PUMP TESTING
  • BY
  • KAUSTUBH V GITAPATHI
  • DIRECTOR
  • VI AUTOMATION (P) LTD, PUNE

2
Pump Test - Requirement
  • No Load Test
  • High Voltage Test
  • Insulation resistance Measured with 500V DC
  • On Load Test
  • Lock Rotor Test
  • CALCULATED PERFORMANCE AT ACTUAL FREQUENCY
  • Flow
  • Head
  • Pressure
  • Efficiency

3
Pump Test - Parameters Measured3 Phase 0.5HP to
300 HP 1 Phase 0.5HP to 003 HP
  • Voltage
  • Current
  • Resistance
  • Frequency
  • RPM
  • Pressure
  • Flow
  • Leakage Current (HV Test 1.5KV)
  • Insulation Resistance
  • Starting torque
  • Temperature

4
Pump Test - Parameters Controlled
  • Solenoid valve for Lock Test (24 V)

5
Pump Test No Load Test
  • No load tests could be done at the various
    voltages starting from 150V to 450V. The system
    would be programmed to carry out the tests at the
    following voltages.
  • For three phase
  • 150V 200V 250V
  • 300V 350V 400V
  • 415V 450V 1000 v
  • For single phase
  • 140V 160 V 180 V
  • 200V 220V 230 V

6
Pump Test No Load Test
  • The following parameters would be recorded and
    tabulated
  • Voltage
  • Current
  • Power
  • Frequency
  • CW RPM
  • CCW RPM
  • Slip
  • Resistance

7
Pump Test High Voltage Test
  • High voltage test would be carried out by
    connecting 1500V AC across the coils and motor
    body. The leakage current in mA would be
    recorded. An indicator light will glow to
    indicate if the leakage current is at acceptable
    levels. If the current exceeds the limit another
    light will glow indicating failure.

8
Pump Test Insulation resistance Measured with
500V DC
  • The insulation resistance in mega ohms would be
    determined by applying 500V DC across the coils
    and the motor body. The resistance in mega ohms
    will be recorded
  • An indicator light will glow to indicate if the
    resistance is at acceptable levels. If the
    resistance is less than the limit another light
    will glow indicating failure.

9
Pump Test Locked Rotor test
  • The following parameters will be recorded in
    locked rotor condition. The rotor would be
    physically locked during this test.
  • Voltage
  • Current
  • Power

10
Pump Test On Load test
  • Load test will be done by varying the flow rate
    with the help of motorized valve. Tabulated
    readings as well as graphical display of various
    parameters Vs flow rate will be provided. The
    following parameters would be measured and
    displayed graphically as and when required to be
    viewed
  • Current Vs Flow rate
  • Power Vs Flow rate
  • Efficiency Vs Flow rate
  • Pressure Vs Flow rate

11
Pump Test Parameters Display
  • Resistance RB, YB, RY
  • Pump Type
  • Flow
  • Head
  • Supply Frequency
  • Overall Efficiency
  • NP in KW
  • NM in KW
  • Sp. Gr. Of liquid used for testing.
  • Motor Type
  • Motor Rated Power in KW
  • Frequency, Voltage and Current.

12
Pump Test No Load Parameters Display
  • Voltage
  • Current (Run, Start and Line)
  • CU Loss (Calculated)
  • Power
  • Power CU Loss at No Load (Calculated)

13
Pump Test On Load Parameters Display at Actual
Frequency
  • Current (Run, Start and Line)
  • Power
  • STATOR Input
  • STATUS CU Loss (Calculated)
  • Losses (Mechanical, Iron, CU Loss) (Calculated)
  • Frequency
  • RPM Direct Input from (CW, CCW)

14
Pump Test Sample Report
15
Pump Test Additional Features
  • Interface with company Database
  • Reporting in Company Format
  • Data Sharing on Internet
  • Any customized requirement

16
Pump Test System Components
  • Data Acquisition System
  • Energy Meter
  • Slip- Speed Meter
  • Magnetic Flow Meter
  • Temperature Indicator
  • Head Meter
  • Solenoid Valve

17
Pump Test Additional Information
  • Contact
  • Mr. Kaustubh V Gitapathi (Mb 9850823210)
  • Director
  • VI automation P Limited
  • C/2, Apna Ghar Housing society,
  • Shankarsheth Road, Pune 411041
  • E mail- kaustubh_at_viapl.com
  • Web - www.viapl.com
  • Ph 91 20 64002256/7
  • Fax 91 20 26451554
Write a Comment
User Comments (0)
About PowerShow.com