Title:
1Non-Typical Economic, Environmental, and
Other Flood Risk Management Benefits
2What are non-typical FRM benefits?
- Evacuation-Transition-Reoccupation
- Increased Living Expenses
- Health Costs
- Traffic Diversions
- Emergency Response
- Public Assistance
- Environmental Damage
3What are underutilized FRM benefits?
- Emergency Response (Search and Rescue)
- Clean Up (Debris Removal)
- Administrative (SBA Loans, Other Agencies)
- Damages to Roads and Public Works
- Damages to Utilities
4What are the potential value of and underutilized
non-typical FRM benefits?
- THESE BENEFITS CAN REPRESENT AS MUCH AS 25 TO
35 OF THE BENEFIT BASE ON A TYPICAL FRM PROJECT - But they can be very difficult to quantify,
difficult to model and differentiate between
alternatives - Hard to make site specific without recent
verified data from historical events
5Expert Elicitation Non-Typical Damage Categories
- In instances where it may be too time consuming
or expensive to collect essential historical
data, EE can be used as a substitute - Specific pre-determined Questions are directed to
subject matter experts for various damage
scenarios - Their responses are used to populate algorithm to
estimate damages
6ARCF Non-typical NED Categories for EE
7(No Transcript)
8Preliminary EE Results
9Environmental Benefits
- Flooding is natural flood damage reduction is
not - Flood damage reduction measures can have
environmental consequences - Some are intended, some are not
- Some are anticipated, some are not
- Some are beneficial, some are adverse
- Unanticipated, unintended consequences may be the
worst type
10USACE Environmental Operating Principles
(condensed version)
- 1. Strive to achieve Environmental
Sustainability. - 2. Recognize the interdependence of life and the
physical environment. - 3. Seek balance and synergy among human
development activities and natural systems. - 4. Continue to accept corporate responsibility
and accountability. - 5. Seek ways and means to assess and mitigate
cumulative impacts. - 6. Build and share an integrated scientific,
economic social knowledge base. - 7. Respect the views of individuals and groups
interested in Corps activities listen to them
actively and learn from their perspective.
See ER 200-1-5 for implementation policy guidance
11Three Reasons for Principles
- 1. To create unity of purpose within the Corps
when dealing with environmental issues - 2. To reflect a new tone and direction for
dialogue on environmental matters - 3. To ensure that conservation, environmental
preservation and restoration are considered in
all Corps activities at same level as economic
issues
12The Marriage of
Environmental Restoration
Flood Risk Management
has been a successional process
13Flood Damage Reduction Mission without
Environmental Concern
Flood Damage Reduction
with Increasing Environmental Awareness, FWCA
CWA NEPA ESA Ecosystem Restoration made a
Stand Alone Mission, WRDA 86 1135 WRDA 90 303
WRDA 96 206 Integrated Flood Risk
Management and Ecosystem
Restoration Purposes, WRDA 99 212
14Finding Environmental Opportunities is not a New
Concept
15AKA 1. Good Environmental Design 2. Impact
Avoidance 3. Impact Minimization 4.
Mitigation 5. The Environmental Alternative
16We have delayed or walked away from many good
projects that were economically marginal by not
claiming environmental improvements as benefits
for non-structural and structural projects
17Breakthrough !! Recognition that Environment has
non-monetary value
Projects can be justified on non-monetary values
WRDA 86 1135
18Dual Purpose Projects may be justified using a
combination of traditional economics
and non-traditional ecosystem values
but you must show significant Flood Damage
Reduction and Ecosystem Improvement
19SCRB Method
- Separable Cost-Remaining Benefits (SCRB)
- Adopted by interagency agreement March 1954 as
preferred method - ER 1105-2-100 reaffirmed its preferred status
20SCRB Definitions
- Cost Allocation is the process of equitably
distributing project costs among project
purposes. - Separable costs - costs incurred specifically to
add a purpose to a project - Joint costs - the difference between the total
project costs and the sum of all separable costs
21Formulation Requirements for SCRB Allocation
- Cost allocation requires formulation of specific
plans - Multipurpose plan
- Multipurpose plans less each purpose
- Most likely alternative single purpose plan
22Allocation Equity
- Use of the SCRB method results in the following
maximum and minimum cost limits for each purpose - Maximum
- Benefits to each purpose
- Cost of the least cost alternative for each
purpose. - Minimum separable costs
- Most likely proportional sharing of joint costs
of multipurpose added to minimum
23Major Key Points
- You know all there is to know
- The allocation method is relatively straight
forward Those who benefit pay - Problems relate to the inputs that are required
24Ecosystem Restoration Example
- To determine alternative project cost for
ecosystem restoration purposes - Determine the cost of the next most efficient
plan producing the same ecosystem output and
meeting the planning objectives - If the plan formulation is done correctly, the
cost of the ecosystem restoration portion of the
multipurpose plan represents a more efficient
investment. If not, reformulate.
25SCRB Example
26The Project Flood Damage Reduction and
Ecosystem Restoration
- Total Cost Dual-purpose Project 7,000
- Cost without Ecosystem Restoration 2,930
- Cost without Flood Damage Reduction 5,350
- Flood Damage Reduction Benefits 1,930
- Ecosystem Benefits Non-monetary
27Flood Damage Reduction - Ecosystem Restoration
SCRB Example
Flood Damage Reduction Ecosystem Restoration Total
Average Annual Benefits 1,930 Non-monetary 1,930 Non-monetary
Single Purpose Alternative Cost 2,930 5,350 8,280
Limited Benefits/Costs 1,930 5,350 7,280
Separable Costs 1,650 5,070 6,720
Remaining Benefits 280 280 560
Percent of Total 50 50 100
Joint Costs - - 280
Allocated joint cost 140 140 -
Total allocation 7,000
1,790
5,210
28Other Social Effects(from IPET Report)
- Drowning
- Infection
- Homicide
- Suicide
- Accidents
- Injury
- Illness
- Fraud
29Other Social Effects (OSE) Account
- Communitys Resiliency Social Vulnerability
- Environmental Justice
- Quality of Life Indicators
- Solid academic literature
- Widely used
- Recommended by GAO
- Models
- Hedonic Models
- Loss of Life Estimation
30Regional Economic Development (RED)
- Typically regional economic impacts of a project
can be classified into one of three categories - Direct effects which represent the initial change
of the new expenditure stream on industries in
direct support of the new project. These direct
industries will require support. - Indirect effects are changes in inter-industry
transactions as supplying industries respond to
new demands placed on them by direct
industries. - Induced effects are changes in consumer spending
patterns caused by increases in employment and
income as direct and indirect industries
increase their employment.
31Evaluating RED
- Construction impacts in project area Creates
direct, indirect and induced jobs for local
economy (why not NED Transfers) - Non-NED Flood damage reduction- interruption of
activities due to flood
32Portfolio Management
- Why is this an important project?
- Why is this project more important than other
projects? - In addition to whether a project delivers high
priority outputs successfully meets established
budget criteria - RED and OSE accounts could help answer why
important? - Ex saves x lives, keeps local economy viable
33Measurement challenges that we will need to
think through
- Can OSE and RED be qualitative or quantitative?
- Technical challenges in measuring them
- Need to measure for existing conditions, future
w/ and w/o project conditions - In addition to the difference between w/ and w/o
project conditions, can we distinguish between
alternatives? - Significance of effect influences need to measure
quantitatively
34(No Transcript)