Chapter 6: Project Cost Management - PowerPoint PPT Presentation

1 / 41
About This Presentation
Title:

Chapter 6: Project Cost Management

Description:

... only parametric models do not suffer from the limits of human decision-making ... Corrective action ... Negative number for schedule variance (SV) mean ... – PowerPoint PPT presentation

Number of Views:141
Avg rating:3.0/5.0
Slides: 42
Provided by: Informatio328
Category:

less

Transcript and Presenter's Notes

Title: Chapter 6: Project Cost Management


1
Chapter 6Project Cost Management
  • adopted from PMIs PMBOK 2000 and
  • Textbook Information Technology Project
    Management
  • (author Dr. Kathy Schwalbe)

2
Contents
  • Importance of Project Cost Management
  • Problem cost overrun and cannot meet cost goals
  • Costs are measured in monetary units
  • Project Cost Management
  • Resource planning, Cost estimating, Cost
    budgeting, Cost control
  • Resource Planning consideration
  • difficulty, uniqueness, track record, people,
    equipment and materials
  • Types of cost estimate
  • basic tools and techniques
  • Earned value management is an important tool for
    cost control

3
The Importance of Project Cost Management
  • IT projects have a poor track record for meeting
    cost goals
  • Average cost overrun from 1995 CHAOS study was
    189 of the original estimates improved to 45
    in the 2001 study
  • In 1995, cancelled IT projects cost the U.S. over
    81 billion

Chapter 6
4
Typical allocation of cost
5
What is Cost and Project Cost Management?
  • Cost is a resource sacrificed or fore-gone to
    achieve a specific objective or something given
    up in exchange
  • Costs are usually measured in monetary units like
    dollars
  • This is the process group to ensure the project
    is completed within the approved budget.
  • The major output is the cost management plan
  • There are 4 processes in Project Cost Management

Chapter 6
6
Project Cost Management Processes
  • Resource planning (planning phase)
  • determining what resources and quantities of them
    should be used
  • Cost estimating (planning phase)
  • developing an estimate of the costs and resources
    needed to complete a project
  • Cost budgeting (planning phase)
  • allocating the overall cost estimate to
    individual work items to establish a baseline for
    measuring performance
  • Cost control (control phase)
  • controlling changes to the project budget

Chapter 6
7
Basic Principles of Cost Management
  • Most CEOs and boards know a lot more about
    finance than IT, IT project managers must speak
    their language
  • Profits are revenues minus expenses
  • Life cycle costing is estimating the cost of a
    project over its entire life
  • Cash flow analysis is determining the estimated
    annual costs and benefits for a project
  • Benefits and costs can be tangible or intangible,
    direct or indirect
  • Sunk cost should not be a criteria in project
    selection

Chapter 6
8
Cost of Software Defects
It is important to spend money up-front on IT
projects to avoid spending a lot more later.
Chapter 6
9
Resource Planning
  • 8th of 21 planning phase process
  • The nature of the project and the organization
    will affect resource planning
  • Some questions to consider
  • How difficult will it be to do specific tasks on
    the project?
  • Is there anything unique in this projects scope
    statement that will affect resources?
  • What is the organizations history in doing
    similar tasks?
  • Does the organization have or can they acquire
    the people, equipment, and materials that are
    capable and available for performing the work?

10
Inputs to Resource Planning
  • WBS
  • identifies the project elements that require
    resources.
  • Historical information
  • identifies required resourced used in similar
    work on previous project.
  • Scope statement
  • contains the project justification and the
    project objectives.
  • Resource pool description
  • identifies available project resources.
  • Organizational policies
  • may impact some of the project management
    decision. These are constraints, such as
    staffing, rentals, and purchasing supplies and
    equipment.
  • Activities duration estimates
  • the best estimates of the time that it will take
    to perform the work
  • It is the output of Time Management Process
    Activity Duration Estimating.

11
Tools techniques
  • Expert judgment
  • access the inputs to the process by
    subject-matter expect, group, or individual,
    including consultants, professional or technical
    associations, industrial advisory groups.
  • Project management software
  • help to organize resource pools, define resource
    availabilities and their rates, and define
    resource calendars.

12
Outputs from Resource Planning
  • Resources requirement
  • describes the types (e.g. skills levels) and
    number of resources required by each element of
    the WBS.

13
Cost Estimating
  • 9th planning phase process
  • collecting and predicting the costs over the life
    cycle of a project or phase of a project
  • developing cost estimates for all the resources
    needed to complete project activities.
  • An important output of project cost management is
    a cost estimate
  • There are several types of cost estimates and
    tools and techniques to help create them
  • It is also important to develop a cost management
    plan that describes how cost variances will be
    managed on the project

Chapter 6
14
Inputs to Cost Estimating (1)
  • WBS
  • Resource requirement
  • Outputs from Resource Planning
  • Resource rates unit rates for each resource
    that are used to calculate project costs.
  • Activities duration estimates
  • output of Time Management Process Activity
    Duration Estimating.
  • Estimating publication
  • provide commercial cost data.

15
Inputs to Cost Estimating (2)
  • Historical information
  • the cost of many categories of resources is
    available from the following sources a) project
    file b) commercial cost-estimating databases c)
    project team knowledge.
  • Chart of accounts (COA)
  • describes the coding structure or the budget
    categories that the performing organization uses
    to report financial information in its general
    ledger.
  • Risk
  • to show the importance of considering the impacts
    of both opportunities and threats for costs
    estimates for each activity

16
Tools techniques
  • Analogous estimating
  • known as top-down
  • A form of expert judgment because it uses actual
    costs from previous, similar projects to estimate
    current costs
  • Although it is less costly than other estimates,
    it is the least accurate
  • It is frequently used to estimate total project
    costs when a limited amount of detailed
    information is available.
  • Parametric modeling
  • uses project characteristics as the parameters is
    a mathematical model to predict project costs
  • Models may be simple or complex (e.g. simulations
    using statistics or function point analysis to
    estimate software development durations)
  • The costs and accuracy of parameters model vary.

17
Tools techniques (2)
  • Bottom up estimating
  • estimating the cost of individual activities or
    work packages and then adding the individual
    estimates to arrive at a project total
  • Defining smaller activities or work packages
    increases both the cost and accuracy of the
    estimate.
  • Computerized tools
  • Project management software, spreadsheets,
    simulation tools, and statistical packages can
    help estimate costs.
  • Other cost estimating methods
  • includes vendor bid analyses.

18
Types of Cost Estimates
Chapter 6
19
Outputs from Cost Estimating
  • Cost estimates
  • Quantitative assessments of the likely costs of
    the resources required to complete project
    activities. Cost estimates types include
  • preliminary estimate
  • budget estimate
  • analogy estimates
  • definitive and control estimates
  • Supporting details
  • include description of the scope of work
    estimated, reference to WBS, the basis of the
    estimate, assumptions, and the range of possible
    results.
  • Cost management plan
  • describe how cost variances will be managed. It
    is part of the project plan.

20
Constructive Cost Model (COCOMO)
  • Prof Barry Boehm helped develop the COCOMO models
    for estimating software development costs
  • a famous parametric model for software
    development industry
  • Parameters include source lines of code or
    function points (these two are common parameters
    to measure the complexity of a program)
  • COCOMO II is a computerized model available on
    the web
  • Boehm suggest that only parametric models do not
    suffer from the limits of human decision-making

Chapter 6
21
Typical Problems with IT Cost Estimates
  • Developing an estimate for a large software
    project is a complex task requiring a significant
    amount of effort.
  • Remember that estimates are done at various
    stages of the project
  • Many people doing estimates have little
    experience doing them.
  • Try to provide training and mentoring
  • People have a bias toward underestimation
  • Review estimates and ask important questions to
    make sure estimates are not biased
  • Management wants a number for a bid, not a real
    estimate.
  • Project managers must negotiate with project
    sponsors to create realistic cost estimates

Chapter 6
22
Cost Budgeting
  • 10th of 21 planning process
  • It is the process of allocating cost estimates to
    individual work activates
  • Cost budget involves allocating the project cost
    estimate to individual work items and providing a
    cost baseline
  • For example, in the Business Systems Replacement
    project, there was a total purchased costs
    estimate for FY97 of 600,000 and another 1.2
    million for Information Services and Technology
  • The project budget is the planned cost of each
    activity at the lowest level, which is then
    rolled into a project total.

Chapter 6
23
Inputs to Cost Budgeting
  • Cost estimates
  • output from cost estimates process
  • WBS
  • output from scope definition process
  • Project schedule
  • includes planned start and expected finish dates
    for the activities or work packages in order to
    allocate costs.
  • Risk management plan
  • A part of the project plan that contains
    procedures to manage risk throughout the project.

24
Outputs from Cost Budgeting
  • Cost baseline
  • A time-phased budget that will be used to measure
    and monitor cost performance on the project
  • It is developed by summing estimated costs by
    period and is usually displayed in the form of an
    S-curve
  • Larger projects may have multiple cost baselines
    to measure different aspects of cost performance.

25
Cost Control
  • 5th of 8 controlling phase process
  • Project cost control include
  • monitoring cost performance
  • ensuring that only appropriate project changes
    are included in a revised cost baseline
  • informing project stakeholders of authorized
    changes to the project that will affect costs
  • During this process, project manager try to
    determine what facts impact, cost, how these
    factors can be influenced, whether these changes
    are beneficial to the project or product.
  • Earned value management (EVM) is an important
    tool for cost control

Chapter 6
26
Inputs to Cost Control
  • Cost baseline
  • includes a time-phased budget used to measure and
    monitor cost performance on the project
  • The cost baseline is usually shown as
    cost-by-period and can be charted in the form of
    an S-curve.
  • Performance reports
  • provide information on cost performance, such as
    which budgets have been met and which have not.
  • Change requests
  • take many forms oral or written, direct or
    indirect, external or internally initiated, and
    legally mandated or optional.
  • Cost management plan
  • describes managing cost variances

27
Tools techniques
  • Cost change control system
  • defines the procedures by which the cost baseline
    may be changed
  • It includes the paperwork, tracking systems, and
    approval levels necessary for authorizing
    changes.
  • Performance measurement techniques
  • help to assess the magnitude or any variation
    that do occur.
  • Earned value analysis is especially useful for
    cost control
  • Earned value management (EVM) is the tools
    commonly used to determine variance causes and
    deciding if the variance requires corrective
    action.
  • Additional planning
  • prospective changes may require new or revised
    cost estimates or analysis of alternative
    approaches.
  • Other general computerized tools
  • project management software or spreadsheets that
    track planned versus actual costs or that
    forecast the effects of cost changes.

28
Earned Value Management (EVM)
  • EVM is a project performance measurement
    technique that integrates scope, time, and cost
    data
  • Given a baseline (original plan plus approved
    changes), you can determine how well the project
    is meeting its goals
  • You must enter actual information periodically to
    use EVM.
  • The following shows a sample form for collecting
    information

Chapter 6
29
Earned Value Management Terms
  • The planned value (PV), formerly called the
    budgeted cost of work scheduled (BCWS), also
    called the budget, is that portion of the
    approved total cost estimate planned to be spent
    on an activity during a given period
  • Actual cost (AC), formerly called actual cost of
    work performed (ACWP), is the total of direct and
    indirect costs incurred in accomplishing work on
    an activity during a given period
  • The earned value (EV), formerly called the
    budgeted cost of work performed (BCWP), is the
    percentage of work actually completed multiplied
    by the planned value

Chapter 6
30
Earned Value Calculations for One Activity After
Week One
31
Earned Value Formulas
To estimate what it will cost to complete a
project or how long it will take based on
performance to date, divide the budgeted cost or
time by the appropriate index.
Chapter 6
32
Rules of Thumb for EVA Numbers
  • Negative numbers for cost variance (CV) and
    schedule variance (SV) indicate problems in those
    areas.
  • The project is costing more than planned
  • The project is taking longer than planned
  • CPI and SPI less than 100 indicate problems
  • The of the project is over budget in cost
  • The of the project is behind schedule in time

Chapter 6
33
Earned Value Calculations for a One-Year Project
After Five Months
Excel file
34
Earned Value Chart for Project After Five Months
Excel file
35
Using Software to Assist in Cost Management
  • Spreadsheets are a common tool for resource
    planning, cost estimating, cost budgeting, and
    cost control
  • Many companies use more sophisticated and
    centralized financial applications software for
    cost information
  • Project management software has many cost-related
    features

Chapter 6
36
Outputs from Cost Control
  • Revised cost estimates
  • update of the project cost estimates.
  • Budget updates
  • changes to an approval cost baseline. The numbers
    are generally revised only in response to scope
    changes.
  • Cost variance may be so severe that re-baselining
    is needed in order to provide a realistic measure
    of performance.
  • Corrective action
  • anything done to bring expected future project
    performance into line with the project plan.

37
Outputs from Cost Control (2)
  • Estimate at completion (EAC)
  • A forecast of total project costs based on
    project performance. The most common variations
    are
  • actual cost to date plus the remaining project
    budget modified by a performance factor
  • actual costs to date plus a new estimate for all
    remaining works
  • actual cost to date plus the remaining budget.
  • Project closeout
  • processes and procedures for closing or canceling
    the project.
  • Lessons learned
  • document the causes of variances, reasons behind
    the corrective action chosen, and other lessons
    learned.

38
Summary
  • Importance of Project Cost Management
  • Problem cost overrun and cannot meet cost goals
  • Costs are measured in monetary units
  • Project Cost Management
  • Resource planning determining what resources and
    quantities of them should be used
  • Cost estimating developing an estimate of the
    costs and resources needed to complete a project
  • Cost budgeting allocating the overall cost
    estimate to individual work items to establish a
    baseline for measuring performance
  • Cost control controlling changes to the project
    budget
  • Resource Planning consideration
  • difficulty, uniqueness, track record, people,
    equipment and materials

39
Summary (2)
  • Types of cost estimate
  • ROM, Budgetary and definitive
  • Basic tools and techniques in cost estimation
  • top-down, bottom-up, parametric Cocomo
  • Cost budget involves allocating the project cost
    estimate to individual work items and providing a
    cost baseline
  • Project cost control includes
  • monitoring cost performance
  • ensuring that only appropriate project changes
    are included in a revised cost baseline
  • informing project stakeholders of authorized
    changes to the project that will affect costs
  • Earned value management is an important tool for
    cost control

40
Quiz
2. What would a single payment of 35,000 two
years from now be worth today with a 10 interest
rate? a. 42,350 b. 28,926 c. 31,818 d.
26,296 answer B
  • 1.The future value of 2000 invested for 2 years
    at 8.5 will be?
  • a. 2,710
  • b. 2,355
  • c. 2,555
  • d. 7,772
  • answer B

41
Short Questions
  • Negative numbers for cost variance (CV) mean
    _______
  • Negative number for schedule variance (SV) mean
    ________________
  • Which problem can be detected if CPI is less than
    100 ? _________________________________
  • Which problem can be detected if SPI is less than
    100 ? ________________________________
  • ans The project is costing more than planned
  • The project is taking longer than planned
  • The of the project is over budget in cost
  • The of the project is behind schedule in time
Write a Comment
User Comments (0)
About PowerShow.com