- PowerPoint PPT Presentation

1 / 34
About This Presentation
Title:

Description:

Non-Typical Economic, Environmental, and Other Flood Risk Management Benefits ARCF Non-typical NED Categories for EE Environmental Benefits Flooding is natural ... – PowerPoint PPT presentation

Number of Views:35
Avg rating:3.0/5.0
Slides: 35
Provided by: GESLINGR9
Learn more at: http://wleb.org
Category:

less

Transcript and Presenter's Notes

Title:


1
Non-Typical Economic, Environmental, and
Other Flood Risk Management Benefits
2
What are non-typical FRM benefits?
  • Evacuation-Transition-Reoccupation
  • Increased Living Expenses
  • Health Costs
  • Traffic Diversions
  • Emergency Response
  • Public Assistance
  • Environmental Damage

3
What are underutilized FRM benefits?
  • Emergency Response (Search and Rescue)
  • Clean Up (Debris Removal)
  • Administrative (SBA Loans, Other Agencies)
  • Damages to Roads and Public Works
  • Damages to Utilities

4
What are the potential value of and underutilized
non-typical FRM benefits?
  • THESE BENEFITS CAN REPRESENT AS MUCH AS 25 TO
    35 OF THE BENEFIT BASE ON A TYPICAL FRM PROJECT
  • But they can be very difficult to quantify,
    difficult to model and differentiate between
    alternatives
  • Hard to make site specific without recent
    verified data from historical events

5
Expert Elicitation Non-Typical Damage Categories
  • In instances where it may be too time consuming
    or expensive to collect essential historical
    data, EE can be used as a substitute
  • Specific pre-determined Questions are directed to
    subject matter experts for various damage
    scenarios
  • Their responses are used to populate algorithm to
    estimate damages

6
ARCF Non-typical NED Categories for EE
7
(No Transcript)
8
Preliminary EE Results
9
Environmental Benefits
  • Flooding is natural flood damage reduction is
    not
  • Flood damage reduction measures can have
    environmental consequences
  • Some are intended, some are not
  • Some are anticipated, some are not
  • Some are beneficial, some are adverse
  • Unanticipated, unintended consequences may be the
    worst type

10
USACE Environmental Operating Principles
(condensed version)
  • 1. Strive to achieve Environmental
    Sustainability.
  • 2. Recognize the interdependence of life and the
    physical environment.
  • 3. Seek balance and synergy among human
    development activities and natural systems.
  • 4. Continue to accept corporate responsibility
    and accountability.
  • 5. Seek ways and means to assess and mitigate
    cumulative impacts.
  • 6. Build and share an integrated scientific,
    economic social knowledge base.
  • 7. Respect the views of individuals and groups
    interested in Corps activities listen to them
    actively and learn from their perspective.

See ER 200-1-5 for implementation policy guidance
11
Three Reasons for Principles
  • 1. To create unity of purpose within the Corps
    when dealing with environmental issues
  • 2. To reflect a new tone and direction for
    dialogue on environmental matters
  • 3. To ensure that conservation, environmental
    preservation and restoration are considered in
    all Corps activities at same level as economic
    issues

12
The Marriage of
Environmental Restoration
Flood Risk Management
has been a successional process
13
Flood Damage Reduction Mission without
Environmental Concern
Flood Damage Reduction
with Increasing Environmental Awareness, FWCA
CWA NEPA ESA Ecosystem Restoration made a
Stand Alone Mission, WRDA 86 1135 WRDA 90 303
WRDA 96 206 Integrated Flood Risk
Management and Ecosystem
Restoration Purposes, WRDA 99 212
14
Finding Environmental Opportunities is not a New
Concept
15
AKA 1. Good Environmental Design 2. Impact
Avoidance 3. Impact Minimization 4.
Mitigation 5. The Environmental Alternative
16
We have delayed or walked away from many good
projects that were economically marginal by not
claiming environmental improvements as benefits
for non-structural and structural projects
17
Breakthrough !! Recognition that Environment has
non-monetary value
Projects can be justified on non-monetary values
WRDA 86 1135
18
Dual Purpose Projects may be justified using a
combination of traditional economics
and non-traditional ecosystem values
but you must show significant Flood Damage
Reduction and Ecosystem Improvement
19
SCRB Method
  • Separable Cost-Remaining Benefits (SCRB)
  • Adopted by interagency agreement March 1954 as
    preferred method
  • ER 1105-2-100 reaffirmed its preferred status

20
SCRB Definitions
  • Cost Allocation is the process of equitably
    distributing project costs among project
    purposes.
  • Separable costs - costs incurred specifically to
    add a purpose to a project
  • Joint costs - the difference between the total
    project costs and the sum of all separable costs

21
Formulation Requirements for SCRB Allocation
  • Cost allocation requires formulation of specific
    plans
  • Multipurpose plan
  • Multipurpose plans less each purpose
  • Most likely alternative single purpose plan

22
Allocation Equity
  • Use of the SCRB method results in the following
    maximum and minimum cost limits for each purpose
  • Maximum
  • Benefits to each purpose
  • Cost of the least cost alternative for each
    purpose.
  • Minimum separable costs
  • Most likely proportional sharing of joint costs
    of multipurpose added to minimum

23
Major Key Points
  • You know all there is to know
  • The allocation method is relatively straight
    forward Those who benefit pay
  • Problems relate to the inputs that are required

24
Ecosystem Restoration Example
  • To determine alternative project cost for
    ecosystem restoration purposes
  • Determine the cost of the next most efficient
    plan producing the same ecosystem output and
    meeting the planning objectives
  • If the plan formulation is done correctly, the
    cost of the ecosystem restoration portion of the
    multipurpose plan represents a more efficient
    investment. If not, reformulate.

25
SCRB Example
26
The Project Flood Damage Reduction and
Ecosystem Restoration
  • Total Cost Dual-purpose Project 7,000
  • Cost without Ecosystem Restoration 2,930
  • Cost without Flood Damage Reduction 5,350
  • Flood Damage Reduction Benefits 1,930
  • Ecosystem Benefits Non-monetary

27
Flood Damage Reduction - Ecosystem Restoration
SCRB Example
Flood Damage Reduction Ecosystem Restoration Total
Average Annual Benefits 1,930 Non-monetary 1,930 Non-monetary
Single Purpose Alternative Cost 2,930 5,350 8,280
Limited Benefits/Costs 1,930 5,350 7,280
Separable Costs 1,650 5,070 6,720
Remaining Benefits 280 280 560
Percent of Total 50 50 100
Joint Costs - - 280
Allocated joint cost 140 140 -
Total allocation 7,000
1,790
5,210
28
Other Social Effects(from IPET Report)
  • Drowning
  • Infection
  • Homicide
  • Suicide
  • Accidents
  • Injury
  • Illness
  • Fraud

29
Other Social Effects (OSE) Account
  • Communitys Resiliency Social Vulnerability
  • Environmental Justice
  • Quality of Life Indicators
  • Solid academic literature
  • Widely used
  • Recommended by GAO
  • Models
  • Hedonic Models
  • Loss of Life Estimation

30
Regional Economic Development (RED)
  • Typically regional economic impacts of a project
    can be classified into one of three categories
  • Direct effects which represent the initial change
    of the new expenditure stream on industries in
    direct support of the new project. These direct
    industries will require support.
  • Indirect effects are changes in inter-industry
    transactions as supplying industries respond to
    new demands placed on them by direct
    industries.
  • Induced effects are changes in consumer spending
    patterns caused by increases in employment and
    income as direct and indirect industries
    increase their employment.

31
Evaluating RED
  • Construction impacts in project area Creates
    direct, indirect and induced jobs for local
    economy (why not NED Transfers)
  • Non-NED Flood damage reduction- interruption of
    activities due to flood

32
Portfolio Management
  • Why is this an important project?
  • Why is this project more important than other
    projects?
  • In addition to whether a project delivers high
    priority outputs successfully meets established
    budget criteria
  • RED and OSE accounts could help answer why
    important?
  • Ex saves x lives, keeps local economy viable

33
Measurement challenges that we will need to
think through
  • Can OSE and RED be qualitative or quantitative?
  • Technical challenges in measuring them
  • Need to measure for existing conditions, future
    w/ and w/o project conditions
  • In addition to the difference between w/ and w/o
    project conditions, can we distinguish between
    alternatives?
  • Significance of effect influences need to measure
    quantitatively

34
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com