Title: MRP
1 MRP
2 Question how do firms actually organize things
to turn materials into finished products?
MRP (Material Requirements Planning) -
determines number of parts, components and
materials to produce each end item - determines
when each component, part and material is needed
to finish the end items on schedule
3Material Requirements Planning
Manufacturing Resource Planning (MRP II)
Enterprise Resource Planning
4Products are combinations of parts
Example Bicycle
Handle bars (1)
Metal Frame (1)
Wheels (2)
5MRP Systems Materials Requirements Planning
- Bill of Materials (product structure tree,
schematic, product flow diagram) - Relationships with suppliers (we can manufacture
some of the parts, others we can get from
suppliers) - Master Production Schedule is the key input
6Summary How does MRP work?
Material Requirement Planning
Production
Assembly
Customer
Production
Assembly
Production
Units are PUSHED forward according to the plan!
7Lets look at an example BOM...
A
Question How many Ds we need in order to
produce 50 As?
B(2)
C(1)
D(3)
E(3)
D(1)
8How do we manage order release?
We need information on delivery times!
Parts-Product Process Lead Time
A 10
B 15
C 10
D 15
E 10
9Lets look at an example BOM...
A
(10)
Question When do we start producing/ordering
each part?
B(2)
C(1)
(15)
(10)
(15)
D(3)
E(3)
D(1)
(15)
(10)
10Lets assume that we need 50 units of A
Delivery date for final product
5 days
Parts-Products
A
B
C
D
E
11Lets assume that we need 50 units of A
Start assembly for 50 units of A
Parts-Products
A
B
C
D
E
12Lets assume that we need 50 units of A
Start assembly for 100 units of B
Parts-Products
A
B
C
D
E
13Lets assume that we need 50 units of A
Start assembly for 50 units of C
Parts-Products
A
B
C
D
E
14Lets assume that we need 50 units of A
Order 300 units of D for Bs process
Parts-Products
A
B
C
D
E
15Lets assume that we need 50 units of A
Order 50 units of D for Cs assembly
Parts-Products
A
B
C
D
E
16Lets assume that we need 50 units of A
Order 50 units of E for Cs assembly
Parts-Products
A
B
C
D
E
17Lot Sizing in MRP Systems
- Lot-for-lot (L4L)
- Produce to cover next period
- EOQ
- Apply the EOQ approximation for yearly demand
- Least Unit Cost
- Minimize total cost (order carry) per unit
These are all approximate methods, none is
guaranteed to be optimal. We can apply all of
them and find the least-cost one to implement.
18Example
Cost per item 10 Order/setup
cost 47 Inventory carrying cost/month 2 Start
ing inventory 50 Production lead time 1
month Monthly requirements 1 2 3 4 5 6 100 50 80
120 70 80
For the solution, see file mrp_methods.pdf