Title: Comprehensive Pump Testing Challenges
1Comprehensive Pump Testing Challenges
2Purpose
- This presentation will discuss
- Hardships encountered while implementing
comprehensive pump test requirements. - Benefits that may be realized if the
comprehensive pump test (CPT) requirement is
eliminated in favor of a Group A tests conducted
at the same flow rate. - A historical review related to the origin of the
CPT.
3Background
- The requirement to conduct a Comprehensive Pump
Test became mandatory with the NRC endorsement of
the 1995 Edition of the ASME OM Code, including
the 1996 addenda. - Since that time, the NRC has received many
requests for relief, however, not all of these
requests were for the anticipated reason. - The expected request dealt with the
impracticality of performing the test due to the
inability to achieve the desired flow rate. - The unexpected requests revealed that utilities
did not see a corresponding increase in the level
of safety or quality based on the additional
costs associated with the development,
implementation and maintenance of a new test and
procurement of new instruments. - This was based on the fact that most quarterly
Group A tests were already being conducted at the
required CPT flow rate.
4Background
- The various issues associated with the CPT were
brought to the attention of the ASME OM Code
Committee. - The Committee agreed that changes were necessary.
- Revisions to the Code have been proposed, but not
approved. - A White Paper was developed to support the
requested change.
5Background
- What are the issues?
- First, an attempt to understand why the CPT was
developed is necessary. - It must be understood that this is my opinion
only and is based on previous writings and
attendance at OM Code meetings and symposiums
since 1996. - I was not involved with ASME during the time that
the original discussions began during the late
1980s and early 1990s.
6Background
- Papers were presented at the second and third
NRC/ASME symposiums, and a letter was written by
the NRC to the OM Chairman regarding the need
for a design basis test. - These documents cover the late 80s and early 90s.
- The NRC wanted a test that was more effective in
detecting pump degradation and that was capable
of assuring the design basis capability of the
pump. - Essentially, there was concern about the ability
to correlate degradation at minimum flows to the
operability. - The NRC was also concerned about pump damage that
could occur by testing on minimum flow. - Both the NRC and the ASME Working Group felt that
this new test needed to be practical and not task
plant resources. - Because the test was more difficult, it would be
conducted at an infrequent interval. - It was decided that there was an urgent need to
develop a comprehensive pump test. - This test would provide a better evaluation of
pump characteristics at a reduced frequency. - The OM-6 working group agreed to develop a CPT
meeting the stated objectives. - With this understanding, the NRC accepted the
expanded upper hydraulic range from 3 to 10.
The expanded limits were introduced in OM-6.
7CPT Challenges
- As the CPT was being developed, ways to improve
the test were reviewed and it was discovered that
the only practical instrumentation improvements
that could be made was associated with pressure
(differential pressure). - Requirement was reduced from 2 to 1/2.
- The hydraulic requirement was changed to require
that the pump be operated at or near design flow. - Due to the hardship involved with installation of
more accurate test instruments, the test would be
performed during shutdown conditions.
8CPT Challenges
- Positives and Negatives associated with the CPT.
- Positives
- Testing at Design Flow makes it easier to
determine the operability of a pump when
degradation occurs. - More accurate pressure instrument results in more
margin. - A more accurate pressure gage reduces the amount
of error included in development of the minimum
performance requirement. - Typically, the accident performance requirement
is artificially elevated to incorporate the error
associated with the test instruments.
9CPT Negatives
- Cost
- Plant modifications or processing of relief
requests will be needed if the required test flow
cannot be achieved. - Potential reduction in safety system availability
- Due to small hydraulic improvements.
- Potential to increase dose and maintenance costs
- Due to small hydraulic improvements.
- Increased procurement, implementation and
maintenance costs - More accurate pressure devices cost more.
- Additional procedures are necessary.
- More engineering work will be necessary.
10CPT Negatives
- Potential for testing with less repeatability
- High accuracy pressure gages cannot be left in
place and must be removed following testing. - Post maintenance test issues
- Related to establishing reference values for the
associated Group A test. - Which test do I run following maintenance?
- More subjectivity
- What is the Engineer supposed to do in the event
that a pump has passed the normally scheduled
Group A test, but would have failed the CPT if it
had been performed?
11CPT Challenges
- It is also important to point out that the
pressure instrument is the ONLY equipment change - This concept is commonly misunderstood.
- Some documents indicate that the CPT requires the
use of more accurate flow instrumentation (ref
NUREG/CP-0152, Vol. 4, page 3A-43). - This position has also been misstated in public
meetings and forums. - In reality, the flow rate, speed and vibration
instrument requirements for a CPT and a Group A
test are identical.
12CPT Challenges
- CPT improvements were limited to
- Requirement to test within 20 of design flow.
- Pressure (differential pressure) gage accuracy
improved to 0.5. - The hydraulic required action limits were reduced
from 1.10 x reference to 1.03 x reference. - Note that this change only involves the upper
required action range. The lower required action
range for all pump types did not change.
13CPT Challenges
- There is no argument that testing a pump at
substantial flow provides a better overall
assessment of both the hydraulic and mechanical
pump condition. - With that understanding, many plants routinely
test their pumps at substantial flow conditions
consistent with the intent of a CPT, when
practical. - Therefore, if the substantial flow condition is
being met, what advantage is there to conducting
a biennial CPT? - The only outstanding differences are the accuracy
of pressure gage and the difference in the upper
acceptance limits.
14CPT Challenges
- Another change that is overstated deals with the
use of the term more restrictive acceptance
criteria. - The fact is that the limits for a CPT are not
more limiting when compared to the Group A test
with respect to degradation. - The lower bounding (required action) limits for a
Group A test and a CPT are IDENTICAL.
15CPT Challenges
- The only hydraulic limit change involves a
reduction from 10 to 3 of reference. - The use of a 3 upper limit may impose a
unwarranted problem for which there is no clear
answer. - With the restricted upper limit, it is quite
possible to easily pass the routine Group A test,
yet find that a CPT would have been unacceptable
due to high flow rate or differential pressure. - This places the engineer in a precarious
position. - Initial guidance regarding this issue suggested
that engineering judgment would apply. - More recent guidance provided at the 2004
NRC/ASME Symposium indicate indicates that the
problem should be resolved prior to the conduct
of the CPT.
16CPT Challenges
- The fact is that there may be no problem to
correct. - A 3 test deviation (or 1.03 x reference) is not
unrealistic given the allowable ranges and
instrument errors associated with an inservice
test. - As previously indicated, the Code instrumentation
requirement for flow rate did not change. - The allowable flow error is 2 of full scale,
with the full scale being limited to three times
the reference value. Under worst case
conditions, this could yield a worst case error
of 6.
17CPT Challenges
- A 6 flow rate error can easily cause a test to
exceed the 3 upper limit. Bear in mind that
other factors have not been considered in this
scenario, such as - Pressure indicator error and the effect of the
performance point on the pump curve - Temperature drift
- Mechanical error contributions (orifice plate,
venturi tolerances, etc.) - Parallax error
- MTE calibration tolerances
- Test data fluctuations
- Meter readability IEEE requirements of ½ the
smallest increment - Allowable variance around the reference point.
18CPT Challenges
- In addition, if a pump fails a CPT due to
exceeding the 3 upper limit, the pump must be
declared inoperable and corrective actions
implemented or the condition evaluated. - The net effect of this action is a reduction in
safety! - Corrective actions will increase maintenance and
operating costs and may introduce unwanted
errors. - Declaring a pump Inoperable as a result of an
improved hydraulic condition is a very
difficult requirement to implement. - Given the fact that many IST pumps may DEGRADE at
least 7 before actions are required, and
centrifugal pumps can degrade by as much as 10.
19CPT Challenges The 3 upper limit
- There is no rational explanation as to why the
Code would require a more critical assessment of
pump performance due to elevated flow or
pressure. - Excessive pump improvement can be indicative of a
potential problem however, these cases are
extremely rare. - Trending of pump performance (increasing or
decreasing) is now a requirement of the Code. - The 3 upper limit was in place up until the
adaptation of the 1988 ASME OM Code edition, at
which point the upper hydraulic limit was
increased from 3 to 10. - To supplement this change, a white paper was
developed and discussed the changes and the basis
for these changes.
20CPT Challenges The 3 upper limit
- With regard to the elimination of the 3 upper
hydraulic limit, the discussion centered on the
fact that more emphasis was being placed on
vibration measurement as the primary indicator of
pump degradation. This was based on measuring
vibration in velocity mode (inches/sec), vice
displacement (mils). - This change was brought about because there was
concern relative to the ability to detect a
change in pump performance based on hydraulic
parameters. - Consequently, it was determined that vibration
measurement (using the new method) would be more
sensitive to changes in pump performance. - It was stated that use of this technology would
reduce the number of pumps requiring increased
testing or corrective action based on erroneous
(hydraulic) test results.
21CPT Challenges The 3 upper limit
- Thus, the extent of the change was to allow
equipment to be run in a window hydraulically
and then to evaluate pump performance more
closely with vibration. - The window serves two purposes.
- First, it ensures that the pump is performing its
primary function of pumping liquid and - Operated in a narrow band where the vibration
data will be repeatable. - It was also recognized that positive displacement
and vertical line shaft pumps could not be
treated the same as centrifugal pumps. Thus, the
hydraulic limits for degradation were not changed
for these pump types.
22CPT Challenges The 3 upper limit
- The 3 upper limit was re-instated in the 95
edition of the OM Code. - It has been published that the reduced upper
limit ensures that the test results are not
impacted by erroneous instrumentation.
23CPT Challenges
- The goal with the development of a CPT was to
establish a more thorough and vigorous biennial
test supplemented with less rigorous quarterly
tests. - However, if a Group A test is performed at the
CPT flow rate, only the Group B pump test, by
eliminating the requirement to measure vibration,
would qualify as a less rigorous test. - The Group B pump population is small.
- Pumps that are operated only to implement IST
requirements for periodic testing.
24CPT Challenges
- It is commonly stated that the CPT is a more
rigorous test that is supplemented with a
periodic Group A or B test using more relaxed
acceptance limits and less rigorous requirements.
In reality - The Group A and B test hydraulic acceptance
limits for Operability DID NOT change from the
previous edition of the Code. - The Group A test mechanical acceptance limits for
Operability DID NOT change from the previous Code
edition.
25CPT Challenges
- The only pumps subjected to less rigorous testing
were the Group B pumps by eliminating the
requirement to measure vibration at a quarterly
interval. - The instrument accuracy requirements for flow
rate, speed and vibration DID NOT change. - All pumps were now required to be tested at
design flow by development of the CPT. - This alleviates previous concerns related to
correlation of minimum flow test results to
design basis capability. Specifically, the
effect of various degradation mechanisms on the
shape of the curve could not be predicted.
26CPT Challenges Pressure indication
- The pressure (differential pressure) instrument
accuracy was reduced from 2 to ½. - The basis for this change was to provide more
accurate reference values. - It was published that the instrumentation
requirements were identical to those established
for the preservice test. - As a result, it would be easier to detect
degradation during subsequent tests based on the
fact that you would be comparing pump performance
using the same instrumentation and reference
point that was established during the preservice
test. - It has been stated that another driving force
behind the ½ gage was due to the fact that the
test was only conducted every two years. - Does the improved pressure instrument accuracy
provide better long term trending capability? - In my opinion
- NO!
27CPT Challenges Pressure indication
- Heres why?
- Repeatability Trend capability
- Sensitivity
- Actual accuracy
- A more accurate pressure instrument may yield
less positive attributes with respect to
repeatability. - The gages are more sensitive and prone to failure
if left in service therefore, are removed and
transported to and from the test site. - The gage is then installed, vented and zeroed
(for many test gages) prior to use. - Interpretation of the result may also lead to
inconsistencies as a result of the increased
sensitivity of the device, which would tend to
result in more active needle oscillations,
forcing the reader to employ averaging techniques
if the oscillations cannot be dampened. - The increased sensitivity also increases the risk
of impacting the calibration of the instrument
due to physical agitation when in transit,
installed or removed.
28CPT Challenges Pressure indication
- This could result in a calibrated gage appearing
uncalibrated, or vice versa. - In short, a test using a more rugged, permanently
installed gage may offer better long term trend
capability when compared to the more accurate,
but less rugged test gage. - Realized accuracy
- Although installed gages are certified to an
accuracy of 2, I have found that they are
actually accurate to at least ½ based on a
review of as-found calibrations and discussion
with our IC department. - In fact, we are looking at increasing our
calibration interval based on the success of our
as-found calibration checks. - It would be interesting to see if a review of
industry calibration records yield a similar
result.
29CPT Challenges - Summary
- Implementation of the CPT requirements may
produce unwanted outcomes for those utilities
that already meet the primary intent of a CPT by
testing their pumps at design flow. - When you update your program and begin
implementing the CPT requirements, you can expect
the following - Challenges from the plant staff (Operations,
Maintenance, Procedures, Management) regarding
the value of this additional test. - Additional workload associated with maintaining
and updating two sets of reference values and
assignment of post maintenance test requirements.
- Emergent work and reduced safety system
availability At RNP, the upper acceptance limit
has been exceeded on two occasions. This
required that pumps be taken out of service. See
bullet 1 for additional effects. - Budget for additional cost RNP spent
approximately 22,000 on new pressure gages. - NRC denial of your proposed request to use the
Group A test at the CPT flow rate in lieu of the
CPT.
30CPT Challenges - Summary
- It is my belief that a quarterly Group A test
conducted at the CPT flow rate is more effective
in evaluating pump performance and detecting
degradation compared to the conduct of a CPT at a
biennial interval supplemented with a quarterly
test at a lower flow rate. - The pump is tested to an identical hydraulic
load. - Vibration, flow rate and speed instrumentation
requirements are identical. - The lower bounding hydraulic limits are
identical. - The mechanical limits are identical.
- More frequent testing at higher flow rates (using
the same test equipment) provides a much better
trend capability.
31CPT Challenges - Summary
- If a quarterly test is conducted at the same flow
rate as a CPT, then - The primary concerns related to verification of
operability and detection of degradation are no
longer valid. - This was the primary motive for developing the
CPT. - A test gage is not necessary.
- Since the equivalent test is being performed
quarterly, there would be no need to obtain more
accurate data every two years. - In reality, the more accurate gage may not offer
better accuracy, or repeatability.
32CPT Challenges - Summary
- The reduced upper hydraulic acceptance limit is
not necessary. - Because the equivalent test is performed
quarterly, there is no need to tighten the upper
limit to counter the effects of instrument error. - There is no equivalent criteria for degradation,
which is the prevalent failure mechanism. - You are required to trend performance.
- The improved vibration requirements that resulted
in the previous expansion of the upper limit are
still in place. - The upper criteria could be exceeded due to
normally expected instrument error allowances.
33CPT Challenges - Benefits
- The benefits associated with this proposal are
many. - First and foremost
- Better assessment of overall pump performance.
- Better trend capability.
- Improved ability to detect degradation.
- Reduced capital costs.
- Accurate pressure gages are expensive.
- Reduced OM costs.
- Installation and maintenance of test gages.
- Develop, maintain and update additional
procedures. - Engineering evaluation using two sets of
criteria.
34CPT Challenges - Benefits
- Focus available resources on more urgent matters.
- The industry has been downsized.
- Evaluations, maintenance, etc. should not be
mandated based on small increases in performance
based solely on test data, unless there is a
valid concern supported by additional data (more
tests, vibration data).
35CPT Challenges - Benefits
- Increased safety system availability.
- If the upper limit is exceeded, the pump is
inoperable. - It cannot be returned to service unless
maintenance is conducted or the condition is
evaluated. - New reference values must be established if an
evaluation is used to return a pump to an
operable status. - New reference values established at a higher
value may not be the best long term solution, if
the test result is not typical of normal
performance and is not supported by additional
data.
36CPT Challenges - Conclusion
- The Code should be used as a tool to
- Determine and assess overall pump health.
- Trend performance and take actions prior to
failure. - Ensure operational readiness and provide one of
the key inputs necessary to determine
operability. - A quarterly test conducted at or near design flow
accomplishes these objectives. - Also, a full flow test conducted 8 times over a
two year period compared to one time in a two
year period is far more effective in evaluating
overall pump health, provides better trend
capability, and provides more frequent assurance
of meeting design requirements.
37CPT Challenges - Conclusion
- The Code should not
- Place unwarranted burden upon the utility.
- This was one of the stated objectives when
developing the CPT. - If your Group A tests are being conducted at
design flow rates, then the additional
comprehensive test may be considered a burden. - Bring acceptable test results into question.
- A Group A test that passes at 104 of the
allowable limit will result in questions relative
to operability. - When compared to the CPT limit.
- This tends to lead to passionate debates and is
very difficult to defend. - It is also difficult to tell management that the
pump may have to undergo maintenance to ensure
that it passes the next scheduled test.
38CPT Challenges - Conclusion