Title: Climate change: Meeting the challenge of flood risk
1Climate changeMeeting the challenge of flood
risk
- James Sharp - Pellings LLP
- Planning Flood Risk
- Alan Fogarty - Cundall
- Flood Risk Assessments
- Peter Wade - Pellings LLP
- Flooding Why we should care and what we can do
2James Sharp
3Planning and flood risk
- 2007 The Year of the Flood
- 13 killed in Northern and Western England
- 48,000 homes and 7,000 businesses inundated
- Massive disruption and financial losses
4Assessment of flood risk
5Types of flooding
- Flooding from rivers
- Flooding from the sea
- Flooding from land
- Flooding from ground water
- Flooding from sewers
- Flooding from reservoirs, canals, and other
artificial sources
66 of homes flooded in summer 2007 occurred from
surface water drains, culverts and sewers
6(No Transcript)
7PPS25 Development and flood risk
- Key Objectives
- Appraising Risk
- Managing Risk
- Reducing Risk
8Key features of PPS25 are as follows
- A strategic, plan led focus with more front
loading of flood risk - More attention to flooding from sources other
than rivers and the sea - Formalisation of regional flood risk appraisals
and strategic flood risk assessments,
contributing to sustainability appraisals and
soundness tests - A stronger sequential approach to allocating land
and granting permission in areas at risk of
flooding
9Key features of PPS25 are as follows
- Introduction of vulnerability classes for
different types of development - Climate change allowances based on the UK climate
impact programme 2002 projections to provide a
quantifiable measure for developers and planners - A new Exception Test where development in flood
zones is needed for wider sustainability reasons - A focus on the consequences as well as the
probability of flooding, because the schemes have
to be safe over their life time taking climate
change into account
10Flood zones
- Zone 1 Low probability
- Less than in 1,000 annual probability of river or
sea flooding in any year - Zone 2 Medium probability
- Between a 1 in 100 and 1 in 1,000 annual
probability of river flooding or a 1 in 200 and
1 in 1,000 annual probability of sea flooding in
any year - Zone 3a High probability
- 1 in 100 or greater annual probability of river
flooding or 1 in 200 or greater annual
probability of flooding from the sea in any year - Zone 3b The functional flood plain
- Land where water has to flow or be stored at
times of flood
11(No Transcript)
12(No Transcript)
13The Exception Test
- For the Exception Test to be passed
- It must be demonstrated that the development
provides wider sustainability benefits to the
community that outweigh flood risk - The development should be on developable
previously developed land - A FRA must demonstrate that the development will
be safe, without increasing flood risk elsewhere,
and, where possible, will reduce flood risk
overall
14(No Transcript)
15(No Transcript)
16(No Transcript)
17(No Transcript)
18Alan Fogarty
19Flood Risk Assessments
20Introduction
- Introduction
- Flood Risk Assessment
- BREEAM
- SUDS
21PPS 25 Development Flood Risk
- Securing the Future preparing for the climate
- change that cannot now be avoided
- Rising sea levels
- High intensity rainfall
- River flooding
- Flash flooding
22Climate Change
- Rising Sea Level
- Land rising in the North
- Dropping in the South East
23Climate Change UK 2000
24Swiss Alps
200?
1875
25Climate Change Ireland 2000
26Climate Change
- Deeper water increased wave height
- Increased wind speed
- Greater potential for storm surges
27Flooding
- A natural phenomena types
- River
- Sea
- Land
- Rising Groundwater
- Sewers
28Planning Authorities
- Regional and Local authorities should
- Appraise Risk Regional flood risk assessment
- Manage Risk Identify low risk sites and
restrict development in higher risk sites - Reduce Risk Storage, SUDS, Defences
29Testing
- Sequential Test Direct development to sites of
lower risk - Exception Test Where Sequential Test cannot
deliver acceptable sites, but development is
necessary to avoid social or economic blight and
the need for essential civil infrastructure to
remain operation during floods
30Environmental Agency
- The Environment Agency has statutory
responsibility for flood management and defence
in England - Will support the planning system
- Providing timely information and advice on
flooding issues that is fit for purpose
31Environmental Agency Flood Maps
32Planning Flood Risk Assessment
- FRA are required in almost all cases
- Large developments and high risk areas require
direct discussions with EA - Otherwise directly with the LPA
33EA Flood Zones
34Purpose of Flood Risk Assessment
- Identify whether site at risk from current or
future flooding - Demonstrate that the site is safe and reduces
overall flood risk - Identify any flood risk elsewhere
- Mitigation
35Methodology of Flood Risk Assessment
- Conduct a background search including
consultation with EA Local Authority or other
potential sources of data. - Review topographic survey of the site and
proposed site layouts in relation to the
potential flood risks and procure additional
survey as required. - For surface water drainage, assess the existing
and proposed surface water runoff from the site
based on proposed layouts. - For fluvial flood risk build a mathematical
hydraulic model of to confirm the extent of the
flood risk. - Attend project meetings to discuss the
development of an outline drainage scheme. - Assess all other potential sources of flood
risk-such as overland flow and groundwater
flooding. - Advise the design team on issues that may affect
the acceptability of the scheme to the
Environment Agency and Local Authority. - Agree mitigation measures through
discussions/meetings with the Environment Agency. - Prepare a flood risk assessment report to submit
with the planning application to the Local
Authority. A discussion of mitigation measures to
minimise the flood risks will be included in the
report.
36EA Flood Zones
- Zone 1 Low Probability site not at risk from
flooding from adjacent watercourses or marine
tides. Suitable for all development types. - Zone 2 Medium Probability site lies within
the floodplain of the extreme flood event. Not
suitable for police/fire stations, basement
dwellings, permanent caravan parks. - Zone 3 High Probability A site lies within
the floodplain of the 1 probability event.
Water compatible and essential infrastructure.
37EA Flood Zones
- Zone 1 the primary flood risk is to others by
surface water runoff - Mitigation EA
- Encourages SUDS
- On-site attenuation of the 100 year event
- Run off rate green field site
38EA Flood Zones
- Zone 2 3 on and off site risk
- Mitigation EA
- No habitable spaces below 1 flood level
- Occupants must be able to evacuate safely
- Developments should not obstruct flood waters or
reduce flood plane storage
39EA Flood Zones
40BREEAM
- 2 Credits in a zone with low annual probability
of flooding or - 1 Credit in a zone of medium annual probability
of flooding and the ground level, car parking and
access is above the design flood level
1.5 .75
41BREEAM
- 1 Credit Sustainable Urban Drainage attenuate
50 of the peak flow rate to natural watercourses
or municipal drainage systems, in Zone 1 or - 1 Credit Sustainable Urban Drainage attenuate
75 of the peak flow rate to natural watercourses
or municipal drainage systems, in Zone 2 or - 1 Credit Sustainable Urban Drainage attenuate
100 of the peak flow rate to natural
watercourses or municipal drainage systems, in
Zone 3
1.5
No credit awarded if development has proceeded
against the recommendation of the relevant flood
defence agency
42Mitigation Traditional Drainage Problems
- Designed to move rainwater rapidly to either a
watercourse or soak away - Hard surface run-off increase the risk of
flooding downstream, as well as speed - Surface water run-off can contain contaminants
such as oil, affecting biodiversity and potential
use - Diverting rainfall to piped systems, depletes
ground water in dry weather
43Mitigation SUDS
- Sustainable Urban Drainage Systems
- Reduce the potential of flooding on new and
existing developments - Helps to protect and enhance ground water quality
44Mitigation SUDS
Permeable Pavement
45Mitigation SUDS
Surface Water retention filtration
46Mitigation SUDS
Attenuation Tanks
47Summary
- Increased Planning complexity
- Early consultation with EA
- Early consultation with Local Planners
48Peter Wade
- Flooding Why we should care and what we can do
49(No Transcript)
50(No Transcript)
51(No Transcript)
52(No Transcript)
53(No Transcript)
54(No Transcript)
55(No Transcript)
56(No Transcript)
57Facts and Figures
- 1 in 3 new homes will be built on floodplains
- Two million homes are at risk 1 in 10
- 200,000 homes are at very high risk
- 160,000 businesses are at risk
- The average annual damage from flooding is
currently 1 billion. This could increase to 20
billion if we take no effective action - Risks from weather are increasing by 2.4 per
year on ABI evidence
58Facts and Figures
- Sea levels are rising by 3.1mm per year
- High water in London has risen by 0.8 metre per
century - Global mean sea level has risen about 0.22 metre
per century. With global warming this could
become 0.33 metre - Last years floods led to 55,000 homes being
flooded and the damage costing 3 billion.
Average claims were 20,000 per property
59What can be done?
- A new Thames Barrier is planned along with
improvements to flood defences - The new Thames Tideway Tunnel is planned to
assist with sewer surcharge - Owners of properties should carry out audits to
establish which ones are at risk - Owners should undertake physical measures where
possible such as moving equipment out of basement
areas, installing electronic warning devices and
having temporary barriers, airbrick covers etc
ready in the event of imminent flooding
60What can be done?
- New buildings should be designed to cope with
flooding - Elements of both existing and new buildings can
be designed to be more resilient to flood waters
such as use of render plaster, keeping electrics
above flood levels and making basement and ground
storeys watertight where possible - In the event of imminent flooding, valuable or
essential items should be moved away from the
flood risk areas - Take a photographic record of the existing
condition of the property particularly where
historic buildings are involved
61What can be done?
- Prepare a flood plan and ensure all occupiers
know what to do and agree evacuation routes - If flooding is likely, turn off electrical power
and gas supplies - Avoid moving in flood water as it is nearly
always contaminated. Following a flood,
sterilisation of internal areas is important and
power supplies should be checked before being
re-connected - Check with the Environmental Health Department
whether contaminants are likely to be present - Soil beneath timber floors may need to be
completely removed if contaminated
62What can be done?
- With historic buildings special care is needed
and consent may be required to replace damaged
timber and plaster finishes - Dry out buildings slowly or else historic
features could be damaged. Where possible use low
background heating, natural ventilation and
dehumidifiers - With new buildings, minimise the use of hard
landscaping to avoid excessive run-off and
surcharging of drains - With new drainage installations in vulnerable
areas, install one-way valves and ensure drainage
connections can be turned-off if surcharging is
likely
63What can be done?
- Check all drains following a flood as silt and
debris can cause blockages - Monitor timber for evidence of fungi and rot for
at least six months after a flood - Some defects will only become apparent many
months after the building has dried out
64(No Transcript)
65(No Transcript)
66(No Transcript)
67 68 69(No Transcript)
70(No Transcript)
71(No Transcript)
72The Thames Barrier
- It was 1922 when central London last flooded
killing 14 people and causing widespread damage - 1953 was a major wake-up call. A storm surge
caused 300 deaths and this largely affected the
lower parts of the Thames - The barrier was designed in the 1970s when sea
levels were rising by 1.8mm per year. Levels are
now rising by 3.1mm per year - The barrier opened in 1984 at a cost of around
500 million - The barrier is designed to cope with 8mm of sea
rise per year and should cope with a 1 in 1,000
year storm surge up to 2030
73The Thames Barrier
- A new barrier is currently being planned as the
predictions are worsening - Current climate predictions are optimistic and it
is thought that by 2030 the current barrier may
not be able to cope - Much depends on the rate of melting of the
Greenland and Antarctic ice sheets. Latest
evidence shows these to be melting at an alarming
rate - It could take 20 years to design and construct a
new barrier and associated flood defences
74(No Transcript)
75(No Transcript)
76Thames Tideway Tunnel
- In 2006 the Minister of State for Climate Change
and the Environment approached Thames Water to
look at ways of tackling Londons sewer
overflows. This was following recent discharges
of raw sewage directly into the River Thames.
This is a regular occurrence - Thames Water produced two options, the most
likely one being the construction of a 30km long
tunnel beneath the Thames - This tunnel will be 7 metres in diameter and the
work will also include improvements to the
Beckton Sewage Works and other major sewers - The latest estimated cost is 1.7 billion
77Thames Tideway Tunnel
- The work will be subject to a Public Enquiry and
the purchasing of land - It is likely that the work will take up to 13
years to complete and there is a need to complete
some of the work in time for the Olympics - At the present rate, the work could add up to 50
to each of Thames Waters customers annual bills - In addition to reducing raw sewage discharge into
the Thames, it is hoped that surcharging of
secondary sewers throughout London will be
alleviated. This risk increases with increased
development - Remember that last year 66 of homes flooded was
due to drain and sewer surcharges
78(No Transcript)
79Sources of Information
- The following websites are useful sources
- Environment Agency www.environment-agency.gov.uk
- Environment Agency postcode search facility
www.environment-agency.gov.uk/subjects/flood - Thames Water www.thames-water.com
- English Heritage www.english-heritage.org.uk
(use search box for the Technical Advice Notes) - Association of British Insurers www.abi.org.uk
- In addition the internet is an excellent source
of flood prevention productswww.aquatitesystems.
com, www.floodark.co.uk, www.floodguards.com,
www.floodgate.ltd.com
80(No Transcript)