Title: Corrective Action Plans Frequently Asked Questions
1Corrective Action PlansFrequently Asked Questions
- Leigh Manasevit, Esq.
- lmanasevit_at_bruman.com
- Bonnie Little Graham, Esq.
- bgraham_at_bruman.com
- Jenny Segal , Esq.
- jsegal_at_bruman.com
- Brustein Manasevit, PLLC
- www.bruman.com
- Spring Forum 2013
2Intro
- Newly purchased items of equipment were not
consistently entered into the property tracking
system or, if entered, some of the items of
equipment remained in the warehouses undelivered,
were delivered to an incorrect location, or were
misplaced or stolen. As of 1998, VIDE began to
implement the corrective actions necessary to
revamp its property management system as well as
to correct other deficiencies in its
administration of Federal grant programs.
Progress was slow. As a result, VIDE was
designated as a high-risk grantee and special
conditions were imposed. Later, ED and VIDE
entered into a compliance agreement that
permitted VIDE to continue to receive funding
while it implemented a structured plan to correct
the administrative and programmatic deficiencies.
- Application of U.S. Virgin Islands Dept. of ED,
Docket No. 05-04-R (Jan. 24, 2011).
3Agenda
- When are corrective action plans necessary?
- What needs to be in a corrective action plan?
- Can the state/grantee require a corrective action
plan from locals/subgrantees? - Can I use grant funds to pay for corrective
actions? - How are corrective actions enforced?
- Can I appeal required corrective actions?
4When are corrective action plans necessary?
5Identifying Noncompliance
- Monitoring by ED or grantee
- OIG audit
- A-133 single audit
- Performance data
- Financial data
- Internal review
6Corrective Action Needed
- Program Determination Letters
- OIG Audit Report
- Single Audit Report
- Grant Award Notification special conditions
- Monitoring report
7What needs to be in a corrective action plan?
8Corrective Action Plans
- Objective/activity (measurable)
- Timeline
- Identify person responsible
- Budget
- Data
- Deliverables
9For example
Activity Responsible Party Deliverable Due Date
Ensure compliance with SEAs application process for Federal education funds, including using SEAs application tools, meeting all SEA deadlines and following SEAs amendment procedures. LEA Director of Federal Programs name, contact info Documentation evidencing that LEA used SEA-provided application tools and submitted its application for funds and any amendments in accordance with SEAs application process and deadlines, including budgets and signed assurances. Signature under penalty of perjury by the Superintendent or highest-ranking administrative position at LEA affirming that the submitted application(s) is true and correct. Consistent with SEA published deadlines
10Corrective Action Plan
- Over-promise
- Under-promise
- Unrealistic timeframe
- Does not address the issue
- Correcting noncompliance can be a lengthy
process, measured in years rather than months
11Can the state/grantee require a CAP from
locals/subgrantees?
12Authority
- EDGAR 80.40(a)
- Grantees are responsible for managing the
day-to-day operations of grant and subgrant
supported activities. Grantees must monitor
grant and subgrant supported activities to assure
compliance with applicable Federal requirements
and that performance goals are being achieved.
Grantee monitoring must cover each program,
function or activity.
13Authority
- EDGAR 80.12(a)
- A grantee or subgrantee may be considered high
risk if - Has a history of unsatisfactory performance
- Is not financially stable
- Has management system that does not meet EDGAR
standards - Has not conformed to terms and conditions of
previous awards - Is otherwise not responsible
14Can I use grant funds to pay for corrective
actions?
15Paying for Corrective Actions
- Allowable?
- Necessary and reasonable
- Legal expenses required in the administration of
Federal programs are allowable. - Costs related to cooperative audit resolution are
allowable - Allocable?
- Activity is allowable under multiple programs,
agency has discretion in determining which
programs may be charged. 34 C.F.R. 76.760 - Agency can make business decision regarding
what combination of funds would be applied to a
function or activity that benefits two or more
programs. Implementation Guide for OMB Circular
A-87, QA 2-16 - Example Cross-cutting grants management
policies and procedures manual
16How are corrective actions enforced?
17Enforcement - ED
- Whenever the Secretary has reason to believe that
any recipient of funds under any applicable
program is failing to comply substantially with
any requirement of law applicable to such funds,
the Secretary may - withhold further payments under that program,
- issue a complaint to compel compliance through a
cease and desist order of the Office, - enter into a compliance agreement with a
recipient to bring it into compliance - Â take any other action authorized by law with
respect to the recipient. - Any action, or failure to take action, by the
Secretary under this section shall not preclude
the Secretary from seeking a recovery of funds - GEPA, 20 USC 1235c
18Enforcement - Grantees
- Withholding approval of application
- Withholding of funds
- Reimbursement with special conditions
- High risk designation
19Compliance Agreement
- Continue to receive federal funding
- Clear requirements and deadlines
- Heightened federal oversight
- Deadlines
- Inflexible
- Expensive
20Withholding of Funds
- Withholding
- Reasonable notice of intent to withhold and
opportunity for a hearing with an impartial
hearing officer. 20
U.S.C. 1232c(b)(2) 20 U.S.C. 1234d(b). - Withhold until satisfied there is no longer a
failure to comply. - Suspending
- SEA must provide notice to the subgrantee and
allow it 15 days to show cause why the suspension
should not take effect. 20 U.S.C. 1232c(b)(2). - If the subgrantee does not show cause, SEA may
suspend funds for 60 days.
21Reimbursement with Special Conditions
- ED and Grantees have discretion to impose special
conditions - Grantees are responsible for ensuring all
expenditures are lawful (including subgrantees
expenditures) and for ensuring all findings of
noncompliance are resolved. 34 CFR 80.40(a). - For example SEA could reimburse 80 of each
Federal draw upon receipt of the summary reports
and detailed lists, and then reimburse the
remaining 20 after sampling certain expenditures
and verifying detailed supporting documentation
(such as time and effort documentation supporting
payroll charges and requisition requests,
purchase orders, contracts, receiving documents,
invoices and canceled checks for non-payroll
charges). - Is this reimbursement scheme withholding?
22High Risk Designation
- After placing the grantee/subgrantee on high
risk, special conditions or restrictions that
correspond to the high risk condition must be
imposed. Such special conditions or restrictions
may include - Payment on a reimbursement basis
- Withholding authority to proceed to the next
phase until receipt of evidence of acceptable
performance within a given funding period - Requiring additional, more detailed financial
reports - Additional project monitoring
- Requiring the grantee or subgrantee to obtain
technical or management assistance or - Establishing additional prior approvals.
- 34 CFR 80.12(b)
23Can I appeal required corrective actions?
24Appeal
- Disallowance vs. Corrective action
- GEPA permits an appeal of a disallowance decision
- No appeal of corrective actions
- A-133, _.315(c) If the auditee does not agree
with the audit findings or believes corrective
action is not required, then the corrective
action plan shall include an explanation and
specific reasons.
25Appeal Disallowance
- Impact of Corrective Action on Recovery Amount
- Compromise authority In certain circumstances,
ED may compromise the amount claimed under GEPA
if the grantee/subgrantee demonstrates the
practice that resulted in the disallowance
decision has been corrected and will not recur.
34 C.F.R. 81.36(a). - Grantback In certain circumstances, ED may offer
a grantback of up to 75 of the recovered funds
if the practices or procedures of the recipient
that resulted in the violation have been
corrected. 20 U.S.C. 1234h(a). - Equitable offset Remedy available to grantees
and subgrantees to prevent the recovery of
sustained audit liabilities. Case law
establishes that evidence of appropriate
corrective actions is an equitable factor in
support of the application of equitable offset.
26The Super Circular on corrective actions
27Cooperative Audit Resolution
- Federal agencies offering appropriate amnesty
for past noncompliance when audits show prompt
corrective action has occurred. - Corrective Action means action taken by the
auditee that - Corrects identified deficiencies
- Produces recommended improvements or
- Demonstrates that audit findings are either
invalid or do not warrant auditee action
28(No Transcript)
29For example
- In one jurisdiction, ED issued a 70 Page PDL
which determined all findings were either - 1. Resolved and closed because ED had received
sufficient documentation that corrective action
was already in place or - 2. Required further corrective action
- Please note that corrective action is required
for some of these audit findings, as well as
audit findings not specifically addressed in this
PDL. ED will continue to work with you to
implement corrective actions required by this
PDL. - Emphasized the importance of
- 1. Producing records at the time they are
requested by the auditors and complying with the
requirements in 76.730(e) of EDGAR to keep
records to facilitate an effective audit and - 2. Working with ED (not being adversarial).
-
30For example
- A second jurisdiction received a 76 page PDL
regarding two single-audits. PDL did not demand
recovery of any funds, but mandated several
corrective actions, such as - MOE Review MOE calculation methodologies and
update use audited data complete MOE
calculations in a timely manner and communicate
data to LEAs to ensure timely completion of A-133
audits. - Is audited data required?
- Subrecipient Monitoring Process for identifying
high risk grantees under 80.12 conduct fiscal
monitoring (cannot rely solely on A-133 audits). - Comparability Develop and implement an
indicator for monitoring comparability and
integrate this indicator into protocols for
subrecipient monitoring.
31For example . . . Colorado
- OIG We commend CDE for initiating timely
corrective action in response to the audits
finding and recommendations. The actions that CDE
describes in its comments, in response to our
recommendations, would appear to address our
finding, but the Department will ultimately make
this determination. - PDL We find that the policies and procedures
provided generally appear sufficient to establish
an effective system to account for the
distribution of effort for employees who work on
multiple programs, however we have questions
regarding implementation . . . - Single audit findings!
32Disclaimer
This presentation is intended solely to provide
general information and does not constitute legal
advice. Attendance at the presentation or later
review of these printed materials does not create
an attorney-client relationship with Brustein
Manasevit, PLLC. You should not take any action
based upon any information in this presentation
without first consulting legal counsel familiar
with your particular circumstances.