Title: Transportation Concurrency Workshop
1Transportation Concurrency Workshop
- Pasco County, Florida
- September 19, 2006
Prepared by Tindale-Oliver Associates, Inc.
COPR Tindale-Oliver and Associates, Inc. 09/19/06
2Overview
- Discussion topics
- What Concurrency is
- Recent Amendments to Concurrency law -- Chap 163,
FS (SB 360) - LDC Amendments by December 1, 2006
- Changes to Pascos Concurrency Process
- Proportionate-Share Mitigation
3Concurrency
- transportation facilities needed to serve new
development shall be in place or under actual
construction within 3 years after the local
government approves a building permit or its
functional equivalent that results in traffic
generation. (F.S.163.3180(2)(c))
4Concurrency
- Based on roadway capacity and level of service
- Different from access management, substandard
roads, and corridor preservation
5SB 360 Amendments
- SB 360 Mandates
- Financial feasibility sufficient revenues are
currently, or will be available to fund the
capital improvements necessary to ensure that
adopted level of service standards are achieved
and maintainedwithinthe five-year schedule of
capital improvements. (F.S. 163.3164 (32))
62003 vs 2006Capacity Funding Plan
2003
2006
1. Does not cure all deficiencies
72003 vs 2006Capacity Funding Plan
2015 (per 2004 MPO LRTP Update)
2015 (per 2006 Cost Estimates)
2003
82003 vs 2006Capacity Funding Plan
2003
2006
1. Does not cure all deficiencies 2. Based on
ratio of 2003 estimate and proposed fee schedule
increase of 217 /-
92003 vs 2006Capacity Funding Plan
2015 (per 2004 MPO LRTP Update)
2015 (per 2006 Cost Estimates)
2003
Estimated, and with no impact fee increase.
With proposed IF increase, capacity added would
be 283,300, VMT below std 40, and CI 0.98
10Concurrency Changes
- Redefined LOS Standards
- Removed multipliers
- LOS D
- SIS
- Intersection Criteria
11Concurrency Changes
12Concurrency Changes
- Initial/Final Certificate of Capacity
13Concurrency Changes
- Initial Certificate of Capacity
- At DRI, Zoning, Preliminary Plan/PSP,
non-Residential Subdivision approval - Establish Time Limits on Vesting
- Two years for de minimis developments
- Up to 10 Years for non-DRI traffic
- Up to 15 years for DRI traffic
- 6 Years for all other infrastructure except
drainage
14Concurrency Changes
- Final Certificate of Capacity
- Issued at Residential Plat or Building Permit for
all other - Grants permanent vesting for residential units on
individual lots - Vests, subject to conditions of approval
15SB 360 Amendments
- De Minimis Developments
- No impact will be De Minimis if volumes
would exceed 110 percent of the adopted level
of service of the affected transportation
facility provided however, that an impact of a
single family home on an existing lot will
constitute a De Minimis impact on all roadways
regardless of the level of the deficiency of the
roadway. Further, no impact will be De Minimis if
it would exceed the adopted level-of-service
standard of any affected designated hurricane
evacuation routes.
Critical Roads Almost Critical Roads
16Concurrency Review Process
De Minimis Determination
Subject to optional DeMinimis determination in
Section 402.5.C.4 1. Does not include
Single-Family home on existing lot, which is
concurrency de minimis.
17Concurrency Review Process
- Exemptions
- Portions of projects with COs, Building Permits
and Final Plats - Portions of projects with unexpired concurrency
certificates - Unexpired DRIs
- Unexpired projects that have been through the
Traffic Impact Study and mitigation process
18Concurrency Review Process
- Exemptions (contd)
- Schools that have been through consistency review
or preliminary plan/construction plan approval - DRIs and other projects with approved and
unexpired transportation methodology statements - Some exemptions can expire or be revoked under
certain conditions outlined in the Ordinance
19Concurrency Review Process
- Limited Exemptions--Exempt from Portions of
Regulations More Stringent than State Law - Affordable Housing Providers
- Target Industries and Office/Industrial Uses in
Employment Centers - Transit Oriented Design (TOD)/Traditional
Neighborhood Design (TND) Projects - Public Schools and other Governmental Uses
20Concurrency Review Process
- Examples of Ordinance Allowances for Limited
Exemption Uses -
- Can utilize first 3 years of committed roadway
capacity (instead of 1) - Administrative extension of vesting periods
without additional review - Not subject to County Traffic Study requirements,
regardless of de minimis thresholds - Payment of proportionate share only for lt110
percent roadways and lt100 percent hurricane
evacuation roadways - Payment of impact fees or non-TIS proportionate
share in lieu of TIS proportionate share - County shall make cure of deficient
transportation facilities for such uses a
priority in the CIE/CIP
21Concurrency Changes
- Developed Uniform Traffic Study Procedures
- Adopt by resolution
- Sets forth consistent study technical procedures
22Concurrency Changes
- Reduced Period of Committed Improvements to One
Year
23Concurrency Changes
- Defined Impact Mitigation Options
- Restore LOS standard
- Proportionate share mitigation
- Eliminates Alternate Location mitigation and
Equal Mitigation that does not restore LOS
standard
24SB 360
- Proportionate Share
- Traffic concurrency is met if all mitigation is
in 5-yr CIE and developer pays proportionate
share. (F.S. 163.3180(16)(b)1.) - Local option to accept a proportionate
share-based improvement as mitigation if all
mitigation is not in 5-yr CIE, but full
improvement to restore LOS must be in 10-year
CIE. (F.S. 163.3180(16)(f))
25Proportionate Share
- Requirement
- Agencies must have remainder of restore LOS
standard improvement funded in 10-year CIE
26Concurrency Changes
TIS Process
Are Needed Improve-ments in CIE?
Is LOS on all roads OK?
Will agency fund cure (beyond prop share)?
Do TIS Study
No
No
No
No
Yes
Yes
Yes
Developer Must Restore Adopted LOS
Developer right to pay prop share and go
No concurrency mitigation
Assess Prop Share, and put restore LOS
improvement in CIE
No
27Proportionate Share
- General form of equation
- Sum of
- Development Trips x Length x Unit Cost
- Change in Capacity
- for significantly impacted locations
28Proportionate Share Example
Office 80,000 sf 1,000 trips
Capacity Capacity Consumed Improvement
Needed Capacity Added Cost Proportionate
Share Cost per s.f.
10,000 vpd 8 (800/10,000) Add 2 lanes 14,000
vpd 4 million (800/14,000)4 mil.
228,571 2.86
10,000 vpd 4 (400/10,000) No further
consideration
29Proportionate Share Example
Office 160,000 sf 2,000 trips
600
200
1,600
400
800
400
200
200
Capacity Capacity Consumed Improvement
Needed Capacity Added Cost Proportionate
Share Total Proportionate Share Cost per
s.f.
10,000 vpd 16 (1,600/10,000) Add 2
lanes 14,000 vpd 4 million (1,600/14,000)4
mil. 457,143
10,000 vpd 8 (800/10,000) Add 2 lanes 14,000
vpd 4 million (800/14,000)4 mil. 228,571
685,714 4.29
30Proportionate Share
- Relationship to Impact Fee
- Prop share addresses concurrency
- Timing of development
- Network condition
- Impact significance test
- Impact fee addresses capacity consumed
- Insensitive to above
- Provides for Proportionate Share credits
31Proportionate Share
- 40 unit, Single-Family Subdivision
- On SR 54 CR 581 to CR 577
- 492,705 (2.3 mi, 1,982/vmc)
- On CR 54 SR 56 to Magnolia
- 786,145 (3.25 mi, 1,584/vmc)
- On US 19
- 97,551 (3.3 mi, 222/vmc)
- Impact Fee 167,160 491,320
-
(Current) (Proposed) - US 19 Fair Share Fee 43,320
32Proportionate Share
Prop Share can typically range from 0 to 250 of
full Impact Fee
33Relation of CIP/CIE and DeMinimis Reporting Tasks
Develop 07-08 CIP/CIE based on 5-year LOS
assessment
CIP/CIE Development
Preliminary 5-year LOS Assessment
Adopt CIP/CIE with final future LOS projection
Transmit to DCA
Monitor DeMinimis Developments for
2007 (Year-Round)
Monitor DeMinimis Developments for
2008 (Year-Round)
DeMinimis Reporting
Report 2007 Critical Facilities and DeMinimis
developments to DCA
Identify Critical Facilities for 2008
Identify Critical Facilities for 2007
December2006
October 2007
December2007
October 2006
34Relation of CIP/CIE and DeMinimis Reporting Tasks
Develop 07-08 CIP/CIE based on 5-year LOS
assessment
CIP/CIE Development
Preliminary 5-year LOS Assessment
Adopt CIP/CIE with final future LOS projection
Transmit to DCA
Monitor DeMinimis Developments for
2007 (Year-Round)
Monitor DeMinimis Developments for
2008 (Year-Round)
DeMinimis Reporting
Report 2007 Critical Facilities and DeMinimis
developments to DCA
Identify Critical Facilities for 2008
Identify Critical Facilities for 2007
December2006
October 2007
December2007
October 2006
35Relation of CIP/CIE and DeMinimis Reporting Tasks
Develop 07-08 CIP/CIE based on 5-year LOS
assessment
CIP/CIE Development
Preliminary 5-year LOS Assessment
Adopt CIP/CIE with final future LOS projection
Transmit to DCA
Monitor DeMinimis Developments for
2007 (Year-Round)
Monitor DeMinimis Developments for
2008 (Year-Round)
DeMinimis Reporting
- Consider alternative planning strategies, e.g.
- Transit service
- Alternative LOS standard
- Long-term congestion management
- Bike and pedestrian mobility
- TCEA
- TCMA
- Additional funding
Report 2007 Critical Facilities and DeMinimis
developments to DCA
Identify Critical Facilities for 2008
Identify Critical Facilities for 2007
December2006
October 2007
December2007
October 2006
36Long-Term Concurrency
- Long-Term Concurrency Option
- Extends horizon of developer right to
proportionate share mitigation - Of questionable value if funding remains in
deficient mode - Needed if funding to cure is beyond 10 years?
37Adoption Schedule
- 9/18 BOCC Workshop
- 9/26 Introduction
- 10/4 CORC
- 10/19 PBA
- 10/24 First Reading (NPR)
- 11/8 Second Reading (DC)
- 12/1 Statutory Deadline for Adoption
38 39Proportionate Share
- General form of equation
- Sum of
- Development Trips x Length x Unit Cost
- Change in Capacity
- for significantly impacted locations
40Proportionate Share
- General form of Impact Fee equation
- Devmt Trips x Length x Unit Cost
- 2 x Change in
Capacity
(
)
41Concurrency Changes
- Application to Parent Tract
- Modified mitigation of Phased developments
42Mitigation Policies
- Developer Questions
- Whats required for concurrency?
- How much to pay or build up front?
- What is my maximum cash out-of-pocket
- What is the end-game out-of-pocket?
- If I pay beyond Impact Fee or Prop Share will I
get reimbused? - If so, how much?
- If so, when?
43Practical Considerations
Example for Discussion
0.85
1.20
1.40
44Concurrency Process
Trips gt 600?
Trips gt 1,200?
Estimate Trips Generated
Start
Yes
Yes
Enter TIS Process
No
No
On gt 90 Road?
On Critical Road?
Yes
No
Yes
No
Pay Generalized Proportionate Share
Pay Normal Fee And Go (OR do Optional study)
A Critical Road is a Hurricane Evacuation Route
where volume gt capacity or any other Regulated
Road where volume gt 110 of capacity.
452003 Critical and Near-Critical Roads
46Mitigation Policies