
  • When using two crane lines, the center of gravity
    must be between them in order to prevent a sudden
    shifting of the load while it is being rotated
  • To ensure that this is avoided, the stability
    condition shown must be met

98
Erection
  • The capacities of lifting devices must be checked
    for the forces imposed during the tripping
    operation, since the directions vary
  • When rotating a panel with two crane lines, the
    pick points should be located to prevent the
    panel from an uncontrolled roll on the roller
    blocks can be done by slightly offsetting the
    pick point locations to shift the weight toward
    the upper crane line lift points, or by using
    chain drags on the rolling block

99
Erecting Wall Panels Example
  • Given
  • The wall panels with openings used on previous
    examples
  • Problem
  • Determine appropriate procedures for erecting
    the wall panels with openings, panel will be
    shipped flat

100
Erecting Wall Panels Example
  • Assumptions
  • Limit stresses to (0.354 ksi).
  • Crane has main and auxiliary lines.
  • A telescoping man lift is available on site.
  • Solution
  • Try three-point rotation up using stripping
    inserts and rolling block To simplify,
    conservatively use solid panel (no openings) to
    determine moments.

101
Erecting Wall Panels Example
102
Erecting Wall Panels Example
  • In Horizontal Position
  • Therefore, 3 point pick not adequate

103
Erecting Wall Panels Example
  • Knowing from the stripping analysis that a
    four-point pick can be used, the configurations
    shown here may be used
  • However, this rigging may become unstable at some
    point during tripping, i.e., continued rotation
    without tension in Line A
  • Therefore, the lower end of the panel must stay
    within inches of the ground to maintain control.

104
Erecting Wall Panels Example
  • Because the previous configuration requires six
    rolling blocks and can be cumbersome, the method
    shown on the following slide may be an
    alternative

105
Erecting Wall Panels Example
106
Erection Bracing Introduction
  • This section deals with the temporary bracing
    which may be necessary to maintain structural
    stability of a precast structure during
    construction
  • When possible, the final connections should be
    used to provide at least part of the erection
    bracing, but additional bracing apparatus is
    sometimes required to resist all of the temporary
    loads

107
Erection Bracing Introduction
  • These temporary loads may include wind, seismic,
    eccentric dead loads including construction
    loads, unbalanced conditions due to erection
    sequence and incomplete connections Due to the
    low probability of design loads occurring during
    erection, engineering judgment should be used to
    establish a reasonable design load

108
Erection Bracing Responsibilities
  • Proper planning of the construction process is
    essential for efficient and safe erection
  • Sequence of erection must be established early,
    and the effects accounted for in the bracing
    analysis and the preparation of shop drawings
  • The responsibility for the erection of precast
    concrete may vary as follows
  • (see also ACI 318-02 Section 10.3)

109
Erection Bracing Responsibilities
  • The precast concrete manufacturer supplies the
    product erected, either with his own forces, or
    by an independent erector
  • The manufacturer is responsible only for
    supplying the product, F.O.B. plant or jobsite
  • Erection is done either by the general contractor
    or by an independent erector under a separate
    agreement

110
Erection Bracing Responsibilities
  • The products are purchased by an independent
    erector who has a contract to furnish the
    complete precast concrete package.
  • Responsibility for stability during erection must
    be clearly understood.
  • Design for erection conditions must be in
    accordance with all local, state and federal
    regulations. It is desirable that this design be
    directed or approved by a Professional Engineer

111
Erection Bracing Responsibilities
  • It is desirable that this design be directed or
    approved by a Professional Engineer
  • Erection drawings define the procedure
  • on how to assemble the components into the final
    structure
  • The erection drawings should also address the
    stability of the structure during construction
    and include temporary connections

112
Erection Bracing Responsibilities
  • When necessary, special drawings may be required
    to include shoring, guying, bracing and specific
    erection sequences
  • It is desirable that this design be directed or
    approved by a Professional Engineer
  • Erection drawings define the procedure
  • on how to assemble the components into the final
    structure

113
Erection Bracing Responsibilities
  • The erection drawings should also address the
    stability of the structure during construction
    and include temporary connections
  • When necessary, special drawings may be required
    to include shoring, guying, bracing and specific
    erection sequences

114
Erection Bracing Responsibilities
  • For large and/or complex projects, a pre-job
    conference prior to the preparation of erection
    drawings may be warranted, in order to discuss
    erection methods and to coordinate with other
    trades

115
Handling Equipment
  • The type of jobsite handling equipment selected
    may influence the erection sequence, and hence
    affect the temporary bracing requirements
  • Several types of erection equipment are
    available, including truck-mounted and crawler
    mobile cranes, hydraulic cranes, tower cranes,
    monorail systems, derricks and others
  • The PCI Recommended Practice for Erection of
    Precast Concrete provides more information on the
    uses of each.

116
Surveying and Layout
  • Before products are shipped to the jobsite, a
    field check of the project is recommended to
    ensure that prior construction is suitable to
    accept the precast units
  • This check should include location, line and
    grade of bearing surfaces, notches, blockouts,
    anchor bolts, cast-in hardware, and dimensional
    deviations
  • Site conditions such as access ramps, overhead
    electrical lines, truck access, etc., should also
    be checked

117
Surveying and Layout
  • Any discrepancies between actual conditions and
    those shown on drawings should be addressed
    before erection is started
  • Surveys should be required before, during and
    after erection
  • Before, so that the starting point is clearly
    established and any potential difficulties with
    the support structure are determined early.
  • During, to maintain alignment.
  • After, to ensure that the products have been
    erected within tolerances.

118
Loads on Structure
  • The publication Design Loads on Structures During
    Construction (SEI/ASCE 37-02) provides minimum
    design loads, including wind, earthquake and
    construction loads and load combinations for
    partially completed structures and structures
    used during construction
  • In addition to working stress or strength design
    using loads from the above publication, the
    designer must consider the effect of temporary
    loading on stability and bracing design

119
Temporary Loading Examples
  • Columns with eccentric loads from other framing
    members produce sidesway which means the columns
    lean out of plumb
  • A similar condition can exist whencladding
    panels are erected on oneside of a multistory
    structure

120
Temporary Loading Examples
  • Unbalanced loads due to partially complete
    erection may result in beam rotation
  • The erection drawings should address these
    Conditions

121
Temporary Loading Examples
  • Some solutions are
  • Install wood wedges between flange of tee and top
    of beam
  • Use connection to columns that prevent rotation
  • Erect tees on both sides of beam
  • Prop tees to level below

122
Temporary Loading Examples
  • Rotations and deflections of framing members may
    be caused by cladding panels. This may result in
    alignment problems and require connections that
    allow for alignment adjustment after all panels
    are erected

123
Temporary Loading Examples
  • If construction equipment such as concrete
    buggies, man-lifts, etc., are to be used,
    information such as wheel loads and spacing
    should be conveyed to the designer of the precast
    members and the designer of the erection bracing

124
Factors of Safety
  • Suggested safety factors are shown

Bracing inserts cast into precast members 3
Reusable hardware 5
Lifting inserts 4
125
Bracing Equipment and Materials
  • For most one-story and two-story high components
    that require bracing, steel pipe braces similar
    to those shown are used

126
Bracing Equipment and Materials
  • Proper anchoring of the braces to the precast
    members and deadmen must be considered
  • When the pipe braces are in tension, there may be
    significant shear and tension loads applied to
    the deadmen
  • Properly designed deadmen are a requirement for
    safe bracing
  • Cable guys with turnbuckles are normally used for
    taller structures

127
Bracing Equipment and Materials
  • Since wire rope used in cable guys can resist
    only tension, they are usually used in
    combination with other cable guys in an opposite
    direction
  • Compression struts, which may be the precast
    concrete components, are needed to complete truss
    action of the bracing system
  • A number of wire rope types are available
  • Note that capacity of these systems is often
    governed by the turnbuckle capacity

128
General Considerations
  • Careful planning of the erection sequence is
    important
  • This plan is usually developed by a coordinated
    effort involving the general contractor, precast
    erector, precaster production and shipping
    departments and a structural engineer
  • A properly planned erection sequence can reduce
    bracing requirements
  • For example, with wall panel systems a corner can
    first be erected so that immediate stability can
    be achieved

129
General Considerations
  • Similar considerations for shear wall structures
    can also reduce bracing requirements
  • All parties should be made aware of the necessity
    of closely following erection with the welded
    diaphragm connections
  • This includes the diaphragm to shear wall
    connections

130
General Considerations
  • In order for precast erection to flow smoothly
  • The site access and preparation must be ready
  • The to-be-erected products must be ready
  • Precast shipping must be planned
  • The erection equipment must be ready
  • Bracing equipment and deadmen must be ready

131
Questions?
Write a Comment
User Comments (0)
About PowerShow.com